Resolved
RESOLVED - i ) That the information be noted. ii) The Committee endorsed the effectiveness of the Council’s risk management arrangements
Audit and Standards Committee noted this item on Monday 19 October 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - i ) That the information be noted. ii) The Committee endorsed the effectiveness of the Council’s risk management arrangements
1. This report updates the Committee on Corporate Risk Management developments during the period 1 July 2020 to 30 September 2020.
2. Quarterly reporting to those with the responsibility for the oversight of risk management issues complies with the principles of good corporate governance. It is also embodied in the Corporate Risk Management, last approved by Council on 21 May 2013, which is kept under review, and whilst it has been amended to reflect changes in Senior Officer titles since that time, it remains relevant and fit for purpose.
3. The report covers progress against the Corporate Risk Management Developmental Objectives for 2020/21 as cited in the Corporate Risk Management Annual Report 2019/20 and any other risk management issues emerging within the quarter under consideration.
Strategic Risk Management
4. In November 2018 Cabinet and Council approved a revised Strategic Risk Register which had been presented to Audit and Standards Committee on 1 October 2018. The Corporate Management Team has continued to ensure strategic risks are responded to in accordance with the Risk Management Policy, with risks and controls being recorded for inclusion within the Strategic Risk Register. As part of the iterative nature of the Register, risk owners are asked to provide updates as part of the quarterly reviews which are reported to Committee as part of the quarterly updates.
5. There have been no changes to the Strategic Risk Register in the second quarter. The Strategic Risk Register is attached for information in Appendix 1.
Operational Risk Management
6. Operational risks identified within the Council are recorded on the operational risk register. Work is ongoing to ensure operational risk management activity within services continues to align with service objectives including those risks specific to operational objectives as a consequence of the Council’s priorities in response to COVD 19 and EU transition.
7. Service risk coordinators, whose role it is to support and champion risk management activity within their Services are working with the Corporate Risk Officer to support risk owners with evaluating existing operational risk assessments. The focus of this work is on ensuring the assessments contain the required information to inform management response.
Business Continuity Management
8. In accordance with the Council’s Risk Management and Business Continuity Policies, all services are required to continuously assess the risk of their activities being disrupted and to develop cost effective continuity plans.
9. All Business Impact Assessments were reviewed by Services in early March to identify the critical activities in the event of a Pandemic and revise Business Continuity Plans accordingly to mitigate as far as possible any threats to delivery of these key activities that could not be interrupted for more than 5 to 10 days without the impact being critical. This process was revisited in early April to identify those activities where service interruption would be critical if it was for longer than 10 days, up to three months. This Business Impact Assessments are currently being revisited to ensure they adequately reflect and address both the current position and the likely pressures facing the Council as we move into the Winter season.
10. Quarterly audit and risk reports are provided to Group Management Teams which also highlight the activities for which services have developed continuity plans. Issues can also be reported in by Services represented on the Corporate Risk and Resilience Group.
Corporate Risk and Resilience Group
11. The Corporate Risk and Resilience Group last met 5 October 2020, the following items were considered:
COVID-19 EU Transition Updates from Groups and Services
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
03 Appendix 1Appendix | 285 KB | Download |
PDF |
Corporate Risk Management 2020/21 Quarter 2 UpdateReport | 155 KB | DownloadRead as text |
Follow Audit and Standards Committee at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2026 | Treasury Management Annual Report 2025/26RESOLVED that the Treasury Annual Report be submitted to Cabinet. | Decided | Open |
| 14 Jul 2026 | Treasury Management Quarter 1 ReportRESOLVED that the Treasury Management Performance at the 2026/27 First Quarter Review be noted. | Noted | Open |
| 14 Jul 2026 | Annual Report To CabinetRESOLVED that the report and the work undertaken by the Audit and Standards Committee during the period 01 July 2025 ... | Noted | Open |
| 14 Jul 2026 | Corporate Risk Management 2026/27 Quarter 1 UpdateRESOLVED that the report be noted, and the Council's risk management be considered effective. | Noted | Open |
| 14 Jul 2026 | Exclusion of the Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of Item 9 in accordance with Par... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.