RESOLVED - ( i ) That the proposed updated package for the proposed Clean Air Zone, including mitigation measures, as set out in the report be noted. (ii) That the updated timeline for the delivery of the scheme as set out in the report be noted. The above decisions have been made to improve air quality in Gateshead and Newcastle.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. Cabinet has previously agreed that the Council’s approach in responding to the Government’s legal Directions to improve air quality in the shortest possible time should look more broadly than government’s narrow focus. 2. Since consultation in 2019 and development of the proposed approach, work has continued on updating the Full Business Case for the Clean Air Zone to account for changes in air pollution. 3. This report updates Cabinet on the proposed preferred option and timeline for implementation. 4. The updated package is a Clean Air Zone Class C and, subject to government funding, a wide range of mitigation and support measures including grants for affected businesses and individuals.
Background
5. Outdoor air pollution is a major risk to human health. As outlined in previous reports to Cabinet, based on national estimates, poor air quality is considered to be responsible for hundreds of deaths each year across Gateshead and Newcastle, as well as thousands across the country. The main cause of roadside Nitrogen Dioxide is road transport, which also has wider impacts on public health and is a significant contributor to carbon emissions and climate change. 6. In 2020, following decisions from Cabinet and Full Council, a draft Full Business Case was submitted to the Government’s Joint Air Quality Unit (JAQU). This was based around the introduction of a Clean Air Zone Class C, alongside traffic restrictions (reducing lanes and removing some access) on the Tyne Bridge and Central Motorway East at New Bridge Street, as well as in Gateshead. It also included a funding request of £60m to cover operation of the scheme, mitigation of any impacts and support people and businesses. 7. In March 2020, the Councils received a provisional funding allocation of £20m from the Government, this included £4.0m to operate the scheme and £15.0m for mitigation. At the same time the Government issued a new legal Direction. 8. The Council is continuing to work with Joint Air Quality Unit and is seeking to ensure that the steps towards NO2 compliance is achieved in the shortest possible time and that exposure to levels above the legal limit to nitrogen dioxide are reduced as quickly as possible.
Proposal
9. As part of the Government’s requirements to update modelling to account for the passage of time and the impact of Covid-19, a number of additional tests were run for 2022 to establish compliance. 10. The updated transport and air quality modelling has indicated that: A Clean Air Zone Class C, without further traffic restrictions, is likely to achieve compliance with legal limits for air pollution in 2022 on all roads. Additional traffic restrictions are not required for air quality compliance and therefore the plan is likely to lead to lower levels of rerouting. These changes mean that the plan is also likely to lead to lower total carbon, particulate and nitrogen dioxide emissions than previously expected. 11. Consequently, this is likely to be the Councils’ preferred option. We are working with government on that basis, and subject to approval of the Full Business Case by Cabinet in September 2021. 12. The current estimate for the launch of the Clean Air Zone Class C is in July 2022. There may be some refinements to this date based on national capacity to support launches of Clean Air Zones, given that others are going live in this time period.
Recommendations
13. It is recommended that Cabinet: (i) Note the proposed updated package for the proposed Clean Air Zone, including mitigation measures. (ii) Note the updated timeline for the delivery of the scheme.
For the following reason: To improve air quality in Gateshead and Newcastle
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.