It was agreed that information regarding rent reviews would be circulated to members of the sub committee following this meeting. Cllr Burford proposed that a report be submitted to the next meeting providing further information on value for money, comparisons, rent reviews, professional fees, what other quotes were received and why this scheme was selected. This was seconded by Cllr Evans. The ... view the full minutes text for item 5.
Word for word from the decision Forest of Dean published for this meeting.Source: meetings.fdean.gov.uk
PERFORMANCE AND VALUE FOR MONEY SCRUTINY SUB COMMITTEE
Priority 3 – Encourage a Thriving Economy
An action from the meeting on 16 November 2015 requested a report on the details and costings of the Bat Roosts and relocation of the Great Crested Newts in the Cinderford Northern Quarter be brought back to the next meeting of this Sub Committee.
1. Replacement Bat Roosts
As outlined in the Cabinet report 19.09.13, the redevelopment of the Northern United (NU) site will result in the loss of two bat roosts in the former colliery buildings which are beyond repair. Existing planning approval for the NU site requires the replacement of the two existing roosts, prior to full demolition and site clearance. Furthermore, demolition cannot take place until a replacement roost is shown to have a minimum of 15 Lesser Horseshoe Bats (LHB) at any one time and a minimum of 50 LHB’s clustering between April & August in any one year.
Planning permission for the construction of two new replacement bat roosts was secured without any legal challenge and the District Council led a project team in 2014/15 to build the new roosts. The Council appointed a project architect, structural engineer, archaeologist, specialist bat advisor and CDM Co-ordinator. The Homes & communities Agency (HCA) appointed TACP to provide ecological expertise to oversee all EPS/NLMS licensing issues with Natural England and to supervise the site clearance and construction works.
Construction costs including professional fees and annual revenue costs breakdown as follows:
CAPITAL EXPENDITURE • Construction works = £181,030 • Professional fees = £30,939 • Forestry compensation payment = £4,100 TOTAL = £216,069 (HCA funded)
REVENUE EXPENDITURE • Annual rent = £900 (50 year lease with Forestry Commission) • Utilities = £300 • Building insurance = £300 TOTAL = £1,500 per annum (FoDDC funded) 2. Great Crested Newts (GCN) Trapping & Translocation
The HCA appointed the ecology team, fencing contractors and site security to undertake the trapping and translocation of GCN and all other amphibian & reptilian species from both the spine road and college development sites and their associated ecological mitigation site. Following a request for the details & costings associated with these various contracts of work, the HCA has provided the following information:
Translocated Species Numbers
317 Great Crested Newts 10,555 Smooth/Palmate Newts 2,284 Common Frogs/Toads 1,585 Common Lizards 640 Slow Worms 54 Grass Snakes 6 Adders 1 Dormouse
Total Species: 15,442 (This number does not include destructive search numbers, but they are not significant numbers)
Costs associated with the GCN Translocation
Ecovigour Ltd (Phase 1 contract) £542,000 (at least 2/3 of the cost covers fencing & materials)
Quarter Performance Report - period 3It was agreed that a short report be presented to the next meeting outlining the package that is being offered and th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.