Resolved
RESOLVED - (i) that the comments of the Committee be noted. ... view the full minutes text for item CR49
Corporate Resources Overview and Scrutiny Committee noted this item on Monday 11 October 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - (i) that the comments of the Committee be noted. ... view the full minutes text for item CR49
CORPORATE RESOURCES OVERVIEW & SCRUTINY COMMITTEE 11 October 2021
TITLE OF REPORT: Budget Savings Delivery 2021
REPORT OF: Darren Collins, Strategic Director, Resources and Digital
SUMMARY This report provides the Committee with an update on the achievement of in year budget savings for 2021/22. _____________________________________________________________________ Background
1. Up to and including 2020/21 the Council has delivered £170.4m of budget cuts cumulatively.
2. On 25 February Cabinet and Council agreed a revenue budget of £238.758m which included £8.117m of budget savings for 2021/22. Unlike in previous years formal consultation on how these savings are delivered in specific areas was to take place during 2021/22 to action some of the savings. Temporary funding for mitigation was agreed for some of the savings to allow the time needed for the activity and consultation.
3. It is important that activity in these areas are closely monitored both to minimise the mitigations required but also to achieve clarity and assurance that by March 2022 all savings values agreed by Cabinet and Council are achieved and do not contribute to the financial gap in future years.
4. In addition, some areas of budget savings that were agreed by Cabinet and Council for 2020/2021 remain undelivered due to activity having to be paused in year due to the pandemic. These were in relation to contract savings across the Council and savings from a move to a corporate landlord model of ensuring a productive use of land and assets to deliver Thrive outcomes. Due to the value these areas remain under review to monitor actions to ensure they are achieved.
5. As part of the Council’s budget and policy framework Cabinet receives quarterly reports on performance against the agreed revenue budget which includes savings delivery. The Corporate Management Team also receive regular updates on budget savings delivery in order to monitor progress and hold lead officers to account.
6. Corporate Resources Scrutiny Committee is being asked to consider this report and review progress of delivery of savings. Savings History
7. £170.4m budget cuts have been delivered to date in the following areas;
*please note any savings achieved within the public health grant ringfence are not included in this analysis
8. To satisfy its legal requirement to balance the budget the Council must make spending plans affordable by matching them to the estimated funding available over that time. Action is required now to enable the Council to legally balance the budget for both next year and in future years. The Council has a track record of meeting its financial obligations and maintaining financial sustainability through delivery within budget. This is shown in the table below; Progress and Implementation
9. Progress against savings is shown below for information. Significant savings considered partially achieved or projected to be undelivered are summarised with more details included at appendix 1.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Budget Savings Delivery 2021Report | 278 KB | DownloadRead as text |
Follow Corporate Resources Overview and Scrutiny Committee at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jun 2026 | Performance Management and Improvement FrameworkRESOLVED that: i) The contents of the Annual Report at Appendix 1 be noted; ii) The additional information available ... | Noted | Open |
| 22 Jun 2026 | Work Programme 2026/27RESOLVED that: i) The proposed work programme items to date be noted; ii) Committee Members should share their views ... | Noted | Open |
| 2 Apr 2026 | Information Governance Annual ReportRESOLVED that the report be noted. | Noted | Open |
| 12 Jan 2026 | Budget Outturn Performance ReportRESOLVED that the report be noted. | Noted | Open |
| 10 Nov 2025 | Annual Workforce Strategy ReportRESOLVED that Corporate Resources OSC: i. Noted the report ii. Supported the delivery of the Corporate Workforce Stra... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.