Resolved
RESOLVED - That the option of requiring the design of s278 work to be carried out in house be approved. The above decision has been made to ensure the effective design of s278 highway works.
Cabinet approved this item on Tuesday 18 July 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - That the option of requiring the design of s278 work to be carried out in house be approved. The above decision has been made to ensure the effective design of s278 highway works.
1. To seek approval to enable the Council to carry out the design of section 278 highway works in-house (‘s278 works’).
2. New development often requires alterations to the existing adopted highway network, for example in the need for new or altered road junctions. Such works to the existing adopted highway network are known as ‘s278 works’..
3. Although led by developers, s278 works ultimately become a part of the Council’s highway asset. As a result, although the developer has the immediate interest in ensuring works are completed, the long term liability for ongoing maintenance reverts to the Council.
4. Previously developers have been responsible for the design and construction of s278 works. The Council has undertaken this role on occasion, but only when requested specifically. Usually the Council’s role to date has been in checking designs and inspecting works.
5. These arrangements can be problematic. Agreeing the design of schemes and ensuring they are consistent with the relevant planning approvals can be a costly and time consuming process.
Proposal
6. This report proposes that the Council will in future require s278 works to be designed in-house. While initially this would cover only the design of the works, the intention eventually would be to consider extending this to include their construction as well.
7. It is not anticipated that all s278 works would be designed in this way. Before taking on any such work it will be important to ensure internal resources are available to allow this, so that development is not delayed unnecessarily. This will be determined on a case by case basis.
8. The new approach should allow a more effective use of available resources. It will also help to ensure that design standards are maintained and that new or modified road layouts do not impose unnecessary future maintenance liabilities. It should reduce officer time currently spent on negotiating a suitable design, and could reduce developer costs by simplifying the design process.
9. It is recommended that Cabinet approve the option of requiring the design of s278 work to be carried out in house.
For the following reason:
To ensure the effective design of s278 highway works.
CONTACT: Anneliese Hutchinson ext 3881 APPENDIX 1
Policy Context
1. The proposals are in line with the Council Plan. They also support the aims and objectives of the Tyne and Wear Local Transport Plan 3 and the Gateshead Highway Asset Management Plan.
2. New development often requires alterations to the existing highway network, for example in the need for new or altered road junctions. Such works are known as ‘S278 works’ after the relevant provision in the Highways Act 1980.
3. Although led by developers, s278 works ultimately become a part of the Council’s highway asset. As a result, although the developer has the immediate interest in ensuring works are completed; the long term liability for ongoing maintenance reverts to the Council.
4. Previously developers have been responsible for the design and delivery of s278 works. The Council has undertaken this role on occasion, but only when requested specifically.
5. These arrangements can be problematic. Agreeing the design of schemes and ensuring they are consistent with the relevant planning approvals can be an extensive process. Developers have provided feedback that the time taken to negotiate highway agreements such as s278 is one of the most difficult parts of the development process.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Design of Section 278 Highway WorksReport | 229 KB | DownloadRead as text |
Follow Cabinet at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Sep 2026 | Approval of Refreshed Resident Influence Strategyi) To approve the Resident Influence Strategy (Appendix 2). ii) To authorise implementation of the strategy supported... | Approved | Open |
| 22 Sep 2026 | Business North East Business Support Frameworki) To agree that the Council be included as a named delivery partner in NEMSA’s Business North East business case and... | Agreed | Open |
| 22 Sep 2026 | NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ... | Approved | Open |
| 22 Sep 2026 | Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report... | Approved | Open |
| 22 Sep 2026 | Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.