Resolved - that Cabinet: a) Agrees to authorise up to £84,998 for the preparation of a planning application submission and supporting technical work for Plot F2, Cinderford Northern Quarter. b) Delegates authority to the Group Manager – Property and Regeneration in consultation with the S.151 Officer and the Cabinet Member for Economy to prepare the planning application submission and all other supporting technical work.
Word for word from the decision Forest of Dean published for this meeting.Source: meetings.fdean.gov.uk
Council name FOREST OF DEAN DISTRICT COUNCIL Name and date of CABINET – 14 JULY 2022 Committee Report Number F.566 Subject CINDERFORD NORTHERN QUARTER: SOUTHERN GATEWAY DEVELOPMENT (PLOT F2) Wards affected Cinderford West Accountable Cllr Bernie O’Neill, Cabinet Member for Economy member Tel: 01594 810000 Email: [email protected] Accountable officer Wendy Jackson, Regeneration Manager Tel: 01595 812645 Email: [email removed] Summary/Purpose This report asks members to authorise spend up to £84,998 from the Cinderford Northern Quarter reserves, to prepare a planning application submission and schedule of works for the development of six commercial units at Plot F2, Cinderford Northern Quarter. This development phase will generate detailed proposals that can be used to market the new units. Once planning permission is secured, a detailed business case will be brought to Cabinet and Full Council for consideration before the project would proceed to the construction phase. Annexes Annex A – Cinderford Northern Quarter Development Plot Plan Annex B - Site Plan Recommendations That Cabinet: a) Agrees to authorise up to £84,998 for the preparation of a planning application submission and supporting technical work for Plot F2, Cinderford Northern Quarter. b) Delegates authority to the Group Manager – Property and Regeneration in consultation with the S.151 Officer and the Cabinet Member for Economy to prepare the planning application submission and all other supporting technical work. Corporate priorities 1.1. Develop a vibrant economy that is resilient and future proofed Key Decision 1.2. NO Exempt 1.3. NO Consultees/ 1.4. Senior officers and professional advice sought from Knight Frank Consultation regarding market demand and impact of Covid-19. 1. BACKGROUND 1.1. A hybrid planning application was approved in February 2015. This consisted of detailed permission for a spine road and college building, and outline permission for mixed use development on 10 other plots (including Plot F2). 1.2. The first phase of the spine road has been constructed, as has the college building. 1.3. Plot F2 is located to the south east of the Cinderford Northern Quarter site, and is the gateway to the development area (Annex A – Cinderford Northern Quarter Plot Plan). It is allocated for employment generating uses within the Cinderford Northern Quarter Area Action Plan.
2. INITIAL DESIGN STAGES 2.1. The District Council had been working with Roberts Limbrick architects to develop commercial units at Plots F1 and F2, Cinderford Northern Quarter. The project team have been working through the Royal Institute of British Architects (RIBA) Stages Plan of Work to achieve this. 2.2. The proposal is for the District Council to develop and own the new commercial assets and rent the new space to increase the Council’s revenue stream. 2.3. A number of design iterations have been undertaken for Plots F1 and F2. These have not progressed either due to financial reasons, or the requested Cabinet pause to all Cinderford Northern Quarter activity whilst an inquiry by the Strategic Overview and Scrutiny Committee has been ongoing. 2.4. The initial work had been funded by part of the One Public Estate (OPE) Sustainable Grant fund of £100,000. The OPE fund has also been used to prepare the planning application submission to vary the hybrid planning approval for the wider CNQ site, this work is currently paused whilst the Scrutiny Inquiry takes place.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Quarter Performance Report - Period OneResolved, that Cabinet: 1. Notes overall progress on the Council priorities and service performance for 2026-27 Q1. A...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.