(i) Cabinet agreed to declare the Dryden Centre, as shown edged black on the plan provided surplus to Council’s requirements. (ii) Cabinet agrees for discussion to progress with an educational provider, with a further report to be received by Cabinet once draft terms are provisionally agreed between parties for a long leasehold. For the following reasons: (a) To manage resources and rationalise the Council’s assets in line with the Corporate Asset Strategy and Management Plan. (b) To realise savings for the Council.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. To seek approval for the Dryden Centre to be declared surplus to Council requirements and inform Cabinet of the proposed future course of action in relation to the building:
Background
2. The Dryden Centre, which is shown outlined in black on the attached plan is held for Educational purposes, although most recently it was used as a training centre and offices. Since 2012, the Council has gradually been withdrawing services from the property, one of the two buildings has been vacant due its poor condition since 2012 which was declared surplus at the time. In 2019 a lease covering approximately a third of the ground floor was granted to the Cumbria, Northumberland and Tyne and Wear NHS Trust (CNTW).
3. Over the last 12 months, the Council has relocated all of its services and CNTW vacated at the end of March 2024. The property is currently vacant.
4. Alternative uses such as housing, offices and corporate educational provision have been considered but are not viable. Discussions are currently taking place with a private education provider to determine whether the property would be suitable for their needs.
Proposal
5. It is proposed that the Dryden Centre, be declared surplus to Council requirements, and that negotiations with the private education provider be progressed by the Strategic Director of Housing, Environment and Healthy Communities who is authorised to agree provisional terms subject to a further Cabinet report.
Recommendations
6. It is recommended that Cabinet (i) declare the Dryden Centre shown edged black on the attached plan surplus to Council’s requirements. (ii) Agree for discussion to progress with the educational provider, with a further report to be received by Cabinet once draft terms are provisionally agreed between parties for a long leasehold. For the following reasons:
a. To manage resources and rationalise the Council’s assets in line with the Corporate Asset Strategy and Management Plan.
b. To realise savings for the Council.
---------------------------------------------------------------------------------------------------------------------- CONTACTS: Andrew Holtham extension: 3466 APPENDIX 1
Policy Context
1. The proposal is in accordance with the Corporate Plan (2023-2028) “Working together and fighting for a better future for Gateshead” , by potentially facilitating a capital receipt/ premium, producing savings by declaring a building surplus, and enabling the provision of educational facilities for a private operator.
2. The proposal is also in accordance with the provisions of the Corporate Asset Strategy and Management Plan. In particular, making the best use of Council assets.
3. The Dryden Centre comprises two of former school buildings and associated car park. The main building comprises of offices and training facilities arranged over the basement, ground and first floors. A smaller two storey block was decommissioned in 2012 due to its deteriorating condition. There is a caretaker’s house and playing fields also associated with the site but these are not subject to this report. All of the land is held for educational purposes, but the majority of the site has not been used for that purpose for some years.
4. The accommodation was primarily used by Council as offices for Education, Schools and Inclusion and to provide training accommodation for staff, teachers and foster carers. A section of the building known at State of the Art (SoTA) was also used to deliver training to people with Learning Difficulties. Since 2019 approximately a third of the ground floor was let to CNTW.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.