Resolved
RESOLVED - That the new banding values for use in calculating the 2019/20 special school budgets was approved.
Gateshead Schools Forum approved this item on Thursday 6 December 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - That the new banding values for use in calculating the 2019/20 special school budgets was approved.
To update Schools Forum on the work that the Special Schools Funding Review (SSFR) group have been undertaking this financial year. This is a sub-group of Schools Forum with the specific purpose to review the special schools funding formula. This report builds on Schools Forum report from February 2018.
The group comprises of all special head teachers and heads of school with input and technical support from a range of officers from Corporate Finance, Educationgateshead, Special Educational Needs and Disabilities Service and other officers as required.
The current special school’s formula is based on work that was undertaken approximately ten years ago and had a phased introduction over 3 years from 2009/10. The pupil based elements were based on the relative needs of children over 5 specialties with 4 levels of need in each specialism. The group developed a range of descriptors that described the “typical” pupil in each speciality for each level of need.
The original formula has been tweaked several times to conform with changes in funding regulations, school developments and pressures.
For the 2018/19 formula the special categories were reduced from 5 to 3 deleting the categories of Sensory Physical and Medical and Communication and Interaction leaving Social Emotional and Mental Health (SEMH), Cognition and Learning (C & L) and Autistic Spectrum Disorder (ASD).
The group worked on reviewing the banding descriptors which details the needs and behaviours of pupils within each specialism and each banding. These were re written, reviewed and agreed by the group.
The next task was to review the staffing requirements of each banding level to determine the levels of relative needs of each pupil. This information is then used to calculate the relative needs of each of the bands. Many meetings have been held to determine this and many models produced.
The model that was chosen and agreed by all the special heads was model 2 as this was least worst option for all schools.
1 of 4 The table below sets out the relative weightings between the different bands.
Level Level Level Level 1 2 3 4
SEMH - Primary 3.810 2.889 1.630 1.000
SEMH - Secondary 3.810 2.593 1.630 1.000
ASD 3.810 3.013 2.259 1.449
Cognition/Learning 3.503 3.013 1.630 1.037
When modelling is undertaken the current year budget is used as a basis and for comparison to understand the probable impact on all schools.
Using the above weightings resulted in the below banding values.
Level 1 Level 2 Level 3 Level 4 SEMH - Primary £10,715.03 £6,283.78 £223.14 -£2,807.58
SEMH - Secondary £10,715.03 £4,858.08 £223.14 -£2,807.58 ASD £10,715.03 £6,878.55 £3,253.85 -£648.35
Cognition/Learning £9,238.09 £6,878.55 £223.14 -£2,628.83
A comparison between the current and proposed banding values is detailed in appendix 1.
To protect special school budgets the minimum funding guarantee (MFG) of minus 1.5% will be applied, to make the formula affordable a capping factor will be applied of 3%. These are applied to the individual special school budget and which is divided by the pupil numbers to give an amount per pupil. Therefore, no school can lose more than 1.5% per pupil or gain more than 3% per pupil.
The table below shows the impact on schools as if the formula had been introduced 2018/19.
Estimated 2018/19 After MFG & School Pupil No. Funding £ Movement Capping Movement % Change DRYDEN 55 £1,259,254 1,349,862 £90,608 £1,297,031 £37,778 3.00% ESLINGTON 60 £1,230,899 1,273,623 £42,724 £1,267,826 £36,927 3.00% FURROWFIELD 73 £1,906,163 1,928,664 £22,502 £1,928,664 £22,502 1.18% GIBSIDE 139.6 £2,947,417 2,826,940 -£120,476 £2,903,206 -£44,211 -1.50% HILLTOP 115 £2,038,708 2,005,994 -£32,714 £2,008,128 -£30,581 -1.50% THE CEDARS 169 £2,549,649 2,547,496 -£2,153 £2,547,496 -£2,153 -0.08%
Total 611.6 £11,932,090 11,932,580 490 11,952,351 20,261
Proposal
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Special Schools Formula UpdateReport | 79 KB | DownloadRead as text |
Follow Gateshead Schools Forum at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Sep 2026 | Alternative Provision Funding for River Tyne AcademyRESOLVED that the information in the report in appendix 1 be noted. | Noted | Open |
| 10 Sep 2026 | Quarter 1 DSG MonitoringRESOLVED that the contents of the report be noted. | Noted | Open |
| 10 Sep 2026 | Department for Education Consultation - Early Years Funding: Proposed Changes to the Entitlements Funding SystemRESOLVED that the response outlined in Appendix 1 be submitted to the DfE's Early Years funding consultation on behal... | Decided | Open |
| 10 Sep 2026 | Department for Education Consultation - Upfront Funding for Mainstream Schools: Creating a Local SEND Inclusion FormulaRESOLVED that the response outlined in Appendix 1 be submitted to the DfE's Local SEND Inclusion Formula consultation... | Decided | Open |
| 10 Sep 2026 | Department for Education Consultation - SEND Reform: Education Otherwise than At SchoolRESOLVED that the EOTAS consultation questions be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.