Resolved, that Council 1) Approve the implementation of Phase 1 of the Publica Transition on the basis of the Detailed Transition Plan: 2) Delegate to the Chief Executive in consultation with the Leader of the Council the authority to deal with any final detail matters arising from the Detailed Transition Plan: 3) Delegate authority to the Chief Executive in consultation with the Leader of the Council to update the constitution as required as a result of the Publica Transition. All such changes to be reported to Council in due course. Voting was as follows: For (33) Councillors Di Martin, Richard Burton, Alison Bruce, Jackie Dale, Johnathan Lane, Jackie Fraser, Beth Llewellyn, Andrew McDermid, Dave Tradgett, Trevor Roach, David Wheeler, Mark Topping, Patrick Kyne, Jacob Sanders, James Bevan, Harry Ives, Clayton Williams, Nick Evans, Alan Preest, Julia Gooch, Jamie Elsmore, Bernie O’Neill, Gill Moseley, Gillian Kilmurray, Clive Elsmore, Philip Burford, John Francis, Shaun Stammers, Chris McFarling, Sid Phelps, Adrian Birch, Andy Moore, Simon Phelps. Abstain (0) Against (0) Total (33) The Democratic Services Officers returned to the chambers at 7.21pm.
Word for word from the decision Forest of Dean published for this meeting.Source: meetings.fdean.gov.uk
Report author Andrew Pollard, Interim Programme Director for the Publica Transition Programme [email protected]
Summary/Purpose To consider the Detailed Transition Plan, to note its contents and to approve the recommendations therein.
Annexes Annex A – Detailed Transition Plan Annex B – Equality and Rurality Impact Assessment
Recommendation(s) That Council: 1. Approve the implementation of Phase 1 of the Publica Transition on the basis of the Detailed Transition Plan; 2. Delegate to the Chief Executive in consultation with the Leader of the Council the authority to deal with any final detail matters arising from the Detailed Transition Plan; 3. Delegate authority to the Chief Executive in consultation with the Leader of the Council to update the constitution as required as a result of the Publica Transition. All such changes to be reported to Council in due course. Council Plan priorities Priority 1: Thriving Communities - to foster resilient and inclusive communities that are motivated and competent to adapt to the challenges and opportunities posed by the climate and nature emergencies. Priority 2: Decarbonisation and nature recovery - for the Forest of Dean to have a protected and enhanced natural environment, and to be on target to be carbon neutral by 2030. Priority 3: Sustainable Economy - to foster economic prosperity while ensuring environmental sustainability and social well-being.
Key Decision YES
Exempt NO
Consultees/ Chief Executive, Section 151 Officer, Monitoring Officer, Leader, Deputy Consultation Leader, Cabinet Members, Publica Review Programme Director, Publica Interim Managing Director and through a facilitated workshop with Local Partnerships, Publica Assistant Directors. Overview and Scrutiny Committee, supported by the Publica Review Scrutiny Panel. 1. BACKGROUND
1.1The majority of Council services are currently delivered through Publica, a joint vehicle owned by the Council together with Cotswold District Council, Cheltenham Borough Council and West Oxfordshire District Council. An options appraisal review of Council services and the way in which they are delivered was undertaken in 2023 by external advisors Human Engine. Their final report recommended that the majority of services should move from Publica and return to being under greater control of the Councils. In November 2023, the Council’s Cabinet resolved to approve the recommendations of the Human Engine report and to develop a Detailed Transition Plan following appropriate due diligence.
1.2Local Partnerships, supported by the Local Government Association (LGA), South West Region transformation funding, subsequently delivered a report in February 2024, expanding on the Human Engine Report findings, providing additional supporting detail and setting out two phases under which the majority of services could be repatriated: phase 1 comprising a significant number of primarily place based services expected to be around October 2024 and phase 2 expected to be in/around March 2025.
1.3To support the Chief Executives of the Shareholders Councils and elected members in implementing the transition of services, an Interim Programme Director was appointed at the end of January 2024 to lead the Publica Transition Programme. The scope of this Programme follows the recommendations of the Human Engine Report delivered in Autumn 2023 which proposed retaining selected services within Publica, meaning that future service delivery move be via direct control, be shared, via Publica or some other collaborative model on a case-by- case basis.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.