RESOLVED - (i) That a six week public consultation on the SPD and masterplan (and any subsequent consultation) be approved. (ii) That the Strategic Director, Economy, Innovation & Growth, following consultation with the Cabinet Member for Environment and Transport, be authorised to make any amendments to the SPD and masterplan, following the public consultation. (iii) That a further report be submitted to Cabinet following the consultation, recommending Council approval and adoption of the final version of the SPD and masterplan. The above decisions have been made for the following reasons: (A) To comply with the Town and Country Planning (Local Planning) (England) Regulations 2012 and the Council’s SCI and to ensure consistency with consultation on previous SPDs. (B) To ensure that new development and infrastructure for the Exemplar Neighbourhood comes forward in a comprehensive and coordinated way and to provide further guidance on current Core Strategy and Urban Core Plan policies relating to the site.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. To request Cabinet to approve public consultation on the Exemplar Neighbourhood (EN) Supplementary Planning Document (SPD) and masterplan.
Background
2. The EN covers a large area of land including the High Street South area, the former Chandless Estate, the former freight depot site, the former Go-Ahead bus depot and the office blocks at Tynegate Precinct. It is bisected by the Gateshead Highway flyover.
3. The Core Strategy and Urban Core Plan (CSUCP) allocates the entirety of the EN site for at least 1000 homes at an average density of 50 dwellings per hectare across the site.
4. Development that has taken place on site so far has been the Aldi supermarket on Sunderland Road, the conversion of Chad House to 89 apartments and the temporary conversion of Bede House to a school. Planning permission has been granted for 300 homes on the former Freight Depot and resolved to be granted for 26 homes on the former Go-Ahead bus depot.
5. The existing SPD (and part 2 (vi) of policy SG2 of the CSUCP) included the potential for a new pedestrian/cycle bridge link over the railway line that separates the Chandless area from the freight depot area. The rail bridge was hoped to be delivered as part of the Freight Depot development to improve pedestrian and cycle movement east and west. The cost and land take of the bridge proved to be prohibitive (approx. £1.3 million) and as such is undeliverable.
6. The existing EN SPD and masterplan was approved in 2013. Given the passage of time since approval of the SPD and masterplan and the development that has taken place on the site and costs of the railway bridge it is considered necessary for the SPD and masterplan to be updated. 7. In 2020, Ian Darby Partnership (IDP) were appointed to update the SPD and masterplan following a competitive tender process.
8. Following consultation with Environment and Transport Portfolio in January 2021 IDP conducted their own informal consultation exercise. This exercise informed the current draft of the SPD and masterplan which is available at www.gateshead.gov.uk/Gateshead-Exemplar-Neighbourhood-Masterplan-and-SPD.
9. In accordance with the Town and Country Planning (Local Planning) (England) Regulations 2012, the Council’s own Statement of Community Involvement (SCI) and consultation on previous SPDs it is proposed to carry out a 6-week public consultation on the draft SPD and masterplan. This will be using a variety of methods such as social media, e-mail and on-line. The Council is then required to take account of any representations made and, if necessary, carry out additional public consultation (this can be less than 6 weeks) and amend the documents. The final decision whether to adopt the SPD and masterplan will need to be taken by full Council.
Recommendation
10. It is recommended that Cabinet:
i. Authorises public consultation to take place on the SPD and masterplan (and any subsequent consultation).
ii. Delegates authority to the Strategic Director, Economy, Innovation & Growth, in consultation with the Cabinet Member for Environment and Transport, to make any amendments to the SPD and masterplan, following the public consultation.
For the following reasons:
i. To comply with the Town and Country Planning (Local Planning) (England) Regulations 2012 and the Council’s SCI and to ensure consistency with consultation on previous SPDs.
ii. To ensure that new development and infrastructure for the Exemplar Neighbourhood comes forward in a comprehensive and coordinated way and to provide further guidance on current CSUCP policies relating to the site.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.