Resolved
RESOLVED - that the information be noted and the revised plan agreed.
Audit and Standards Committee noted this item on Monday 5 March 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - that the information be noted and the revised plan agreed.
1 This report is to update the Committee on the review of outstanding planned audits to revise the audit plan to reflect and maximize the impact of anticipated resources available for the remainder of the audit year.
2 The Internal Audit Plan Quarterly Monitoring Report to 31 December 2017 reported to the Audit and Standards Committee of 29 January 2018 highlighted that due to delays experienced in recruiting to fill unplanned vacancies which arose during the year, further compounded by the impact of the necessary training and support for the new employees, progress to date was not on target to achieve the local performance target of 97.25% of actual hours against planned hours for the year.
3 To optimise the impact of a revised level of resources, it was agreed that a review of the outstanding planned audits and consideration of their relative risk ratings would be been undertaken, following which high and medium priority audits would be prioritised and any outstanding audits would be carried out early in the new audit plan year.
4 This report summarises the outcome of that review and proposes amendments to the plan which balances the mitigation of risk with available resources.
Summary of Progress
5 A review of the audit plan and discussion with Service Directors highlighted changes to Service delivery that enabled available resources to be optimized by some audits being either no longer required or combined with other audits, which removed 555 hours from the plan.
6 In previous years, audits of key systems were scheduled to take place at specified times on an annual basis to coincide with External Audit work on the financial statements as they placed reliance on this work. As External Audit no longer place reliance on this, it is reasonable to reprofile the audits into the next financial year, despite them being high priority, as the internal audit opinion has consistently been operating well and it is actually less than 12 months since the most recent audit opinion was issued and reported. This removed 1,200 hours from the plan
7 The remaining audits in the plan were then assessed against a prudent estimate of the productive hours that could be delivered in the remainder of the financial year, and where necessary low and medium priority audits that would otherwise have taken place in the final quarter of the year will be rescheduled to the first quarter of the new audit plan year. These audits account for 1,040 hours.
8 The final vacancy within the Service will be filled when a new member of staff commences employment 5 March 2018, which when coupled to the recent investment in recruitment and training will put the Service in a strong position for the sustained delivery of future audit plans.
9 The following table shows the revised plan taking account of the review process set out in the report, which revises the planned hours to 15,994:
Audit Area Planned Revised Hours Hours Groups and Services Care, Wellbeing and Learning 1,595 1,065 Communities and Environment 1,840 1,245 Corporate Resources 1,835 1,655 Corporate Services and 1,115 705 Governance Office of the Chief Executive 596 336 Schools 900 740 Key Systems 2,068 1,408 Corporate Audit Planning and Management 1,410 1,410 Counter Fraud 2,750 2,750 Grant Certification 350 350 Total Groups and Services 14,459 11,664
External Bodies 4,330 4,330
Total 18,789 15,994
10 The list of audits which account for the reduction in the planned hours is attached at Appendix A to this report.
11 The Committee is asked to note the contents of this report and agree the revised Audit Plan. Appendix A
Audits revised in 2017/18 plan
Group Audit Audit Priority
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Plan 2017/18 Update ReportReport | 71 KB | DownloadRead as text |
Follow Audit and Standards Committee at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2026 | Treasury Management Annual Report 2025/26RESOLVED that the Treasury Annual Report be submitted to Cabinet. | Decided | Open |
| 14 Jul 2026 | Treasury Management Quarter 1 ReportRESOLVED that the Treasury Management Performance at the 2026/27 First Quarter Review be noted. | Noted | Open |
| 14 Jul 2026 | Annual Report To CabinetRESOLVED that the report and the work undertaken by the Audit and Standards Committee during the period 01 July 2025 ... | Noted | Open |
| 14 Jul 2026 | Corporate Risk Management 2026/27 Quarter 1 UpdateRESOLVED that the report be noted, and the Council's risk management be considered effective. | Noted | Open |
| 14 Jul 2026 | Exclusion of the Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of Item 9 in accordance with Par... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.