Capital Programme and Prudential Indicators 2023/24 – Third Quarter Review

Approved Executive 3 papers

Cabinet approved this item on Tuesday 23 January 2024. Below is the council's own wording, with the papers it was decided on.

ItemC98

Resolved

RESOLVED - (i) That the Council be recommended to approve all variations to the 2023/24 Capital Programme as detailed in appendix 2 to the report. (ii) That the Council be recommended to approve the financing of the revised programme set out in this report. (iii) That it be confirmed to Council that capital expenditure and financing requirements have been revised in line with the amended budget and none of the approved Prudential Indicators set for 2023/24 have been breached. The above decisions have been made for the following reasons: (A) To ensure the optimum use of the Council’s capital resources in 2023/24. (B) To accommodate changes to the Council’s in-year capital expenditure plans. (C) To ensure performance has been assessed against the approved Prudential Limits.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1. This report sets out the latest position on the 2023/24 Capital Programme and Prudential Indicators at the end of the third quarter to 31 December 2023. The report assesses reasons for the variances from the approved programme and details the proposed financing of the capital programme. In addition, the report considers the impact of CIPFA’s Prudential Code on the capital programme and the monitoring of performance against the statutory Prudential Indicators.

Background

2. The original budget for the capital programme for 2023/24, as agreed by Council on 23 February 2023, totalled £112.1m. This was increased to £113.5m at the first quarter review and decreased to £106.8m at the second quarter review to accommodate re-profiling to future years. The third quarter review of progress has resulted in a revised estimate for capital expenditure of £78.0m by the year end, £52.8m General Fund and £25.2m HRA.

3. The proposed reduction in the capital programme at the third quarter comprises of the following movements: £m Additional capital expenditure 2.176 Re-profiling of capital expenditure to future years (30.929) Total Variance (28.753)

4. The proposed increase of £2.176m relates to variations of less than £0.500m for a number of projects within the General Fund due to accelerated spend and £1.3m within the HRA for new home acquisitions.

5. The re-profiling of expenditure to future years of £30.929m relates to the following schemes:

• (£8.153m) Quays – slippage due to collating final plans and costs. • (£7.562m) Transforming Cities - schemes have been designed and costed with some started on site. • (£5.000m) Flood Alleviation – schemes are being designed and costed. • (£3.000m) Schools Basic Need – schools are to submit their funding requests to meet the demand for places.

1 of 4 • (£2.000m) West Askew Road – junction works have been approved and waiting to commence on site. • (£1.000m) Schools Special Education Needs High Needs – work is ongoing to determine how to best utilise the funding. • (£0.750m) Local Transport Plan – Integrated Transport – slippage on some schemes which require more design and modelling work. • (£0.650m) High Street South – work is ongoing to determine how to best progress the development.

Proposal

6. The report identifies planned capital expenditure of £78.0m for the 2023/24 financial year. The expected resources required to fund the Capital Programme are as follows: £m Prudential Borrowing 23.711 Projected Capital Receipts 0.679 Capital Grants and Contributions 28.420 Major Repairs Reserve (HRA) 19.264 Capital Grants and Contributions (HRA) 1.541 Right to Buy Receipts (HRA) 4.387 Total Capital Programme 78.002

7. CIPFA’s Prudential Code advises the regular monitoring of performance against the prudential indicators which regulate borrowing and investment. Targets and limits for the prudential indicators for 2023/24 were agreed at Council on 23 February 2023 and borrowing and investment levels have remained within these limits. Performance against the indicators for 2023/24 is set out in Appendix 5.

Recommendations

8. It is recommended that

(i) Cabinet recommends to Council the revision to the capital programme. (ii) Cabinet recommends to Council the financing of the revised programme. (iii) Cabinet confirms to Council that the capital expenditure and capital financing requirement indicators have been revised in line with the revised budget and that none of the approved Prudential Indicators set for 2023/24 have been breached.

For the following reason(s)

(i) To ensure the optimum use of the Council’s capital resources in 2023/24 (ii) To accommodate changes to the Council’s in-year capital expenditure plans. (iii) To ensure performance has been assessed against approved Prudential Limits.

CONTACT: Clare Tait extension: 3417

2 of 4 APPENDIX 1

Policy Context

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme and Prudential Indicators 2023/24: Third Quarter ReviewReport 103 KB DownloadRead as text
PDF
Capital Q3 2023-24 Appendix 5Appendix 107 KB Download
PDF
Capital Q3 Appendices 2-4Report 100 KB Download

At this meeting

Whole meeting

Who was there

9 of 26 attended
GC
Gaylor CarleCouncil Staff, expected
LB
Linda BartramCouncil Staff, expected
AD
Alison DunnCouncil Staff, expected
SC
Sarah CoxonOfficer, expected
NP
Neil PorteousOfficer, expected
CO
Craig OakesCouncil Staff, expected
AT
Andrew TateCouncil Staff, expected
IB
Iain BurnsCouncil Staff, expected
DW
Deborah WiseCouncil Staff, expected
ER
Emma ReynardCouncil Staff, expected
MG
Councillor Martin GannonChair, present
CD
Councillor Catherine DonovanVice-Chair, present

All 26 on the meeting page

On this subject at Gateshead

Search all
  1. Capital Programme and Prudential Indicators 2023/24 – Third Quarter ReviewThis decision
  2. Capital Programme and Prudential Indicators - Year End Outturn 2025-26Noted
  3. Capital Programme and Prudential Indicators - First Quarter Review 2026-27Approved
  4. Capital Programme and Prudential Indicators – Year End Outturn 2025-26Approved
  5. Capital Programme and Prudential Indicators – First Quarter Review 2026-27Approved
  6. Transport Capital Programme Year End ReportApproved

More from Gateshead Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Approval of Refreshed Resident Influence Strategyi) To approve the Resident Influence Strategy (Appendix 2). ii) To authorise implementation of the strategy supported... Approved Open
22 Sep 2026 Business North East Business Support Frameworki) To agree that the Council be included as a named delivery partner in NEMSA’s Business North East business case and... Agreed Open
22 Sep 2026 NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ... Approved Open
22 Sep 2026 Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report... Approved Open
22 Sep 2026 Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies