Capital Programme and Prudential Indicators 2020/21 – 1st Quarter Review

Approved Committee 7 papers

Council approved this item on Thursday 17 September 2020. Below is the council's own wording, with the papers it was decided on.

ItemCL21

Resolved

RESOLVED - ( i ) That all variations to the 2020/21 Capital Programme be approved as the revised programme. (ii) That the financing of the revised programme be approved. (iii) That the capital expenditure and capital financing requirement indicators have been revised in line with the revised budget and that none of the approved Prudential Indicators set for 2020/21 have been breached.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Council

Purpose of the report

1. This report sets out the latest position on the 2020/21 Capital Programme and Prudential Indicators at the end of the first quarter to 30 June 2020. The report assesses reasons for the variances from the approved programme and details the proposed financing of the capital programme. In addition, the report considers the impact of CIPFA’s Prudential Code on the capital programme and the monitoring of performance against the statutory Prudential Indicators. The report requests that Cabinet recommends to Council that it agrees the revised capital budget and its financing.

Background

2. The original budget for the capital programme for 2020/21, as agreed by Council on 25 February 2020, totalled £110.475m. The first quarter review now projects the year-end expenditure to be £96.792m, £76.266m General Fund and £20.526m HRA.

3. The proposed reduction in the capital programme at the first quarter comprises of the following movements: £m Slippage of planned capital expenditure from 2019/20 14.057 Additional capital expenditure 10.193 Reduced Project Cost (16.380) Re-profiling of capital expenditure to future years (21.553) Total Variance (13.683)

4. A total of £14.057m of slippage has been identified on several key schemes which have been carried forward into 2020/21 with resources from the 2019/20 financial year.

5. The proposed £10.193m increase includes the re-profiling of allocations to reflect the final funding settlement for investment in the Council’s schools and highways infrastructure. The Council has also received notification of additional external funding to support capital investment including £1.2m to increase the housing stocks in the borough. Also included are several additional schemes, which it is proposed are added to the programme to support business critical activity and recovery timelines. Appendix 6 details all additional schemes and the investment requirement in 2020/21 – 2024/25.

1 of 7 6. Planned investment has been re-profiled to future financial years on several schemes, amounting to a reduction of £21.553m. This reduction has been contributed to by the impact of COVID-19 and schemes which have slipped include the following:

 £10.1m in year reduction due to reprofiling of the Clasper Housing Development, whilst work continues to assess financial viability and alternate delivery options.  £3.8m reduction due to reprofiling of Eastwood/ Riverside, the progression of which has been delayed due to COVID-19.  £3.5m reduction due to reprofiling of West Askew Rd, delays incurred on the development of the infrastructure on the site.

Proposal

7. The report identifies planned capital expenditure of £94.341m for the 2020/21 financial year. The expected resources required to fund the Capital Programme are as follows: £m Prudential Borrowing 41.534 Projected Capital Receipts 1.000 Capital Grants and Contributions 33.732 Major Repairs Reserve (HRA) 18.026 Right to Buy Receipts (HRA) 2.500 Total Capital Programme 96.792

8. CIPFA’s Prudential Code advises the regular monitoring of performance against the prudential indicators which regulate borrowing and investment. Targets and limits for the prudential indicators for 2020/21 were agreed at Council on 25 February 2020 and borrowing and investment levels have remained within these limits.

9. The Prudential Code sets out a range of Prudential Indicators that were agreed by the Council on 22 February 2018. Performance against the indicators for 2020/21 is set out in Appendix 5.

Recommendations

10. It is requested that Cabinet recommends to Council that;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CAPITAL Appendix 2 v2Appendix 53 KB Download
PDF
CAPITAL Appendix 3 v2Appendix 52 KB Download
PDF
CAPITAL Appendix 4 v2Appendix 117 KB Download
PDF
CAPITAL Appendix 5 TreasuryAppendix 141 KB Download
PDF
CAPITAL Appendix 6 v2Appendix 181 KB Download
PDF
CAPITAL Capital Monitoring Q1Report 313 KB DownloadRead as text
PDF
Capital Programme and Prudential Indicators 2020/21: 1st Quarter ReviewReport 216 KB Download

At this meeting

Whole meeting

Who was there

62 of 70 attended
AD
Alison DunnCouncil Staff, expected
JA
Councillor John AdamsCommittee Member, present
VA
Councillor Vicky AndersonCommittee Member, present
RB
Councillor Ron BeadleCommittee Member, present
DB
Councillor Dave BradfordCommittee Member, present
MB
Councillor Malcolm BrainCommittee Member, present
CB
Councillor Chris BuckleyCommittee Member, present
DB
Councillor Dot BurnettDeputy Chair, present
LC
Councillor Lynne CaffreyCommittee Member, present
MC
Councillor Marilyn CharltonCommittee Member, present
BC
Councillor Brenda ClellandCommittee Member, present
PC
Councillor Peter CraigCommittee Member, present

All 70 on the meeting page

On this subject at Gateshead

Search all
  1. Capital Programme and Prudential Indicators 2020/21 – 1st Quarter ReviewThis decision
  2. Capital Programme and Prudential Indicators - Year End Outturn 2025-26Noted
  3. Capital Programme and Prudential Indicators - First Quarter Review 2026-27Approved
  4. Capital Programme and Prudential Indicators – Year End Outturn 2025-26Approved
  5. Capital Programme and Prudential Indicators – First Quarter Review 2026-27Approved
  6. Transport Capital Programme Year End ReportApproved

More from Gateshead Council

All decisions
MeetingDecisionOutcome
16 Jul 2026 To confirm the Minutes of the meeting held 4 June 2026i. That the minutes of the meeting held on 4 June 2026 be approved. Approved Open
16 Jul 2026 Capital Programme and Prudential Indicators - Year End Outturn 2025-26i. That the Capital Programme Outturn for 2025/26 be noted; ii. That the financing of the Capital Programme be approv... Noted Open
16 Jul 2026 Capital Programme and Prudential Indicators - First Quarter Review 2026-27i. That all variations to the 2026/27 Capital Programme as detailed in appendix 2 be approved; ii. That the financing... Approved Open
4 Jun 2026 To confirm the Minutes of the meeting held on 19 March 2026 and on 29 May 2026i. That the minutes of the meeting held on 19 March 2026 and on 29 May 2026 be approved. Approved Open
4 Jun 2026 Post-16 Strategyi. that the Post-16 Education Strategy for Gateshead be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies