RESOLVED - ( i ) That Council be recommended to approve all variations to the 2022/23 Capital Programme as detailed in Appendix 2. (ii) That Council be recommended to approve the financing of the revised programme as set out in the report. (iii) That it be confirmed to Council that the capital expenditure and financing requirements have been advised in line with the amended budget and none of the approved Prudential Indicators set for 2022/23 have been breached. (iv) That the urgent decision in relation to the Gateshead International Stadium Floodlighting project set out in the report be noted. For the following reasons: (A) To ensure the optimum use od the Council’s capital resources in 2022/23. (B) To accommodate changes to the Council’s in-year capital expenditure plans. (C) To ensure performance has been assessed against the approved Prudential Limits.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. This report sets out the latest position on the 2022/23 Capital Programme and Prudential Indicators at the end of the second quarter to 30 September 2022. The report assesses reasons for the variances from the approved programme and details the proposed financing of the capital programme. In addition, the report considers the impact of CIPFA’s Prudential Code on the capital programme and the monitoring of performance against the statutory Prudential Indicators.
Background
2. The original budget for the capital programme for 2022/23, as agreed by Council on 24 February 2022, totalled £146.7m. At the first quarter review, this reduced to £103.2m and at the second quarter review expenditure is now projected to be £85.4m, £65.0m General Fund and £20.4m Housing Revenue Account (HRA) by year end.
3. The proposed reduction in the capital programme at the second quarter comprises of the following movements: £m Increased borrowing/external funding/contributions 6.420 Reduced Project Costs (2.160) Re-profiling of capital expenditure to future years (22.115) Total Variance (17.855)
4. The proposed £6.4m increase includes the re-profiling of allocations to reflect the final contract termination for the Green Homes Chopwell scheme, increased civil engineering costs on the Gateshead District Energy Network Solar Panels project, the addition of several Decent Homes projects, increased costs on the Gateshead International Stadium project and delays on the Social Care Mosaic system.
5. The Gateshead International Stadium Floodlighting Project was included in the Capital Programme with a budget of £0.500m at Q1 and was approved by Cabinet on the 19th July 2022. Following return of tenders, an additional budget of £0.135m, has been approved under an urgent decision dated 18th October 2022 in accordance with Part 2 General Delegation to Managers 4(e) of the
1 of 5 Constitution. Cabinet is asked to note the additional budget of £0.135m for this project. The additional budget will enable the required improvements to the lighting levels ensuring that the athletics and football activities can continue at the site. The tender costs were time limited and, due to the current market volatility and uncertainty, there was a significant risk of further cost increases had the urgent decision not been undertaken.
6. The Strategic Director, Economy, Innovation and Growth (in consultation with the Service Director of Corporate Services and Governance and the Strategic Director, Resources and Digital) approved the contract award for the floodlighting works using the delegated decision approved by Cabinet on the 19 July 2022 and the Strategic Director, Resources and Digital approved the additional budget using the urgent decision dated 18th October 2022.
7. The proposed reduction of £2.16m includes a reduction on the Baltic Quarter Enabling Infrastructure project due to better than expected ground conditions resulting in a reduction in the total cost of the project.
8. Planned investment has been re-profiled to future financial years on several schemes, amounting to a reduction of £22.1m in 2022/23. The schemes which have slipped include the following:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.