Resolved
Resolved , that Committee; 1. Noted the Strategic Risk Register.
Audit Committee noted this item on Thursday 26 June 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved , that Committee; 1. Noted the Strategic Risk Register.
Updates are shown in red Forest of Dean District Council - Strategic Risk Register Annex A - HPS.133 Last Review Date June 2025 Risk Description of Risk/Opportunity Initial Risk Previous Residual Residual Risk Overall Direction of Travel since last ID Existing Control, Mitigation or Contingency Change Risk Response & Further Action Assessment Risk Score Assessment review impact likelih score impact likelih score impact likelih score ood ood ood Services & Finance: Deliver great services through achieving financial stability F-CRR-01 Future Funding 4 4 16 2024/25 Budget approved and is balanced and 4 4 16 4 4 16 TREAT If future Government funding and income from other funding streams aligned to the Council Plan. 0 Continue to update business rate assumptions and monitor the accuracy of the are significantly lower than previously assumed, this would lead to Budget continually reviewed to ensure it remains on MTFS. Implementing the approved capital strategy. Ensure savings outlined in reduction or cessation of some services provided and subsequent target. the MTFS are realised. Where not, alternatives will be sought. The Council will damage to the reputation of the Council. Assumptions built in for inflation and annual Local continue to search for investment opportunities and ways of decreasing The Government's Autumn Spending Review will only provide funding Government Pay increases. expenditure and/or increasing income. Await Central Government decisions and figures for one year only. This leaves the Council with some long term Treasury Management and investments reviewed discussions on future funding and future settlements. MTFS and budget signed financial uncertainty. and reports provided to Members. off and aligned to the Council Plan. Risk score to reflects medium term uncertainty around Council budget. Risk Owner: Section 151 Officer Responsible Officer: Deputy 151 Officer Revised MTFP and Budget Strategy for 25/26 approved by Cabinet in November 2024. The global economic position is being monitored for any national impact e.g., inflation, energy prices, interest rates. A review will be undertaken to understand any potential impact on FODC following the spending review and any other changes from central government.
Next Review: September 2025
F-CRR-02 Publica Partnerships; Transition of services, Governance Arrangements 4 4 16 Contracts in place for the delivery of services 4 3 12 4 3 12 REDUCE and Performance through Publica. 0 The Council is reliant on Partnership Working to deliver its Statutory, Shareholder Forum established as part of company The phase 1 transition of services from Publica to the Council was completed on Mandatory and Discretionary services. The largest of these providers is Governance Arrangements. 1/11/24 and work continues on embedding these services and the values / Publica which provides the majority of services following the transfer of Two Publica Assistant Directors act as Locality Leads culture for the organisation. staff to this company. If these providers do not provide the services as for Forest of Dean and are part of FoDDC Senior Work has been completed on the review of services for consideration under
contracted to do so, this would reflect poorly on the reputation of the Management Team. phase 2 with options costed and due dilligence completed. Recommendations Council as well as challenges if statutory services are not delivered. Performance information presented to Scrutiny. made on the future delivery of these services was approved by Council and the services will transfer on 1 July 2025. Work will commence on readiness for LGR. Risk Owner: Chief Executive Officer (CEO) On 1 July 2025, we will have some gaps in our structure, which are currently out Responsible Officer: Interim Publica Managing Director to recruitment. This will mean that we may not be able to deliver on all priorities immediately.
Next review: September 2025
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Strategic Risk Register: June 2025Report | 440 KB | DownloadRead as text |
PDF |
Strategic risk registerReport | 95 KB | Download |
Follow Audit Committee at Forest of Dean and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | Internal audit progress reportResolved, that Committee; 1. Considered the reports and commented as necessary | Decided | Open |
| 2 Jul 2026 | Statement of AccountsResolved, that Committee; a) Noted the report and draft statement of accounts in Annex A | Noted | Open |
| 2 Jul 2026 | Treasury Management Out-turn ReportResolved, that Committee; a) recommends to Council that they approve the actual 2025/26 prudential and treasury indic... | Approved | Open |
| 2 Jul 2026 | Annual governance statement action plan updateResolved, that Committee; 1. Noted the action plan and associated progress update. | Noted | Open |
| 2 Jul 2026 | Strategic risk registerResolved, that Committee; Approved the changes made to the Risk Register as outlined in section 2 of this report. App... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.