RESOLVED - ( i ) That the entering into a delivery agreement with Wilmott Dixon Construction via the SCAPE Major Works Framework , for combined delivery of the HEIGHTs project and associated fabric measures be approved. (ii) That delegated authority be given to the Strategic Director, Communities and Environment, following consultation with the Strategic Director, Corporate Resources, to agree the final terms, scope and costs of the contract awards. The above decisions have been made for the following reasons: (A) To continue to deliver Council priorities around reducing fuel poverty, energy consumption and sustaining tenancies. (B) To maximise efficiencies through combining fabric improvements with ERDF grant funded works that will support capital investment as part of the Council’s Capital Programme. (C) To improve the Council’s assets and ensure that the Council’s Housing stock remains fit for purpose and deliver a sustainable HRA.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. To seek approval for the award of a construction contract to Wilmott Dixon Construction via the SCAPE Major Works Framework, for delivery of fabric works to be undertaken alongside the High Rise Energy Infrastructure for Gateshead Housing Tenants (HEIGHTs) project:-
Window replacement for all Harlow Green high rise blocks Façade replacement and replacement windows at Regent Court
Background
2. Approval was given at Cabinet on 8 November for the acceptance of ERDF grant funding to support the delivery of the HEIGHTS project and for construction contracts to be awarded to Wilmott Dixon Construction via the SCAPE Major Works Framework to deliver the works.
3. The HEIGHTS project will install new district heat and/or power systems to 7 High Rise Housing blocks in the Town Centre and Harlow Green.
4. Since then, the Council has entered pre-construction works contracts with Wilmott Dixon Construction to proceed with the design of the scheme, and is aiming to receive planning approval, and enter into the construction contract, prior to 5 May 2017.
Proposal
5. Additional improvement works to the fabric of the 7 blocks have been identified as follows:
Window replacements for Harlow Green and regent Court high rise blocks Roof replacement for Harlow Green blocks Façade replacement for Regent Court
6. Provision to fund the works has been included in the HRA Capital Programme Report that was approved by Cabinet on 24 January 2017.
7. The five year HRA Capital programme includes £11.1m, towards the part ERDF funded HEIGHTS energy efficiency scheme at Harlow Green and Regent Court, with a further £4.4m of planned window replacements to be delivered alongside these works. In addition £4m is included within the programme to replace the façade at Regent Court;
1 of 4 8. It is proposed that the work is combined with the HEIGHTS project and awarded to the same contractor for the following reasons:-
To minimise costs and Health and Safety risks by having one contractor delivering all elements as works overlap on the tower blocks To ensure timescales are maintained (in particular the façade at Regent Court which is in a state of disrepair) Adding additional works to existing contract will minimise the overall scheme development costs To minimise disruption for customers and leaseholders.
9. In order to ensure that a combined delivery programme, including the additional works, can be undertaken a pre-construction order for design works, valued at £211,000, was placed with Wilmott Dixon Construction in February, following consultation with Housing Portfolio.
10. The pre-construction order allows the scheme to progress to full delivery under the SCAPE framework, without additional delays and costs being incurred through a separate procurement exercise. The pre-construction order does not bind the Council to full construction contract, should for any as yet unforeseen reason, the works are not able to be progressed.
Recommendations
11. It is recommended that:-
(i) Approval is given to entering into a delivery agreement with Wilmott Dixon Construction via the SCAPE Major Works Framework, for combined delivery of the HEIGHTs project and associated fabric measures;
(ii) Approval is given to delegate authority to the Strategic Director, Communities and Environment, following consultation with the Strategic Director, Corporate Resources, to agree the final terms, scope and costs of the contract awards.
For the following reasons:
(i) To continue to deliver Council priorities around reducing fuel poverty, energy consumption and sustaining tenancies.
(ii) To maximise efficiencies through combining fabric improvements with ERDF grant funded works that will support capital investment as part of the Council’s Capital Programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.