RESOLVED - That the Service Director, Corporate Commissioning and Procurement be authorised to invite or negotiate tenders or conduct other procurement processes (or to complete the relevant processes where they have already begun) in respect of the contracts listed in appendix 2 to the report and to award the relevant contracts to the tenderers submitting the most economically advantageous tenders (or otherwise proving successful in accordance with other procurement processes) in accordance with the Contract Procedure Rules. The above decision has been made to enable the procurement of goods, works and services required for the efficient and effective delivery of services.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. Cabinet is asked to consider and approve the procurement and award of the contracts listed in appendix 2.
Background
2. On 21st May 2019, it was agreed by Cabinet, a procurement and contract reports would be considered by Cabinet approximately twice per year.
3. On 24th March 2020, Cabinet approved a report on procurement and contracts report containing a number of contracts which had already been awarded through delegated authority, or were likely to be tendered (or procured via another means), during the next six months (or beyond) and cabinet approval was sought to invite or negotiate tenders, or to conduct some other procurement process, and to award the contract in accordance with the outcome of the procurement evaluation.
Proposal
4. The contracts listed in appendix 2 are at various stages of the procurement cycle. The first table includes contracts that have either already been awarded or are no longer required as described in “progress since March 2020” column. These contracts will not appear on the next report to Cabinet.
5. The second table includes contracts that exceed £250k in value and require Cabinet approval to invite tenders or undertake some other procurement process (including using existing frameworks that have been let by other organisations, or directly award contracts where there is justification to do so), in accordance with the Contract Procedure Rules and to continue the process through to award of contract.
6. The third table includes a number of contracts that are at the early planning stage and therefore authorisation is requested to invite tenders or undertake some other procurement process (for example use existing frameworks that have been let by other organisations, or directly award contract where there is justification to do so) in accordance with the Contract Procedure Rules and to continue the process through to award of contract. The contract value is not known at this stage and some contracts will exceed £250k in value and others will be less than this value. There is also a possibility that some of the procurements may not progress.
1 of 5 7. In order to provide a complete picture of procurement activity, a list of contracts that do not require Cabinet approval due to their value, or because they are being undertaken on behalf of the Gateshead Housing Company or a school, is included for information and to enable Councillors to influence them should they wish to do so.
8. Councillors may also note that some contracts have been extended due to Covid-19 and these are highlighted in the appropriate table. Decisions to extend contracts were based on the Council’s capacity to undertake this work at the time it was required, and/or the ability of specific markets to respond to the tender opportunities.
Recommendations
9. It is recommended that the Service Director, Corporate Commissioning and Procurement be authorised to invite or negotiate tenders or conduct other procurement processes (or to complete the relevant processes where they have already begun) in respect of the contracts listed in appendix 2 and to award the relevant contracts to the tenderers submitting the most economically advantageous tenders (or otherwise proving successful in accordance with other procurement processes) in accordance with the Contract Procedure Rules.
For the following reason:
To enable the procurement of goods, works and services required for the efficient and effective delivery of services.
CONTACT: Andrea Tickner extension: 5995
2 of 5 APPENDIX 1
Policy Context
1. To deliver efficient and effective services, and the Council’s Thrive agenda it is necessary for the Council to procure a wide variety of goods, works and services from a range of external organisations in accordance with the Corporate Commissioning and Procurement Strategy 2016-2021
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.