Resolved
RESOLVED - That the Joint Executive Committee noted the contents of the report .
South Tyne and Wear Waste Management Partnership Joint Executive Committee noted this item on Friday 23 September 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - That the Joint Executive Committee noted the contents of the report .
1.1To update the Joint Executive Committee on the resource recovery sector, including issues arising across the sector in other treatment technologies that were previously considered as part of the process to secure a residual waste treatment solution for the South Tyne and Wear Waste Management Partnership (STWWMP).
2.1As part of the residual waste treatment solution procurement process, councillors from each of the three partner authorities visited a variety of different waste treatment facilities, both within the UK and in Europe.
2.2The programme of visits enabled the Joint Executive Committee to consider all of the treatment technologies available within the market, and provide enough background information for analysis to be undertaken to identify the most appropriate solution for STWWMP.
2.3Electricity generation through energy-from-waste (EfW) was identified as the most cost-effective solution for the residual waste collected across Gateshead, South Tyneside, and Sunderland. STWWMP subsequently appointed SUEZ to construct an EfW facility at Teesside.
2.4However, since this decision, a number of waste treatment technologies within the sector have encountered a range of technical, financial, or health and safety issues.
3. WASTE TREATMENT TECHNOLOGIES
3.1Identifying a long-term and cost effective residual waste treatment solution for STWWMP was a difficult decision for the Joint Executive Committee. A programme of site visits was undertaken to understand the broad range of residual waste treatment technologies available, the situation within the waste market, and the visual and environmental impact of the facilities.
3.2To ensure that all available treatment options could be fully considered, a number of different technologies were considered, including:
Anaerobic Digestion Autoclaving Bio-fertilisation Composting Energy from Waste Energy Recovery with Combined Heat and Power Energy Recovery with District Heating Facility Gasification Material Recovery Mechanical Biological Treatment
4. RESOURCE RECOVERY SECTOR TODAY
4.1Across the country, a number of waste treatment facilities have encountered major problems in demonstrating their long-term viability.
4.2The gasification sector, for example, has encountered a number of issues and several facilities have not been successfully completed because the technology can be considered as complex or embryonic in comparison with other combustion techniques. A high-profile and local example of this is Air Products’ withdrawal from the sector by scrapping the Billingham-based Tees Valley 1 and 2 plants. Writing-off the part- built facility is expected to cost Air Products approximately £770m, but is symptomatic of the wider issues surrounding advanced thermal gasification.
4.3Elsewhere, several facilities utilising mechanical biological treatment (MBT) technology have encountered long-term site closures following major issues such as large-scale fires. In some cases, this has resulted in extreme remedial action including changes to aeroplane flight paths, large-scale local business evacuations and road closures, or catastrophic failures in essential equipment that required new, bespoke, expensive equipment to be designed and installed.
4.4Furthermore, several local authorities have encountered significant issues with the delivery of their energy-from-waste PFI projects.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Resource Recovery Sector: UpdateReport | 173 KB | DownloadRead as text |
Follow South Tyne and Wear Waste Management Partnership Joint Executive Committee at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Mar 2026 | Waste Sector Contracts UpdateRESOLVED i. The Joint Executive Committee noted the contents of the report. | Noted | Open |
| 4 Dec 2025 | Waste Strategy RefreshRESOLVED i . to note the contents of the report and the decision of the Cabinet of South Tyneside Council to endorse ... | Noted | Open |
| 24 Jul 2025 | Election of ChairRESOLVED i . Councillor Hall to assume the role of Chair of the Committee. | Decided | Open |
| 24 Jul 2025 | Election of Vice ChairsRESOLVED i . Councillor Gibson to assume the role of Vice Chair of the Committee. ii. Councillor Leonard to assume th... | Decided | Open |
| 24 Jul 2025 | Contracts Update - ReportRESOLVED i. The Joint Executive Committee noted the contents of the report. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.