Corporate Asset Management - Delivery and Performance Report
AgreedScrutiny2 papers
Corporate Resources Overview and Scrutiny Committee agreed this item on Monday 28 November 2016. Below is the council's own wording, with the papers it was decided on.
It was agreed that a breakdown of the factors be provided. Business cases were prepared and assessed prior to energy efficiency works being approved and carried out. Once the works have been completed, the same process will be followed for energy generation schemes. This approach was welcomed by the Committee. In respect of carbon emission monitoring, the use of weather corrected figures was queried. It was clarified that changes in weather can result in a 15% variance in gas consumption figures therefore the weather correction calculation deducts this variability. It was commented that there is much evidence of borough-wide energy efficiency schemes and this was praised. It was suggested that activity could now focus on energy generation schemes, such as the installation of solar panels on properties within the Council’s housing stock. It was recognised that centralisation will generate savings, however, it was commented that the Council should seek to maintain a public interface with residents in localities. The Committee was pleased to note that work is being undertaken to maintain the delivery of some services from within local communities, by linking with schools, GP practices and other partner organisations. It was agreed that a performance report be received in respect of the Council’s Music Service which is based at the Dryden Centre. Information was sought on the operation and performance of the Civic Centre heating system along with timescales for maintenance works. It was noted ... view the full minutes text for item CR25
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
Gateshead’s sustainable community strategy, Vision 2030, aims to improve the wellbeing and equality of opportunity for the people of Gateshead, enabling them to realise their full potential and enjoy the best quality of life.
In July 2015, the Council adopted a new Council Plan. The Council Plan 2015 -2020 is effectively the Council’s delivery plan for the Community Strategy, Vision 2030 and sets out the direction of the Council for the period to 2020 in order to achieve the longer term goals (the “Big Ideas”) described in Vision 2030.
The Council Plan is supported by a number of corporate and service strategies developed to ensure resources are aligned to meet the Council’s priorities. These include:
The Medium Term Financial Strategy 2017/18 – 2021/22 Gateshead Economic Growth Acceleration Plan 2014 – 2018 Core Strategy and Urban Core Plan for Gateshead and Newcastle upon Tyne 2010 - 2030 Housing Strategy 2013 – 2018 Housing Revenue Account Business Plan 2013 - 2043 Culture Strategy 2014 – 2017 Workforce Strategy 2015 – 2020 Corporate Asset Strategy and Management Plan 2015 - 2020
It is imperative that, with the current budgetary constraints on local government, the Council is confident all the resources at its disposal are deployed as efficiently and effectively as possible.
The Corporate Asset Strategy and Management Plan provides the framework within which the Council can ensure that its property assets are fully utilised in terms of:
Operating as efficiently as possible in terms of outgoings Generation of sustainable income Support of service delivery
This report provides an overview of how the Council’s portfolio is performing against these three criteria. Property Performance
Benchmarking is a way of demonstrating how the portfolio is performing in relation to other, preferably similarly constituted, authorities; it provides a snapshot of performance and compares information in order to identify areas of improvement and best practice.
Benchmarking has in the past been undertaken on a national basis using key, nationally recognised indicators. However, over the last few years, due to budgetary pressures, the opportunities to benchmark with other directly comparable authorities has ceased.
The NaPPMI indicators are no longer collected and collated by CIPFA with the organisation relying on information obtained through the work CIPFA Property undertakes for local authorities in connection with the Value for Money Exercise.
As a result of the lack of national data the Council will continue to rely on its own data and consider its year-on-year performance in areas such as energy consumption, water use and CO2 emissions.
The Council was part of the North East Property Group which comprised all local authorities within the Combine Authority Region together with other key public sector organisations, including the NHS Foundation Trust, the Police and Fire and Rescue Services. It had been hoped that, in due course, it would be possible to progress to a position where data could be made available to make benchmarking an option.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate Resources Overview and Scrutiny Committee at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
Annual Workforce Strategy ReportRESOLVED that Corporate Resources OSC: i. Noted the report ii. Supported the delivery of the Corporate Workforce Stra...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.