RESOLVED - That the urgent action taken by the Strategic Director, Communities and Environment in submitting the infrastructure funding bid to DCLG and HCA in relation to the Freight Depot site, by the deadline of 28 September 2017, be endorsed. The above decision has been made for the following reasons: (A) To maximise potential housing delivery on a key strategic site. (B) To realise the Council’s policies and objectives in relation to housing growth.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. Cabinet is asked to endorse the submission for infrastructure funding which was made to the Department for Communities and Local Government (DCLG) and the Homes and Communities Agency (HCA) on the 28th September 2017 in relation to the Freight Depot site.
Background
2. In July 2017 DCLG invited local authorities across England to come forward with proposals “to help build homes faster”. Up to £2.3bn capital grant funding will be allocated to local authorities on a competitive basis and will be available from 2017/18 to 2020/21 to unlock and or accelerate housing site development.
3. The monies will come from the Housing Infrastructure Fund (HIF), part of the National Productivity Investment Fund (NPIF) announced in last year’s autumn statement, when it was said it would be aimed at “areas where housing need is greatest”. The DCLG said that once proposals have been approved, it expects local authorities to begin building the necessary infrastructure immediately “and for the homes to follow quickly afterwards”. The scheme is expected to be highly competitive.
Proposal
4. This is an opportunity to bid for a new stream of funding to help pay for infrastructure up front and unlock significant housing development in the borough. Under the HIF Funding guidelines, infrastructure is defined very broadly and includes funding for schools, health care facilities, heritage infrastructure and land assembly, as well as roads, bridges and energy networks.
5. Bids could be submitted for up to £10m for Marginal Viability proposals. It is intended that it would be used to provide the final or missing piece of infrastructure which may currently be preventing development in order to get sites unblocked quickly.
6. This Fund is available up to 31 March 2021 with priority given to strong, strategically important schemes that can start quickly. The bids had to be submitted ahead of the 28 September 2017 and awards will be announced from late 2017 or early 2018.
1 of 7 7. Successful bids will need to demonstrate: a. Value for money based on the acceleration and number of homes set against the funding requested alongside the potential for land value uplift (in line with the new DCLG guidance) – 50% b. A strategic fit, an adopted up-to-date plan or a plan that has been submitted for examination; or the release of otherwise undeliverable land which will speed up getting the plan in place, alongside strong local leadership and evidence of joint working – 25% c. Deliverability – The infrastructure will unlock and or accelerate the delivery of homes. Recovery of monies and re investment will be noted - 25%.
8. Officers have worked with key stakeholders within the Council’s joint venture partnership namely Gateshead Regeneration Partnership (“GRP”) to consider the potential developments which met the funding criteria. Recent work which has been carried out with GRP and consultants Queensberry Architects, helped to inform the bid submission for the Freight Depot site.
9. The Council is seeking the maximum £10m of grant funding to facilitate the delivery of the scheme and contribute towards an estimated £17m of eligible infrastructure costs. This funding would help to ensure that the scheme becomes commercially viable and the anticipated sales income would then fund the remaining development costs.
10. GRP updated the development appraisal in September to reflect the outcome of the initial site investigations and masterplanning work undertaken by Queensbury, providing independently verified estimates of the potential costs and projecting the likely sales income. The appraisal clearly identified the need for additional investment to progress the development, which is consistent with the earlier conversations with the Homes and Communities Agency around the Housing Zone.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.