RESOLVED - ( i ) That the scheme and estimate be approved. (ii) That the Service Director, Council Housing, Design and Technical Services be authorised to place an order through the SCAPE Major Works Framework within the agreed overall budget limit. The above decisions have been made for the following reasons: (A) To enable the Council to fulfil its statutory duty to ensure a match between the predicted demand for school places and the number of schools and places maintained, and to ensure efficient use of resources. (B) To meet the required timescale for delivery of the additional school places.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. This report asks Cabinet to approve the scheme and estimate to create a new expanded school on a new site to replace the existing Gibside School.
2. To enable Service Director, Council Housing, Design & Technical Service to place orders through the Scape Major Works Framework in order to deliver the scheme within the restricted timescales and overall budget limit.
Background
3. The Education Act 1996 as amended requires Local Authorities to adopt a strategic role, with a duty to promote choice, diversity and fair access to school provision. This is only possible when there are sufficient numbers of school places situated within the right location.
4. Gibside School is currently located at Burnthouse Lane, Whickham and meets the needs of pupils aged 3 – 11 with profound and multiple learning difficulties. It also meets the needs of pupils with autistic spectrum disorders (ASD) and children with complex communication and medical needs.
5. The school has further developed its Early Years Foundation Stage provision off site at Blaydon/Winlaton Children’s Centre.
6. At present there are 130 children on roll however, despite recently extending the school, the demand for this school from within Gateshead has exceeded the accommodation available. In addition, there are significant transport issues due to the constraints of the Burnthouse Lane site. There is also insufficient space within Blaydon/Winlaton Children’s Centre.
Proposal
7. The proposal is to transfer Gibside school to a new site on the former Shipcote Playing Field (see site boundary attached) and expand its numbers to develop a new build special educational needs school for 170 pupils. 8. The bespoke facility will include hydrotherapy facilities and will cater for the needs of children from the age of 3 – 11 with profound and multiple learning disabilities as well as those with other complex communication and medical needs.
9. The proposal to expand Gibside School from Autumn 2020 will involve a separate statutory consultation process in line with School Organisation legislation.
10. The Council’s Development and Public Protection Service will also carry out a consultation exercise relating to the proposed new build school as part of the Planning Permission Application process.
11. There is a total project budget of £11.6 m which is made up of funding available to the Council and accounted for across the financial years 2018/19 and 2019/20.
12. Cabinet agreed in November 2016 that the Council’s responsibilities for construction work were transferred to The Gateshead Housing Company. The Service Director of Council Housing, Design and Technical Services has consulted with the Managing Director of The Gateshead Housing Company who has advised that the proposals contained within this report will enable TGHC to focus delivery on the housing repairs and maintenance contract, the housing capital programme, new build council housing as well as other non housing work.
13. In order to deliver the requisite additional pupil places by Autumn 2020 it is proposed to deliver the scheme through the Scape Major Works framework.
Recommendations
14. It is recommended that Cabinet:
(i) Approves the scheme and estimate. (ii) Authorise the Service Director of Council Housing, Design and Technical Services to place an order through the SCAPE Major Works Framework within the agreed overall budget limit.
For the following reasons:
(i) To enable the Council to fulfil its statutory duty to ensure a match between the predicted demand for school places and the number of schools and places maintained, and to ensure efficient use of resources. (ii) To meet the required timescale for delivery of the additional school places.
CONTACT: Sandra Watson extension: 3384 APPENDIX 1
Policy Context
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.