- That the Cabinet:- a) Takes a phased, risk based approach to reopening leisure facilities, to manage the financial impact on the Council and therefore instructs Freedom Leisure to open on the 12 th of April 2021 or whenever Government Guidelines allow. b) Agrees to subsidise Freedom Leisure up to a maximum of £596,744 for financial year 2021/2022. This is seen as the worst case cost scenario. c) Delegates authority for final terms of the agreement with Freedom Leisure, in line with the decision made in a) and b) above to the Head of Paid Service in consultation with the Cabinet Member for Communities. d) Delegates monthly review process to S151 Officer along with Group Manager – Commissioning, all variances to be reported to Cabinet through Quarterly Performance report.
Word for word from the decision Forest of Dean published for this meeting.Source: meetings.fdean.gov.uk
Summary/Purpose To decide when leisure centres should reopen, which centres and facilities should reopen and to agree the associated subsidy to enable the sustained provision of leisure facilities.
Annexes EXEMPT - Annex A – Best and Worst case options Annex B – reopening timetable EXEMPT - Annex C - Legal advice as per Aug-20 paper
Recommendations That the Cabinet; (a) Takes a phased, risk based approach to reopening leisure facilities, to manage the financial impact on the Council and therefore instructs Freedom Leisure to open on the 12th of April 2021 or whenever Government Guidelines allow. (b) Agrees to subsidise Freedom Leisure up to a maximum of £596,744 for financial year 2021 / 2022. This is seen as the worst case cost scenario. (c) Delegates authority for final terms of the agreement with Freedom Leisure, in line with the decision made in (a) and (b) above to the Head of Paid Service in consultation with the Cabinet Member for Communities. (d) Delegates monthly review process to S151 Officer along with Group Manager – Commissioning, all variances to be reported to Cabinet through Quarterly Performance report.
Corporate priorities Improve community wellbeing, supporting and celebrating our distinctiveness. Deliver great services through achieving financial sustainability
Key Decision NO - net losses can be met from Government grant to the Council and is therefore within budget. Risk of overspend will be managed by monthly tracking of projected net costs against actual net costs.
Exempt NO but Exempt Annexes A and C - containing Commercially sensitive information
1.1Leisure centres closed for the 3rd time on 31st December 2020 (when Gloucestershire went into Tier 4 Restrictions and then the Third National Lockdown enforced closure from 5th January 2021) under Government instruction and whilst expenditure reduced significantly, with the majority of staff furloughed, Freedom Leisure has continued to incur some staff, building management and insurance costs.
1.2Freedom Leisure like a number of leisure operators is a not for profit trust and therefore has a low level of reserves. It has also been unable to access most forms of government financial help. With ongoing costs but no income they cannot survive financially and requested that the Council (and other Councils that they have contracts with) support their ongoing costs during shut down.
1.3Without this subsidy they would need to end staff contracts and hand back the facilities. This would result in significant costs to the Council and no leisure provision until such time as a new contract could be put in place. This would be a minimum of six months but is likely to be much longer. In the current economic market providers will be cautious and the Council is likely to receive risk based bids for the contract resulting in no income and permanent subsidy throughout the contract period. Any community managed provision is also likely to require considerable subsidy as they would not benefit from the strategic management, contracts and advertising and the market intelligence and expertise professional providers hold. Local experience shows that community led facilities fail and facilities close once Council subsidy ends. This has occurred in both the Tetbury and Fairford leisure facilities in Cotswold District both of which were well run but were unable to break even.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Quarter Performance Report - Period OneResolved, that Cabinet: 1. Notes overall progress on the Council priorities and service performance for 2026-27 Q1. A...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies