Resolved, that Cabinet; a) Approved the installation of the first phase of EVCPs, as detailed in this report, with costs of up to £206,352.65 allocated from the Council’s Capital Budget, together with already secured ORCS grant funding of up to £199,853.35. b) Delegated authority to the S.151 officer, in consultation with the Cabinet Member for Finance to: i. agree final costs in (a) prior to work commencing, ii. agree a standard fee per kWh, which will be kept under review to ensure that as a minimum, the installations cover their costs, including any contract management costs; iii. agree how revenue funds are used in the management of the EVCP contract, including monitoring demand, costs (specifically fluctuating electricity costs) and income; iv. agree how revenue funds are used for EVCP annual repairs/maintenance and back-office services; v. agree amendments to the Parking Order, restricting vehicles from parking in charging bays unless they are charging a vehicle and that if appropriate, any required changes are approved as part of the current Parking Order Review. c) Delegated authority on the procurement strategy (e.g. which procurement framework to use and contract length) to the Chief Executive, in consultation with Interim Head of Legal and the Cabinet Member for Climate Emergency. d) Noted the draft timetable for the project and the challenging timescales for installation and commissioning of the charge points. Agreed by assent.
Word for word from the decision Forest of Dean published for this meeting.Source: meetings.fdean.gov.uk
Accountable member Cabinet Member for Climate Emergency – Chris McFarling Email: [email protected]
Accountable officer [name removed] - Head of Climate Action | Net Zero Email: [email removed]
Report authors [name removed] - Head of Climate Action | Net Zero Email: [email removed] Marcus Perrin – Climate Emergency Officer Email: [email protected]
Summary/Purpose To brief Cabinet on the current status of the ORCS funded EVCP project and to seek approval for delegation of future decisions to enable to project to proceed.
Annexes Annex A – On-going grant commitments Annex B – Draft high-level service and project needs Annex C – List of proposed installation sites (carparks) Annex D – 2020 EVCP Report Annex E – Equality and Rurality Impact Assessment Annex F – Impact Assessment Tool Recommendations
1 On-Street Residential Chargepoint Scheme
See: https://www.gov.uk/government/publications/grants-for-local-authorities-to-provide-residential- on-street-chargepoints/grants-to-provide-residential-on-street-chargepoints-for-plug-in-electric- vehicles-guidance-for-local-authorities Recommendation(s) That Cabinet resolves to: (a) Approve the installation of the first phase of EVCPs, as detailed in this report, with costs of up to £206,352.65 allocated from the Council’s Capital Budget, together with already secured ORCS grant funding of up to £199,853.35; (b) Delegate authority to the S.151 officer, in consultation with the Cabinet Member for Finance to: (i) agree final costs in (a) prior to work commencing, (ii) agree a standard fee per kWh, which will be kept under review to ensure that as a minimum, the installations cover their costs, including any contract management costs; (iii) agree how revenue funds are used in the management of the EVCP contract, including monitoring demand, costs (specifically fluctuating electricity costs) and income; (iv) agree how revenue funds are used for EVCP annual repairs/maintenance and back-office services; (v) agree amendments to the Parking Order, restricting vehicles from parking in charging bays unless they are charging a vehicle and that if appropriate, any required changes are approved as part of the current Parking Order Review. (c) Delegate authority on the procurement strategy (e.g. which procurement framework to use and contract length) to the Chief Executive, in consultation with Interim Head of Legal and the Cabinet Member for Climate Emergency. (d) Note the draft timetable for the project and the challenging timescales for installation and commissioning of the charge points.
Council Plan priorities Applicable to all priorities. Priority 1: Thriving Communities - to foster resilient and inclusive communities that are motivated and competent to adapt to the challenges and opportunities posed by the climate and nature emergencies. Priority 2: Decarbonisation and nature recovery - for the Forest of Dean to have a protected and enhanced natural environment, and to be on target to be carbon neutral by 2030. Priority 3: Sustainable Economy - to foster economic prosperity while ensuring environmental sustainability and social well-being.
Key Decision YES Exempt NO
Consultees/ Consultation on proposed locations of the chargepoints within car parks Consultation planned with Ward Members and relevant Town and Parish Councils.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Quarter Performance Report - Period OneResolved, that Cabinet: 1. Notes overall progress on the Council priorities and service performance for 2026-27 Q1. A...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.