Resolved
RESOLVED - That the Schools Forum approved the request for £14,000 in order to proceed with option 2 at a total cost of £14,000.
Gateshead Schools Forum approved this item on Thursday 14 July 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - That the Schools Forum approved the request for £14,000 in order to proceed with option 2 at a total cost of £14,000.
To request the use of Early Years DSG reserves for the Council’s Design and Technical Services to prepare concept designs as requested within the Department for Education (DfE) capital grant application to support the extended free entitlement for working parents of three- and four-year-olds.
The extended free childcare entitlement will be available from September 2017 for working parents of three- and four-year-olds and will provide eligible parents with a total of 30 hours of free childcare per week, over 38 weeks or 1,140 hours across more weeks per year.
Officers from Gateshead Early Years Childcare Service (EYCS) submitted an expressions of interest (EOI) to the Department for Education (DfE) in April 2016 to work with local childcare providers to bid for capital funding to expand childcare provision (including schools that currently offer, or plan to offer, provision for 3- and 4-year-olds).
On 1st July 2016 officers received information from DfE requesting applications from Local Authorities setting out specific provider capital projects in their area by 31st August 2016.
Notification was also received of our ‘Project Limit’ ranking of Medium – 4 projects maximum. This is based on the number of 3- and 4-year-old children that DfE estimate are eligible for 30 hours in the local authority. The figure for Gateshead is 1370 eligible children.
Application Process
Expressions of interest from all providers that are interested in building on the existing 15 hour universal entitlement, and require capital to do so, were requested to be submitted to EYCS by 8th July 2016. For the purposes of this bid round DfE define a place as a 30 hour funded place offered over at least 38 weeks per year. The place may either build on an existing 15 hour place to create a 30 hour place or be an entirely new 30 hour place.
An Officer Group consisting of representatives from the Councils Design and Technical Service, Corporate Finance, Legal Services, educationGateshead and EYCS will apply the DfE assessment criteria to ensure that the four most suitable providers/schemes from Gateshead are submitted to DfE for their consideration. The DfE criterion is divided into to a two stage bid assessment process. Stage 1 will assess individual projects against a set of pass or fail qualifying tests based on: track record with Ofsted or the Independent Schools Inspectorate; completion date by the end of August 2017; total cost of the project is below £1 million; and a minimum of 25% of the total project cost is funded from alternative sources.
Stage 2 will assess individual projects that were successful at the initial stage based on the following criteria: evidence of localised sufficiency need, project outcomes, and value for money.
In order to completely fulfil this criterion it is necessary that the Council’s Design and Technical Services prepare concept designs, preliminary schemes and estimates of costs. This detail will be completed for the four EOI which the officer group select as the most suitable schemes to go forward to DfE. An allowance of £3,500 for each scheme is needed in order that this work can be carried out.
Successful bids will receive grants awards within financial year 2016-17. Successful bidders will be notified by December 2016.
There are 2 options:
1) Not to proceed with the capital applications.
2) To proceed with the capital applications. This will involve upfront funding from Early Years DSG Reserves of £3,500 per scheme to prepare concept designs, preliminary schemes and estimates of costs. Four schemes will be submitted for consideration. Should the applications be successful and the grant awarded the upfront outlay from Early Years DSG reserves will be reimbursed.
That schools forum approves the request for £14,000 in order to proceed with option 2 at a total cost of £14,000.
For the following reasons:-
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Use of Dedicated Schools Grant ReservesReport | 155 KB | DownloadRead as text |
Follow Gateshead Schools Forum at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Sep 2026 | Alternative Provision Funding for River Tyne AcademyRESOLVED that the information in the report in appendix 1 be noted. | Noted | Open |
| 10 Sep 2026 | Quarter 1 DSG MonitoringRESOLVED that the contents of the report be noted. | Noted | Open |
| 10 Sep 2026 | Department for Education Consultation - Early Years Funding: Proposed Changes to the Entitlements Funding SystemRESOLVED that the response outlined in Appendix 1 be submitted to the DfE's Early Years funding consultation on behal... | Decided | Open |
| 10 Sep 2026 | Department for Education Consultation - Upfront Funding for Mainstream Schools: Creating a Local SEND Inclusion FormulaRESOLVED that the response outlined in Appendix 1 be submitted to the DfE's Local SEND Inclusion Formula consultation... | Decided | Open |
| 10 Sep 2026 | Department for Education Consultation - SEND Reform: Education Otherwise than At SchoolRESOLVED that the EOTAS consultation questions be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.