Corporate Risk Management 2021/22 - Quarter 2 Update

Noted Finance 1 paper

Audit and Standards Committee noted this item on Monday 18 October 2021. Below is the council's own wording, with the papers it was decided on.

ItemASC358

Resolved

RESOLVED - i ) That the information be noted ii) The Committee requested a briefing note be prepared on the impact of COVID 19 and Brexit and what the Council is doing to address and mitigate any problems iii) The Committee endorsed the effectiveness of the Council’s risk management arrangements
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Audit and Standards Committee

Purpose of the report

1. This report updates the Committee on Corporate Risk Management developments during the period 1 July 2021 to 30 September 2021.

Background

2. Quarterly reporting to those with the responsibility for the oversight of risk management issues complies with the principles of good corporate governance. It is also embodied in the Corporate Risk Management Policy. This was last approved by Council on 21 May 2013 and is kept under review. Whilst it has been amended to reflect minor structural changes and roles in that time, it remains relevant and fit for purpose.

3. The report covers progress against the Corporate Risk Management Developmental Objectives for 2021/22, as cited in the Corporate Risk Management Annual Report 2020/21, and any other risk management issues emerging within the quarter under consideration.

Strategic Risk Management

4. In November 2018, Cabinet and Council approved a revised Strategic Risk Register which had been presented to Audit and Standards Committee on 1 October 2018. The Corporate Management Team has continued to ensure strategic risks are responded to in accordance with the Risk Management Policy, with risks and controls being recorded for inclusion within the Strategic Risk Register.

5. There have been no changes to the Strategic Risk Register in the second quarter 2021/22. The current Strategic Risk Register is attached for information in Appendix 1.

Operational Risk Management

6. Operational risks identified within the Council are recorded on the operational risk register. Work is ongoing to ensure operational risk management activity within services continues to align with service objectives, including those risks specific to operational objectives.

7. Service Risk Coordinators, whose role it is to support and champion risk management activity within their Services, are working with the Corporate Risk Officer to support risk owners with evaluating existing operational risk assessments. The focus of this work is on ensuring the assessments contain the required information to inform the management response.

Business Continuity Management

8. In accordance with the Council’s Risk Management and Business Continuity Policies, all Services are required to continuously assess the risk of their activities being disrupted and to develop cost effective business continuity plans.

9. All Business Impact Assessments were reviewed by Services in March 2020, again in November 2020 and most recently in May 2021. This was to continue to identify threats to critical activities and potential increased demand on Council Services following a further wave of infections. Business Continuity Plans were also revised accordingly to mitigate, as far as possible, any threats to the delivery of key activities with a focus on activity that could not be interrupted for more than 48 hours without critical impact. This exercise was also used to assess which activities might require additional support to strengthen resilience and estimated the officer numbers and skills that might be needed.

10. This process has been further strengthened since mid August with weekly updates by exception requested of Service Directors regarding the short term assessment of resilience in respect of their critical activities to provide CMT of assurance in relation to critical activities, and also highlight areas where additional support may be necessary.

11. Quarterly audit and risk reports are provided to Group Management Teams to highlight the activities for which Services have developed continuity plans.

Corporate Risk and Resilience Group

12. The Corporate Risk and Resilience Group last met 11 October 2021. The following items were considered:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Risk Management 2021/22: Quarter 2 UpdateReport 234 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 26 attended
GM
Ged MortonCouncil Staff, expected
AD
Alison DunnCouncil Staff, expected
SC
Sarah CoxonOfficer, expected
NP
Neil PorteousOfficer, expected
MC
Councillor Marilyn CharltonChair, present
RB
Councillor Ron BeadleCommittee Member, apologies
LG
Councillor Linda GreenCommittee Member, present
SG
Councillor Stuart GreenCommittee Member, present
HK
Councillor Hugh KellyCommittee Member, apologies
JM
Councillor John McElroyCommittee Member, present
SB
Mr Stuart Bell (Independent Member)Committee Member, present
GC
Mr George Clark (Independent Member)Committee Member, present

All 26 on the meeting page

On this subject at Gateshead

Search all
  1. Corporate Risk Management 2021/22 - Quarter 2 UpdateThis decision
  2. Corporate Risk Management 2026/27 Quarter 1 UpdateNoted
  3. Corporate Risk Management Annual Report 2025/26Noted
  4. Corporate Risk Management 2025/26 - Quarter 4 UpdateDecided
  5. Corporate Risk Management 2025/26 Quarter 3 UpdateNoted
  6. Corporate Risk Management Annual Report 2024/25Noted

More from Gateshead Audit and Standards Committee

All decisions
MeetingDecisionOutcome
14 Jul 2026 Treasury Management Annual Report 2025/26RESOLVED that the Treasury Annual Report be submitted to Cabinet. Decided Open
14 Jul 2026 Treasury Management Quarter 1 ReportRESOLVED that the Treasury Management Performance at the 2026/27 First Quarter Review be noted. Noted Open
14 Jul 2026 Annual Report To CabinetRESOLVED that the report and the work undertaken by the Audit and Standards Committee during the period 01 July 2025 ... Noted Open
14 Jul 2026 Corporate Risk Management 2026/27 Quarter 1 UpdateRESOLVED that the report be noted, and the Council's risk management be considered effective. Noted Open
14 Jul 2026 Exclusion of the Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of Item 9 in accordance with Par... Decided Open