Resolved
i. That the Committee agrees the Council is considered to be a going concern based on the assessment in the report presented.
Audit and Standards Committee agreed this item on Thursday 26 September 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
i. That the Committee agrees the Council is considered to be a going concern based on the assessment in the report presented.
1. The purpose of this report is to consider the Council’s status as a going concern and request Committee to agree this.
2. As Local Authorities are created and abolished only by statutory changes there is an underlying assumption in the 2023/24 CIPFA/LASAAC Code of Practice on Local Authority Accounting (Accounting Code) that their accounts will be prepared on a going concern basis.
3. Authorities are required by Section 32 of the Local Government Finance Act 1992 to set a balanced budget. However, financial pressures within the local government sector mean that the Chief Finance Officer (section 151 officer) may need to consider whether action is required under section 114 of the 1988 Act, where the section 151 officer must report, following consultation with the Council’s monitoring officer, to all authority’s Councillors if they believe expenditure is likely to exceed incoming resources in the current or in any future year.
4. This report outlines the assessment of the Council’s status as a going concern in line with best practice.
Context
5. The provisions in the Accounting Code on the going concern accounting requirements reflect the economic and statutory environment in which local authorities operate. These provisions confirm that local authorities have no ability to cease being a going concern as described by IAS 1 - Presentation of Financial Statements. As local authorities cannot be dissolved without statutory prescription, it would not be appropriate for the Council’s financial statements to be prepared on any other than a going concern basis.
6. Although the financial context continues to be challenging and uncertain the Council has a strong track record of meeting its financial obligations and maintaining financial sustainability through delivery within budget. Since 2012 the Council has delivered an outturn within its budget. A Council wide approach to the budget, which is priority driven and over a medium-term planning horizon will ensure that this continues to be the case.
1 7. The Audit Progress Report from Forvis Mazars outlines that the review of the Council’s Value for Money arrangements is ongoing. At this stage they have not identified any significant weaknesses in arrangements to secure economy, efficiency and effectiveness. The last Annual report combined the financial years 2021/22 and 2022/23. The report outlined that Forvis Mazars did not identify any significant weaknesses in arrangements.
Current Position - 2023/24
8. Council agreed the revenue budget for 2023/24 on 23 February 2023. This was set at £289.903m with a requirement to use £25.883m of reserves. At the first quarter Cabinet agreed an amendment to the net revenue budget for 2023/24 from £289.903m to £281.885m.
9. The overall 2023/24 outturn position for the Council including non-service budgets and financing results in an overall Council revenue position for 2023/24 of a surplus of £5.8m.
10. The position is testament to the collective approach taken by groups and services to keep cost pressures under review within the financial year and ensuring that action was taken in a timely manner to ensure an outturn within budget.
11. The Corporate Management Team receive regular updates on budget delivery in order to monitor progress and hold lead officers to account.
12. Council originally approved a Capital Programme of £112.1m for the 2023/24 financial year. At the third quarter review the capital programme was set at £78.0m,
13. £52.8m General Fund schemes and £25.2m HRA. The Capital Programme outturn for 2023/24 was £68.9m, £44.6m General Fund and £24.3m HRA £9.1m lower than the third quarter review.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Achievement of Going Concern Status 2023-24Report | 110 KB | DownloadRead as text |
Follow Audit and Standards Committee at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2026 | Treasury Management Annual Report 2025/26RESOLVED that the Treasury Annual Report be submitted to Cabinet. | Decided | Open |
| 14 Jul 2026 | Treasury Management Quarter 1 ReportRESOLVED that the Treasury Management Performance at the 2026/27 First Quarter Review be noted. | Noted | Open |
| 14 Jul 2026 | Annual Report To CabinetRESOLVED that the report and the work undertaken by the Audit and Standards Committee during the period 01 July 2025 ... | Noted | Open |
| 14 Jul 2026 | Corporate Risk Management 2026/27 Quarter 1 UpdateRESOLVED that the report be noted, and the Council's risk management be considered effective. | Noted | Open |
| 14 Jul 2026 | Exclusion of the Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of Item 9 in accordance with Par... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.