RESOLVED - That the Council be recommended to: ( i ) Approve that all variations to the 2016/17 Capital Programme as detailed in appendix 2 to the report be agreed as the revised programme. (ii) Approve the financing of the revised programme. (iii) Note the capital expenditure and capital financing requirement indicators have been revised in line with the revised budget and that none of the approved Prudential Indicators set for 2016/17 have been breached. The above decisions have been made for the following reasons: (A) To ensure the optimum use of the Council’s capital resources in 2016/17. (B) To accommodate changes to the Council’s in-year capital expenditure plans. (C) To monitor performance within the approved Prudential Limits.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. This report sets out the latest position on the 2016/17 capital programme and Prudential Indicators at the end of the first quarter to 30 September 2016. The report assesses reasons for the variances from the approved programme and details the proposed financing of the capital programme. In addition the report considers the impact of CIPFA’s Prudential Code on the capital programme and the monitoring of performance against the statutory Prudential Indicators.
Background
2. The original budget for the capital programme for 2016/17, as agreed by Council on 23 February 2016, totalled £71.069m, which was then revised to £76.297m as part of the first quarter review. The second quarter review now projects the year-end expenditure to be £73.346m.
3. The proposed reduction to the capital programme at the second quarter comprises of the following movements: £m Slippage of planned capital expenditure from 2015/16 0.050 Increased borrowing/external funding/contributions 3.869 Re-profiling of capital expenditure to future years (5.414) Re-profiling of planned HRA Investment (1.256) Other reductions (0.200) Total Variance (2.951)
4. The proposed slippage in the capital programme is resourced by external funding and prudential borrowing, and the Council continues to manage the available resources in a flexible manner to ensure that the use of external resources is maximised where possible.
5. A total of £5.414m of slippage has been identified on a number of key schemes throughout the capital programme where expenditure has been re-profiled into 2017/18. This includes £2.412m relating to potential development at Baltic Business Quarter, relating to a planned delay in the progression of the speculative office development element of the scheme. The Council’s resources are currently focussed instead on progressing the Northern Centre for Emerging Technology scheme which is expected to utilise external funding from ERDF and the Local Growth Fund.
1 of 5 6. The slippage to future years also includes: £0.590m relating to the proposed Street Lighting LED replacements following delays in the procurement process which means installation is unable to commence in the current financial year; £0.500m relating to potential investment in Gateshead Quays. Work is ongoing to develop specific investment proposals with our Development Partner which will then inform the Council’s investment plans within the future Capital Programme; £0.400m relating to the proposal to reconfigure the Public Spaces within the Civic Centre. This will be considered alongside potential opportunities to improve the use of the building and explore options to work with other Public Sector organisations; £0.400m relating to the planned extension of the Energy Network to Trinity Square as commercial negotiations with potential end users continue.
7. Additions to the programme identified during the second quarter review amount to £3.869m. This includes the proposed acquisition of retail and residential units as an investment at St Mary’s Green in Whickham. The retail units will form part of the non- operational portfolio whilst the residential units utilise HRA capital receipts and will form part of the HRA in a manner consistent with the Council’s existing assets held at St Mary’s Green.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.