Resolved
RESOLVED – to approve the allocation of the Commercial Services Initiative reserve fund of £55K to be identified as match funding to encourage funding bids to other bodies for the Parkend to Lydney multi-use track.
Cabinet approved this item on Thursday 11 December 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – to approve the allocation of the Commercial Services Initiative reserve fund of £55K to be identified as match funding to encourage funding bids to other bodies for the Parkend to Lydney multi-use track.
CABINET December 2014 CSW.35 Subject PARKEND TO LYDNEY MULTI-USE TRACK – ALLOCATION OF THE COMMERCIAL SERVICES INITIATIVES RESERVE Key Decision This is a key decision Accountable Councillor Patrick Molyneux – Cabinet member for Regeneration member Telephone: 01594 529174 email: [email protected] Accountable officer Paula Burrows – Commercial Manager - Customer Services Tel: 01594 812389 email: [email protected] Summary Since 2002 the local community and several organisations have expressed a desire for a multi-use off road track to link Parkend to Lydney, the main benefits would be: • Connecting local communities • Be a safe commuter link • Many leisure and tourism uses for both walkers and cyclists • A key link connecting the rivers Wye and Severn • Positive economic impact • Addresses air pollution issue in Lydney In 2006 a feasibility study was undertaken, however the proposed route was not acceptable and therefore the project remained on hold until 2013 when the Forest of Dean District Council and the Forestry Commission agreed to re-visit the project to try and identify an alternative route. This has been achieved. In 2006 approval was granted for a fund of £55k to be placed in reserves to support a Canopy Walkway. This project was negated by the introduction of the private enterprise Go Ape! The reserve has been held in abeyance for a project that would benefit the local community, visitors and the economy. This report recommends use of the reserve as match funding towards a multi-use track kick starting the project.
Annexes A. Map of the route
Recommendations Cabinet is recommended to: Approve the allocation of the Commercial Services Initiative reserve fund of £55k to be identified as match funding to encourage funding bids to other bodies for the Parkend to Lydney multi-use track Corporate priorities Encourage a thriving economy: • Working with partners to attract investment to support the local economy Implications (details at end of LEGAL FINANCIAL RISK EQUALITIES SUSTAINABILITY report) NO YES NO YES YES
1. REASONS FOR RECOMMENDATIONS 1.1. The perceived overall cost of the project is around £600k to complete a 5.2 kilometre multi-use track between Parkend and Lydney, a sum that will require funding from a variety of sources. Approval will enable funding bids to be submitted to relevant bodies and lead the way to encouraging other funding opportunities
2. BACKGROUND Multi-Use Track 2.1. As far back as 2002 the local community have expressed a desire for a track to connect Parkend to Lydney for use as a safe commuter link that would enable users to travel safely on foot or bike 2.2. In 2006 a feasibility study was commissioned by the Forest of Dean District Council. Sustrans completed the report, however the route was never approved due agreement not being reached with one of the land owners which continued into 2013 2.3. The route had to be ‘family friendly’ and a suitable alternative has never been identified since placing the project on hold indefinitely £55k Reserve Budget 2.4. Also in 2006 a feasibility study was commissioned by the Forest of Dean District Council for a tourism attraction of a Canopy Walkway. The Tourism Company completed the report and the Forest of Dean District Council allocated a budget of £55k to support the project 2.5. The Canopy Walkway project never got off the ground due to a lack of other investment being available. Since then the desire for such an attraction has declined, particularly with the growth of Go Ape! 2.6. The reserve has been held in abeyance since then until a project that would benefit the local community, visitors and the economy was proposed
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Commercial Services Initiatives Reserve: Parkend to Lydney cyclewayReport | 120 KB | DownloadRead as text |
PDF |
Scanned from a Xerox Multifunction DeviceReport | 143 KB | Download |
Follow Cabinet at Forest of Dean and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Sep 2026 | Introduction of James watch to Forest Linkline & Cotswold Careline product rangeResolved , that Cabinet: 1. Approves the introduction of the James Watch service within Forest Linkline and Cotswold ... | Approved | Open |
| 10 Sep 2026 | Health and Safety PoliciesResolved , that Cabinet; 1. Approves the implementation of the attached Health and Safety Delegated Responsibility Fr... | Approved | Open |
| 10 Sep 2026 | Quarter Performance Report - Period OneResolved, that Cabinet: 1. Notes overall progress on the Council priorities and service performance for 2026-27 Q1. A... | Agreed | Open |
| 10 Sep 2026 | Financial Performance Report - Period OneResolved, that Cabinet; 1. Notes the 2026-27 Quarter One Financial Performance report and, 2. That the Business Rates... | Agreed | Open |
| 9 Jul 2026 | Conservation Areas SWOT Analysis: Explorer Hubs and Summary SheetsResolved, that Cabinet: Noted the value of the analysis undertaken and support its appropriate use and application in... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.