Resolved
(i) The Committee noted the progress made within the report.
Corporate Resources Overview and Scrutiny Committee noted this item on Monday 14 June 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
(i) The Committee noted the progress made within the report.
This report provides an update on the operation of Gateshead District Energy Scheme, by Gateshead Energy Company, since starting full operation in February 2018, and an update on Gateshead Energy Company’s 5 year business plan.
1. Gateshead Energy Company (GEC) was incorporated in October 2015 specifically to manage and operate the Gateshead District Energy Scheme. The heat network was designed to expand to meet the full needs of all new development in and around Gateshead Town centre (See Appendix 1 for the full network masterplan)
2. In April 2016, GEC and the Council signed a 40-year concession contract, which sets out the terms of operation, in which the GEC leases assets from the Council and takes sole responsibility of operating and managing all technical and commercial activities.
3. In addition to the operation of the energy scheme, other objectives were set out at the time of incorporation, which included policy priority outcomes for residents: • Attracting economic growth • Cost savings for commercial customers in the borough • Reductions in fuel poverty for residents • Carbon reduction in the borough • Income generation for the Council
4. Regarding governance, GEC is a subsidiary of Gateshead Energy Holdings Ltd (GEH). This structure allows other ventures to be created under GEH, if required. Following CMT agreement to increase Board membership from three to five, two additional directors have been appointed. Current Board membership is as follows:
• Andrew Marshall (Chair) • John Shiel (replaced Darren Collins, from 22 October 2020 • Mike Barker • Alison Dunn (from 26 November 2019) • Andrea Tickner (from 26 November 2019)
5. A Members Advisory Panel was established to advise the Board, and meets the week prior to all board meetings, to consider Board business and make recommendations. The Panel comprise Deputy Leader and three members on Transport and Environment Portfolio. GEC Board itself meets quarterly with arrangements in place where decisions are needed between Board meetings. These are followed up by decision records presented at the subsequent board meeting. 6. Day to day operations are led by Jim Gillon, Energy Services Manager, acting as the nominated representative for GEC. Peter Udall, as Strategic Director for Economy, Innovation and Growth, acts the Council’s representative under the Concession Agreement.
Operational Update
7. Key operational progress since commencement are set out below: • Heat and power supply commenced in Feb 2018, to core customers • From Summer 2018, Gateshead Leisure Centre, Library, Shipley Art Gallery and Talmudical College were connected, as well as 159 flats in Regent Court • From Oct 2019, GEC became the first small scale CHP generator to participate in the UK’s Balancing Mechanism, securing revenue from being available to turn on / off, at 30 mins notice, to balance the grid • Further new customers were completed to two additional Council buildings (PROTO and Baltimore House) and the first new build connection for heat/power to RIGA office building was completed in March 2020. • Most recently, the new Gibside Special School was connected to the heat network in early 2021 • The current list of customers is provided in Appendix 1. • In addition, GEC has commercial connection offers issued to a number of potential customers: ◦ Gateshead Quays (due 2024) ◦ Mutli Storey Car Park (due 2022) ◦ Speculative Office 2 (Baltic Quarter) – awaiting decision if this will be constructed ◦ Park Rd, Shearlegs Rd, Gateshead Stadium, Gateshead Academy of Sport (due end 2021) ◦ Freight Depot – (due 2022-2025)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Gateshead District Energy Scheme: Operations Update and 5 Year Business PlanReport | 1.6 MB | DownloadRead as text |
Follow Corporate Resources Overview and Scrutiny Committee at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jun 2026 | Performance Management and Improvement FrameworkRESOLVED that: i) The contents of the Annual Report at Appendix 1 be noted; ii) The additional information available ... | Noted | Open |
| 22 Jun 2026 | Work Programme 2026/27RESOLVED that: i) The proposed work programme items to date be noted; ii) Committee Members should share their views ... | Noted | Open |
| 2 Apr 2026 | Information Governance Annual ReportRESOLVED that the report be noted. | Noted | Open |
| 12 Jan 2026 | Budget Outturn Performance ReportRESOLVED that the report be noted. | Noted | Open |
| 10 Nov 2025 | Annual Workforce Strategy ReportRESOLVED that Corporate Resources OSC: i. Noted the report ii. Supported the delivery of the Corporate Workforce Stra... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.