Resolved
RESOLVED - i ) That the information be noted ii) The Committee endorsed the effectiveness of the Council’s risk management arrangements
Audit and Standards Committee noted this item on Monday 31 January 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - i ) That the information be noted ii) The Committee endorsed the effectiveness of the Council’s risk management arrangements
1. This report updates the Committee on Corporate Risk Management developments during the period 1 October 2021 to 31 December 2021.
2. Quarterly reporting to those with the responsibility for the oversight of risk management issues complies with the principles of good corporate governance. It is also embodied in the Corporate Risk Management Policy. This was last approved by Council on 21 May 2013 and is kept under review. Whilst it has been amended to reflect minor structural changes and roles in that time, it remains relevant and fit for purpose.
3. The report covers progress against the Corporate Risk Management Developmental Objectives for 2021/22, as cited in the Corporate Risk Management Annual Report 2020/21, and any other risk management issues emerging within the quarter under consideration.
Strategic Risk Management
4. In November 2018, Cabinet and Council approved a revised Strategic Risk Register which had been presented to Audit and Standards Committee on 1 October 2018. The Corporate Management Team has continued to ensure strategic risks are responded to in accordance with the Risk Management Policy, with risks and controls being recorded for inclusion within the Strategic Risk Register.
5. There have been no changes to the Strategic Risk Register in the third quarter 2021/22. The current Strategic Risk Register is attached for information in Appendix 1.
Operational Risk Management
6. Operational risks identified within the Council are recorded on the operational risk register. Work is ongoing to ensure operational risk management activity within services continues to align with service objectives, including those risks specific to operational objectives.
7. Service Risk Coordinators, whose role it is to support and champion risk management activity within their Services, are working with the Corporate Risk Officer to support risk owners with evaluating existing operational risk assessments. The focus of this work is on ensuring the assessments contain the required information to inform the management response.
Business Continuity Management
8. In accordance with the Council’s Risk Management and Business Continuity Policies, all Services are required to continuously assess the risk of their activities being disrupted and to develop cost effective business continuity plans.
9. All Business Impact Assessments were reviewed by Services in March 2020, November 2020, May 2021 and most recently November 2021. This was to continue to identify threats to critical activities and potential increased demand on Council Services following a further wave of infections. Business Continuity Plans were also revised accordingly to mitigate, as far as possible, any threats to the delivery of key activities with a focus on activity that could not be interrupted for more than 48 hours without critical impact. This exercise was also used to assess which activities might require additional support to strengthen resilience and estimated the officer numbers and skills that might be needed.
10. This process has been further strengthened through the autumn with weekly updates by exception requested of Service Directors and Service Risk Champions regarding the short-term assessment of resilience in respect of their critical activities to provide CMT of assurance in relation to critical activities, and also highlight areas where additional support may be necessary.
11. Quarterly audit and risk reports are provided to Group Management Teams to highlight the activities for which Services have developed continuity plans.
Corporate Risk and Resilience Group
12. The Corporate Risk and Resilience Group has met monthly and last met 18 January 2022. The following items were considered:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Risk Management 2021/22: Quarter 3 UpdateReport | 233 KB | DownloadRead as text |
Follow Audit and Standards Committee at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2026 | Treasury Management Annual Report 2025/26RESOLVED that the Treasury Annual Report be submitted to Cabinet. | Decided | Open |
| 14 Jul 2026 | Treasury Management Quarter 1 ReportRESOLVED that the Treasury Management Performance at the 2026/27 First Quarter Review be noted. | Noted | Open |
| 14 Jul 2026 | Annual Report To CabinetRESOLVED that the report and the work undertaken by the Audit and Standards Committee during the period 01 July 2025 ... | Noted | Open |
| 14 Jul 2026 | Corporate Risk Management 2026/27 Quarter 1 UpdateRESOLVED that the report be noted, and the Council's risk management be considered effective. | Noted | Open |
| 14 Jul 2026 | Exclusion of the Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of Item 9 in accordance with Par... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.