RESOLVED - ( i ) That the Strategic Director, Corporate Services and Governance be authorised to sign the Delivery Agreement with Kier Services Limited via the SCAPE Minor Works Framework, for the delivery of the Local Studies redevelopment at Central Library. (ii) That the Acting Strategic Director, Communities and Environment, following consultation with the Strategic Directors, Corporate Services and Governance and Corporate Resources, be authorised to agree the final terms, scope and costs of the contract awards. The above decisions have been made for the following reasons: (A) To greatly improve public access to the unique local history archive held at Gateshead Central Library. (B) To allow the implementation of a project that will engage a wide range of community organisations and volunteers in the heritage of Gateshead and the resources held within the collection.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. To seek Cabinet approval to proceed with the placing of orders to commit National Lottery Heritage Fund (NHLF) funding to the value of £499,200 and to provide match funding to the value of £75,762 capital funding to support a project that will improve access to the local studies collection at the Central Library.
Background
2. Council approved the submission of a funding application to Heritage Lottery Fund on 17 July 2018. A successful stage two application was submitted to the Heritage Lottery Fund, now renamed the National Lottery Heritage Fund, for funding to improve access to the local studies collection at the Central Library. This collection comprises over 40,000 items including unique and rare newspapers, maps, books, photographs and pamphlets dating from 1640s to the present day.
3. 95% of the collection is currently kept in secure stacks at the Central Library and as a result the public cannot freely browse the collection and it is under used. It is hard to promote the breadth of the collection or the wealth of material in it.
4. The National Lottery Heritage Fund (NLHF) has approved this stage two application and released £499,200 for the Council to implement the full project. In December the terms of the grant were accepted using delegated powers and the capital allocation from the Council adjusted.
5. The capital project will create a much improved, larger public facility within the Reference section of the Central Library. Around 60% of the collection currently stored in staff areas will become public access, with up to 7,000 books becoming available for the public to browse. Improved study facilities will support easier group and independent research. New interactive terminals will also allow easy access to the unique collection of maps, newspapers and photographs.
6. Digitisation and conservation of the collections will ensure material can increasingly be used online or on our digital interactives to preserve fragile originals. For some larger items (e.g. maps) digitisation work will be outsourced, but an ongoing digitisation programme will also begin inhouse, with up to 20 volunteers contributing to the work and a digitisation area with specialist equipment created.
7. An outreach element and activities programme will promote the collection beyond the Central Library and encourage use of it. A ‘Friends of Gateshead Local Studies’ group will be formed and members will promote the collection in their localities and support a programme of events and activities promoting Gateshead’s heritage. There will be improved use of the local studies archive with schools and community groups. Appendix 1 provides more detail on planned community activities. Project delivery phase
8. The Council engaged Keir Services Limited through the SCAPE Minor Works Framework during the development phase, to provide design assistance and inform the stage two application for project funding. Having secured full funding for the project, it is now proposed to appoint Keir Services Limited for the completion of the delivery phase of capital elements of the project. The capital works are estimated to last for 14 weeks, with works currently scheduled for completion September/ October 2019. The works will be preceded by the replacement of windows in the relevant part of the building. This work will be undertaken outside of the contract to Keir Services Limited and is included in the in-kind capital contribution by the Council.
9. The full delivery phase of the project is scheduled to run for 18 months, giving time for a wide programme of events and community activities as part of an opening programme and celebration of Gateshead’s history.
Recommendations
10. It is recommended that Cabinet:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.