RESOLVED - (i) That the Council be recommended to agree all variations to the 2022/23 Capital Programme as detailed in appendix 2 to the report. (ii) That the Council be recommended to approve the financing of the revised programme as set out in the report. (iii) That it be confirmed to Council capital expenditure and financing requirements have been revised in line with the amended budget and none of the approved Prudential Indicators set for 2022/23 have been breached. (iv) That the Strategic Director, Economy, Innovation and Growth, in consultation with the Strategic Director, Corporate Services and Governance and the Strategic Director, Resources and Digital be given delegated authority for the negotiation and approval of the tender and contract award for the floodlighting works at Gateshead International Stadium within the agreed capital programme allocation of £0.5m. The above decisions have been made for the following reasons: (A) To ensure the optimum use of the Council’s capital resources in 2022/23. (B) To accommodate changes to the Council’s in-year capital expenditure plans. (C) To ensure performance has been assessed against the approved Prudential Limits. (D) In respect of (iv) above, to allow the contract for the works to be entered into and works completed prior to the start of the new football season.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. This report sets out the latest position on the 2022/23 Capital Programme and Prudential Indicators at the end of the first quarter to 30 June 2022. The report assesses reasons for the variances from the approved programme and details the proposed financing of the capital programme. In addition, the report considers the impact of CIPFA’s Prudential Code on the capital programme and the monitoring of performance against the statutory Prudential Indicators.
Background
2. The original budget for the capital programme for 2022/23, as agreed by Council on 25 February 2022, totalled £146.7m. The first quarter review now projects the year-end expenditure to be £103.2m, £80.9m General Fund and £22.3m HRA.
3. The proposed reduction in the capital programme at the first quarter comprises of the following movements: £m Slippage of planned capital expenditure from 2021/22 3.598 Increased borrowing/external funding/contributions 4.734 Other movements (0.248) Re-profiling of capital expenditure to future years (51.550) Total Variance (43.466)
4. A total of £5.8m of slippage was identified in 2021/22 on several key schemes, which were carried forward into 2022/23 including:
£2.115m Quays Development. Scheme design and enabling works continue to be progressed however there has been a re-profiling of the construction works given current market volatility. £1.090m School Condition Investment, progress was held up due to supply chain issues, but this should be spent in year with works planned. £1.121m Sister Winifred Laver PIC following a 14-week delay in construction but works are ongoing.
1 of 5 £0.769m Gateshead Multi Storey Carpark, following construction delays but works are progressing well. £0.526m Gateshead District Heat Network, slippage to deliver the Academy of Sport works.
5. The increased borrowing of £4.7m comprises of a £4.2m loan to the Gateshead Energy Company for the District Energy Extension, which is the remainder of the £7m loan agreed by Cabinet, and £0.5m for the Gateshead International Stadium.
6. The £0.5m, detailed in paragraph 5 of this report, has been added to the programme in Quarter 1 for the floodlighting at the Gateshead International Stadium. This scheme originally formed part of the Capital Programme for 2019/20 to 2023/24, and was approved by Cabinet on the 19th February 2019. The original full project was to improve the track, seating and floodlighting at the stadium and had a budget of £1.21m, of which £0.8m was for the floodlighting. The project subsequently became part of the Public Sector Decarbonisation Scheme, which was approved by Cabinet on the 23rd February 2021. The floodlighting works at the stadium will no longer proceed under the Public Sector Decarbonisation Scheme due to viability issues with the grant funding. The £0.5m added to the programme within Quarter 1 will allow the required improvements to the lighting levels ensuring that the athletics and football activities can continue at the site.
7. Cabinet is asked to delegate to the Strategic Director, Economy, Innovation and Growth (in consultation with the Service Director of Corporate Services and Governance and the Strategic Director, Resources and Digital) the negotiation and approval of the tender and contract award for the floodlighting works within the agreed capital programme allocation of £0.5m. A delegated decision is sought as the works are required to be completed prior to the start of the new football season.
8. Planned investment has been re-profiled to future financial years on several schemes, amounting to a reduction of £51.6m in 2022/23, the schemes which have slipped include the following:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.