Resolved
RESOLVED - ( i ) The Joint Executive Committee noted the contents of the report. (ii) The Joint Executive Committee agreed to receive further updates regarding the reclassification of IBA, as appropriate.
South Tyne and Wear Waste Management Partnership Joint Executive Committee noted this item on Friday 24 June 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - ( i ) The Joint Executive Committee noted the contents of the report. (ii) The Joint Executive Committee agreed to receive further updates regarding the reclassification of IBA, as appropriate.
1.1To update the Joint Executive Committee on the latest position with regard to the reprocessing of materials produced as Incinerator Bottom Ash (IBA) at the Partnership’s Energy from Waste facility (EfW), and the potential impact of its reclassification within the waste hierarchy and data reporting requirements from ‘material recovery’ to ‘material recycling’.
2.1South Tyne and Wear Waste Management Partnership’s Joint Municipal Waste Management Strategy aims to achieve a 50% recycling/ composting target for household waste by 2020.
2.2IBA is the by-product from the incineration of waste through the EfW process. It contains materials, such as metals, which are extracted and sent for reprocessing, and the remaining IBA aggregate is used by the construction sector as a direct replacement for quarried stone.
2.3However, within the waste hierarchy and WasteDataFlow reporting requirements, the treatment of materials produced through IBA is classified as ‘material recovery’ and not ‘material recycling’.
2.4Furthermore, there is some ambiguity within the European Union (EU) regarding the classification of IBA, as some countries appear to include it in calculating recycling performance.
2.5Reclassifying IBA in the UK could, therefore, help the Partnership to close the gap in achieving the European 50% recycling/composting target set for 2020 increasing the overall recycling/composting rate by an average of 11.1%. 2.6 In January 2016, the Joint Executive Committee wrote to Defra to support the issues raised by Hampshire County Council’s ‘Project Integra’ regarding IBA classification and its potential impact on recycling performance.
3. UPDATE
3.1The Joint Executive Committee received a response from Defra, in which, Rory Stewart, the Parliamentary Under Secretary of State for Environment and Rural Affairs, welcomed the Partnership’s efforts to divert waste from landfill and improve recycling performance. He acknowledged the issues that the Partnership raised regarding the calculation of recycling performance in the UK, and highlighted that Defra is aware of the approach in some other EU Member States.
3.2The correspondence noted that materials retrieved from the recovery process, such as IBA, cannot be recycled in a ‘closed-loop’ fashion (i.e. where materials are recycled into new products made from the same material), which was a key element of the EU’s new circular economy package.
3.3However, in conclusion, [name removed] noted that Defra will “continue to keep under consideration the way in which we estimate recycling rates and to make sure that we accurately capture the full range of materials included” and that “If there were any proposals to make significant changes to the position of IBA, we would engage Local Authorities and industry on these”. The full response can be found at Appendix A.
4. PROJECT INTEGRA
4.1In June 2016, the interim Chair of Project Integra wrote to 30 local authorities (see Appendix B) who are successfully recycling at least 10,000 tonnes of IBA per annum (including Gateshead and Sunderland). The letter asked Portfolio Holders to pledge their support in presenting the following point of view to the relevant Government Ministers:
i. The UK should be including all forms of IBA recycling in its calculation of the national recycling rate to ensure our performance is based on the same practice as other EU Member States.
ii. There should be one standardised measure of recycling rate that is reported by the UK, individual countries of the UK, and individual local authorities, to allow for fair comparisons to be made.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Energy from Waste Facility: Incinerator Bottom AshReport | 477 KB | DownloadRead as text |
Follow South Tyne and Wear Waste Management Partnership Joint Executive Committee at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Mar 2026 | Waste Sector Contracts UpdateRESOLVED i. The Joint Executive Committee noted the contents of the report. | Noted | Open |
| 4 Dec 2025 | Waste Strategy RefreshRESOLVED i . to note the contents of the report and the decision of the Cabinet of South Tyneside Council to endorse ... | Noted | Open |
| 24 Jul 2025 | Election of ChairRESOLVED i . Councillor Hall to assume the role of Chair of the Committee. | Decided | Open |
| 24 Jul 2025 | Election of Vice ChairsRESOLVED i . Councillor Gibson to assume the role of Vice Chair of the Committee. ii. Councillor Leonard to assume th... | Decided | Open |
| 24 Jul 2025 | Contracts Update - ReportRESOLVED i. The Joint Executive Committee noted the contents of the report. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.