Resolved
RESOLVED - That no decision can be made on the proposals until a cost breakdown and a supply and demand analysis be brought back to a future meeting.
Gateshead Schools Forum decided this item on Thursday 17 March 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - That no decision can be made on the proposals until a cost breakdown and a supply and demand analysis be brought back to a future meeting.
To request that Schools Forum agree to the use of some of the Early Years Block underspend to create additional two year old funded places.
The Council has a statutory duty to provide 15 hours per week of free early education for disadvantaged 2 year olds. This duty came into effect from September 2013 for 20% of all 2 year olds and was extended to include 40% of all 2 year olds from September 2014, estimated by DfE to amount to 1,100 places.
Eligibility for this entitlement is the same as for Free School Meals (FSM), Looked After Children (LAC), some children with Special Educational Needs and Disabilities and those families with a low income through the extension of benefits criteria.
In April 2013 funding for the 2 year old free entitlement came into the Council in the Early Years Block of the Dedicated Schools’ Grant (DSG). This was made up of statutory funding for places (£1,407,568) and trajectory (capacity) building funding (£552,573).
In addition to the revenue funding there was a capital allocation of £356,444, to be used to create sufficient places to meet the 40% statutory target in September 2014. All capital funding has been spent. There is now £258,000 left in unspent early years reserves.
Ongoing analysis of take-up of 2 year old free places indicates that there is still a need for additional funding for projects in the Crawcrook and Ryton areas of Gateshead. There is an estimated need for an additional 19 places in Crawcrook and 14 places in Ryton.
Proposal
Crawcrook All schools and registered childcare organisations within the Crawcrook area have been contacted to establish whether there is any interest in creating 2 year old places. This consultation gave a result of no interest from St Agnes RC Primary School, St Agnes
1 of 3 Day Nursery and Bright Sparks Nursery. An expression of interest was gained from Emmaville Primary School which already has a foundation stage unit, including a nursery PAN of 39. The school and the early years provision was graded Outstanding by Ofsted in October 2014.
Council Officers from Schools Finance Department and Early Years Childcare Service have met with the School Governors of Emmaville Primary School to assist them in reaching a decision of whether to progress or not with the creation of these places. A decision was reached by the Governing Body to create places for 2 year old children based on the positive benefit for children within the community. A separate space is required to meet the needs of the younger children. There are 2 options to accommodate this provision which have been considered further:
Option 1 - Demountable accommodation of 3 bay unit - (One classroom, circulation & WCs) at a cost of £175,000 including building work and fees.
Option 2 – To build an extension onto the school. This has been costed at £380,000, and therefore exceeds the remaining underspend in reserves.
The school’s preferred option for accommodation is to build an extension onto the school. However, this is unaffordable and therefore the recommended option is option 1, the demountable accommodation. In addition, revenue funding of £10 k is requested for the purchase of suitable equipment and resources.
Ryton All schools and childcare organisations within the Ryton area have been contacted to establish whether there is an interest in creating additional 2 year old places. This consultation gave a result of no interest from Ryton Infant School and Willow’s Montessori Nursery. An expression of interest was gained from Crookhill Early Years Pre-school, supported by Crookhill Primary School, and from Care with Cuddles Day Nursery. These 2 options have been further considered:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Early Years Revenue UnderspendReport | 187 KB | DownloadRead as text |
Follow Gateshead Schools Forum at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Sep 2026 | Alternative Provision Funding for River Tyne AcademyRESOLVED that the information in the report in appendix 1 be noted. | Noted | Open |
| 10 Sep 2026 | Quarter 1 DSG MonitoringRESOLVED that the contents of the report be noted. | Noted | Open |
| 10 Sep 2026 | Department for Education Consultation - Early Years Funding: Proposed Changes to the Entitlements Funding SystemRESOLVED that the response outlined in Appendix 1 be submitted to the DfE's Early Years funding consultation on behal... | Decided | Open |
| 10 Sep 2026 | Department for Education Consultation - Upfront Funding for Mainstream Schools: Creating a Local SEND Inclusion FormulaRESOLVED that the response outlined in Appendix 1 be submitted to the DfE's Local SEND Inclusion Formula consultation... | Decided | Open |
| 10 Sep 2026 | Department for Education Consultation - SEND Reform: Education Otherwise than At SchoolRESOLVED that the EOTAS consultation questions be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.