Resolved
RESOLVED - i ) That the information be noted ii) The Committee endorsed the effectiveness of the Council’s risk management arrangements
Audit and Standards Committee noted this item on Monday 27 January 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - i ) That the information be noted ii) The Committee endorsed the effectiveness of the Council’s risk management arrangements
1. This report updates the Committee on developments in Corporate Risk Management during the period 1 October to 31 December 2019 in compliance with the requirements of good corporate governance.
2. Quarterly reporting to those with the responsibility for the oversight of risk management issues complies with the principles of good corporate governance. It is also embodied in the Corporate Risk Management Policy, last approved by Council on 21 May 2013. This Policy is kept under review, and whilst it has been amended to reflect changes in Senior Officer titles since that time, it remains relevant and fit for purpose.
3. The report covers developments within the Corporate Risk Management function and any other risk management issues emerging within the quarter under consideration.
4. In November 2018 Cabinet and Council approved the revised Strategic Risk Register which had been presented to Audit and Standards Committee on 1 October 2018.
5. The Register has now been adopted and will be monitored and any actions reported quarterly to Audit and Standards Committee with any significant amendments reported to Cabinet.
6. To reflect ALARM/CIPFA best practice, the internal risk management guidance will be updated to require individual risk owners to be recorded on all risk assessments.
7. Work is ongoing to ensure operational risk management activity within services continues to be aligned with service objectives.
8. Service risk coordinators, whose role it is to support and champion risk management activity within their services are working with the Corporate Risk Officer to support risk owners with evaluating existing operational risk assessments. The focus of this work is on ensuring the assessments contain the required information to inform management response.
Business Continuity 1 9. In accordance with the Council’s Business Continuity Policy, all Services are required to assess the impact of their activities being disrupted and to ensure any continuity plans they have developed are cost effective and adequate.
10. As a test of the existing business continuity planning arrangements across the Council, a short questionnaire was developed and circulated to services. The information is currently being analysed and updates will be provided to Group Management Teams by way of a quarterly update or through service risk coordinators who are members on the Corporate Risk and Resilience Group as appropriate.
Benchmarking
11. To enable comparison with other public sector organisations, the Council participated in the 2019 ALARM/CIPFA Risk Management Benchmarking Club.
12. Membership of the club provides access to a performance measurement tool designed to test the organisation’s performance against the major risk management standards, expectations of inspection bodies and criteria that inform the risk management element of the Annual Governance Statement.
13. The benchmarking question set is based on ALARM’s National Performance Model for Risk Management in Public Services published in 2009. The model breaks down risk management activity into seven strands and aims to provide an in-depth picture of the maturity of risk management within the organisation.
14. Scores of levels 1 to 5 are awarded for each strand to identify the level of maturity that the organisation has reached with level 5 being the highest possible score. The categories are as follows: 1 Awareness 2 Happening 3 Working 4 Embedded and Integrated 5 Driving
15. The benchmarking results for Gateshead over the seven strands are as follows: Leadership and Management 4 Policy and Strategy 4 People 4 Partnerships and Resources 5 Processes 4 Risk Handling and Assurance 4 Outcomes and Delivery 3
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Risk Management 2019/20: Quarterly Report to 31 December 2019Report | 163 KB | DownloadRead as text |
Follow Audit and Standards Committee at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2026 | Treasury Management Annual Report 2025/26RESOLVED that the Treasury Annual Report be submitted to Cabinet. | Decided | Open |
| 14 Jul 2026 | Treasury Management Quarter 1 ReportRESOLVED that the Treasury Management Performance at the 2026/27 First Quarter Review be noted. | Noted | Open |
| 14 Jul 2026 | Annual Report To CabinetRESOLVED that the report and the work undertaken by the Audit and Standards Committee during the period 01 July 2025 ... | Noted | Open |
| 14 Jul 2026 | Corporate Risk Management 2026/27 Quarter 1 UpdateRESOLVED that the report be noted, and the Council's risk management be considered effective. | Noted | Open |
| 14 Jul 2026 | Exclusion of the Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of Item 9 in accordance with Par... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.