Resolved
(i) The Committee noted the report.
Audit and Standards Committee noted this item on Thursday 7 March 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
(i) The Committee noted the report.
1 This report updates the Audit and Standards Committee on the Government’s consultation around proposals to address the local audit backlog and embed timely audits.
2 On 8 February 2024, Department for Levelling Up, Housing and Communities (DLUHC), issued a consultation and joint statement on proposals to clear the audit backlog for English councils. The joint statement included recommendations from DLUHC, the Financial Reporting Council (FRC), the National Audit Office (NAO), the Chartered Institute of Public Finance and Accountancy (CIPFA), the Institute of Chartered Accountants in England and Wales (ICAEW), and the Public Sector Audit Appointments (PSAA).
3. The Committee will be aware that Gateshead Council is in a more favourable position compared to many other authorities as all financial accounts up to and including 2022/23 have been completed by external audit and we will receive the audit certificate once we have received a joint value for money statement for 2021/22 and 2022/23. We anticipate to receive a positive value for money opinion from Mazars the external auditor shortly and as such we would not be affected by any of the proposals as part of phase 1.
4 The joint statement set out three phases of measures to address the audit backlog:
• Phase 1: Reset – this involves clearing the backlog of historical audit opinions up to and including the financial year 2022/23 by 30 September 2024. This phase is not applicable to Gateshead Council as all audits up to and including 2022/23 have now been completed.
• Phase 2: Recovery – introducing audit backstop dates to prevent the recurrence of the backlog and allowing audit assurance to be built up over multiple audit cycles.
5 Phase 3: Reform – addressing the systematic challenges in the local audit systems to embed timely financial reporting and audit.The consultation is to seek views on phases 1 and 2 of the project plan and the Council’s response to this consultation is shown in Appendix 1. Phase 1: Reset
6 The Government would use changes to legislation and the Code of Audit practice to implement a backstop date of 30 September 2024 for all outstanding audits up to and including the financial year 2022/23.
7 Auditors will be required to publish an opinion based on completed work as at the backstop date and this opinion can be either unmodified, modified (qualified or adverse) or disclaimed.
8 Auditors will be able to produce a single commentary on Value for Money arrangements covering all outstanding periods up to 2022/23.
9 The Government is proposing to publish a list of local bodies and their auditors which do not meet the backstop date.
Phase 2: Recovery
10 With the introduction of modified or disclaimed audit opinions auditors will require time to obtain assurances over the opening balances in the financial statements and the aim of the recovery phase is to give auditors multiple financial years in which to achieve assurances.
11 New statutory backstop dates for all financial years up to and including 2027/28 will be introduced. These backstop dates will replace the existing statutory deadline of 30 September for the publication of audited accounts.
12 Councils would not be required to publish a delay notice during these periods.
13 The introduction of these new backstop dates may result in more modified or disclaimer audit opinions.
14 The proposed new backstop dates have been designed to limit the impact on other public sector audits and are as follows:
Year end 31 March 2024: 31 May 2025 Year ended 31 March 2025: 31 March 2026 Year ended 31 March 2026: 31 January 2027 Year ended 31 March 2027: 30 November 2027 Year ended 31 March 2028: 30 November 2028
15 The Government is proposing to publish a list of local bodies and audit firms which meet and do not meet the deadlines.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Local audit delays: proposals to clear the backlog and embed timely auditReport | 107 KB | DownloadRead as text |
Follow Audit and Standards Committee at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2026 | Treasury Management Annual Report 2025/26RESOLVED that the Treasury Annual Report be submitted to Cabinet. | Decided | Open |
| 14 Jul 2026 | Treasury Management Quarter 1 ReportRESOLVED that the Treasury Management Performance at the 2026/27 First Quarter Review be noted. | Noted | Open |
| 14 Jul 2026 | Annual Report To CabinetRESOLVED that the report and the work undertaken by the Audit and Standards Committee during the period 01 July 2025 ... | Noted | Open |
| 14 Jul 2026 | Corporate Risk Management 2026/27 Quarter 1 UpdateRESOLVED that the report be noted, and the Council's risk management be considered effective. | Noted | Open |
| 14 Jul 2026 | Exclusion of the Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of Item 9 in accordance with Par... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.