What the committee will consider, in order, with every paper attached to its item.
Cabinet is asked to approve as a correct record the minutes of the last meeting held on 25 June 2019. : The minutes of the last meeting held on 25 June 2019 were approved as a correct record and signed by the Chair.
Report of the Acting Strategic Director, Communities and Environment
Decision: RESOLVED - ( i ) That the submission of a full application for £5.8m of grants to the NE ERDF Low Carbon fund be approved. (ii) That the awarding of contracts to Willmott Dixon Construction Ltd for the design, preconstruction works and pilot installations in relation to the Scheme be approved. (iii) That the Acting Strategic Director, Communities and Environment be authorised, following consultation with the Strategic Director, Corporate Resources, to agree detailed terms, scope of contracts... Decision page
Report of the Acting Strategic Director, Communities and Environment
Decision: RESOLVED - ( i ) That the immediate updating of the Management Agreement by way of a variation letter recording newly agreed performance metrics, reporting and monitoring processes between the Council and Gateshead Housing Company based on Appendices 2 and 3 in the report be approved and the Strategic Director, Communities and Environment be authorised, following consultation with the Leader of the Council and the Cabinet member for Housing, to approve any minor amendments to the proposed... Decision page
Report of the Acting Strategic Director, Community and Environment
Decision: RESOLVED - That Council be recommended to adopt the Enforcement Policy, as set out in appendix 2 to the report. The above decision has been made to ensure that enforcement action is carried out successfully by the Council to protect and promote the health and safety of the public and residents and to protect the environment. Decision page
Report of the Strategic Director, Corporate Resources
Decision: RESOLVED - ( i ) That the Council be recommended to agree all variations to the 2019/20 Capital Programme, as detailed in Appendix 2 to the report, as the revised programme. (ii) That the financing of the revised programme be recommended to the Council. (iii) That it be confirmed to Council that the capital expenditure and capital financing requirement indicators have been revised in line with the revised budget and that none of the approved Prudential Indicators set for 2019/20 have been... Decision page
Report of the Strategic Director, Corporate Resources
Decision: RESOLVED - That the Council’s revenue expenditure position at the end of the first quarter, as set out in Appendix 1, of the report be noted. The above decision has been made to contribute to sound financial management and the long-term financial sustainability of the Council. Decision page
Report of the Chief Executive
Decision: RESOLVED - ( i ) That the recommendations of all the Council’s Overview and Scrutiny Committees in relation to the 2018/19 year-end performance report, as set out in Appendix 4 to the report, be approved. (ii) That it be conformed that the activities undertaken during April 2018 to March 2019 are supporting delivery of the Thrive agenda. The above decisions were made to ensure performance and focus supports the delivery against the strategic approach of Making Gateshead a Place Where Everyone... Decision page
Report of the Strategic Director, Care, Wellbeing and Learning
Decision: RESOLVED - ( i ) That the responses to the consultation exercise be noted. (ii) That Council will continue to support funding for post 16 provision for two years of sixth form for children in the main school of Hill Top and Cedars, and commits to continuing to strengthen the Council’s work with young people and families from Year 9 onwards to identify and secure the most appropriate post 16 pathway which will best prepare individual learners for adulthood and to ensure all children are offered... Decision page
Report of the Strategic Director, Corporate Services and Governance
Decision: RESOLVED - That the Service Director, Corporate Commissioning and Procurement be authorised to invite or negotiate tenders or conduct other procurement processes (or to complete the relevant processes where they have already begun) in respect of the contracts, listed in Appendix 2 to the report, and to award the relevant contracts to the tenderers submitting the most economically advantageous tenders (or otherwise proving successful in accordance with other procurement processes) in accordance... Decision page
Report of the Acting Strategic Director, Communities and Environment
Decision: RESOLVED - That the Acting Strategic Director, Communities and Environment and the Service Director, Council Housing, Design and Technical Services be authorised, in consultation with the Strategic Directors, Corporate Resources and Corporate Services and Governance, to jointly approve the letting of any contracts relating to the Cabinet approved 2019/20 Capital Works Programme which exceed £250,000 in value: such approval is to be in the form of either: (a) an authorisation to invite or... Decision page
Report of the Strategic Director, Corporate Services and Governance
Decision: RESOLVED - That the petitions received and action taken on them be noted. The above decision has been made to inform the Cabinet of the progress of the petitions. Decision page
The Cabinet may wish to exclude the press and public from the meeting during consideration of the following item(s) on the grounds indicated: Item Paragraph of Schedule 12A to the Local Government Act 1972 14 3 15 3 16 3 17 3 18 3 19 3 20 3 21 3
Decision: RESOLVED - That the press and public be excluded from the meeting during consideration of the remaining business in accordance with paragraph 3 of Schedule 12A to the Local Government Act 1972. Decision page
Report of the Acting Strategic Director, Communities and Environment and Strategic Director, Care, Wellbeing and Learning
Decision: RESOLVED - ( i ) That the scheme and estimate be approved. (ii) That the Service Director, Council Housing, Design and Technical Services be authorised to place an order through the SCAPE Major Works Framework within the agreed overall budget limit. The above decisions have been made for the following reasons: (A) To enable the Council to fulfil its statutory duty to ensure a match between the predicted demand for school places and the number of schools and places maintained, and to ensure...
Report of the Acting Strategic Director, Communities and Environment
Decision: RESOLVED - ( i ) That the entering into a contract with WCL be approved , via the Scape Framework for the site enabling works up to the value of £6.7m and the Service Director, Council Housing, Design and Technical Services be authorised to place an order for the works, subject to the form and content of the contract being approved by the Strategic Director, Corporate Services and Governance in accordance with the Constitution. (ii) That the total scheme cost estimates be noted and further...
Report of the Acting Strategic Director, Communities and Environment
Decision: RESOLVED - ( i ) That the progression of initial design and pre- construction work to develop the supporting infrastructure for Gateshead Quays be approved. (ii) That the development of a Gateshead Quays Development Framework to coordinate site development and infrastructure improvements be approved. The above decisions have been made to progress the development of the Gateshead Quays site.
Report of the Acting Strategic Director, Communities and Environment
Decision: RESOLVED - (i) That comprehensive development of the High Street South regeneration area be approved, as set out in the report. (ii) That the provision of a 5 year capital allocation, as detailed in the report, be approved. , (iii) That the Strategic Director, Corporate Services and Governance be authorised, following consultation with the Leader of the Council, and with the Strategic Directors, Communities and Environment and Corporate Resources, to negotiate and agree the necessary legal...
Report of the Acting Strategic Director, Communities and Environment
Decision: RESOLVED - That the Service Director, Council Housing, Design and Technical Services be authorised to place an order with the Gateshead Housing Company, as set out in the report, and enter into a contract for the works with the Gateshead Housing Company, following consultation with the Strategic Director, Corporate Services and Governance. The above decision has been made for the following reasons: (A) Young people needing residential care will be placed within Gateshead rather than being...
Report of the Acting Strategic Director, Communities and Environment, Strategic Director, Corporate Services and Governance and Strategic Director, Corporate Resources
Decision: RESOLVED - ( i ) That the transfer of the freehold interest in the sites at Rowlands Gill and Windy Nook for nil consideration to Gateshead Regeneration Partnership for the provision of new homes be approved. (ii) That the provision of a capital injection, as set out in the report, for these sites to facilitate the delivery of new homes be approved; and that the Council enter into site specific funding agreements with GRP in a form approved by the Strategic Director, Corporate Services and...
Report of the Acting Strategic Director, Communities and Environment and Strategic Director, Corporate Resources
Decision: RESOLVED - ( i ) That the principle of South of Tyne and Wear Energy Recovery Limited revising their funding arrangements in accordance with the provisions contained within the PFI contract be approved. (ii) That the Strategic Director, Corporate Resources be given delegated powers to approve the revisions to the financial model and funding terms, including the calculation of the gain for the Partnership in consultation with the S151 Officers from Sunderland and South Tyneside Councils and in...
Report of the Strategic Director, Corporate Resources
Decision: RESOLVED - ( i ) That the report outlining company activity to date including the contribution to Council Thrive priorities be noted. (ii) That an annual composite report be presented to Cabinet covering the activities of the companies. The above decisions have been were made for the following reasons: (A) To contribute to the sound governance, operational and financial management of the Council’s wholly owned subsidiary companies. (B) To assist effective financial and performance oversight and...
All 15 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 25 June 2019. 1 of its items lead into this meeting; 10 items are new. Point at any item to follow a thread. Procedural items are left out.
Tenders for the Supply of Goods and Services, Revenue Outturn 2018/19, Treasury Annual Report 2018/19, Review to Address Skills Shortages & Increase Employment Opportunities and 7 more do not return this time.
See the 25 June meetingEvery Cabinet meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Gateshead, Cabinet
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Cabinet, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.