CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Gateshead Metropolitan Borough Council
Cabinet, Tuesday 17 December 2024 at 2.00pm

Construction contracts for swimming pool energy projects

Noted Executive 1 paper

Cabinet noted this item on Tuesday 17 December 2024. Below is the council's own wording, with the papers it was decided on.

ItemC261

Resolved

(i) Cabinet noted the progress to date, and the remaining risks and reasons, in taking this project forward to construction at this time (ii) Cabinet approved the award of construction contracts up to a value of £3.736m to Equans Regeneration Limited for heat pump and solar PV installations at Dunston Leisure Centre and Blaydon Leisure and Primary Care Centre The above decision was made for the following reasons: (i) To improve energy efficiency and reduce carbon emissions of the swimming pools in question (ii) To support the future viability of swimming pools in Gateshead (iii) To support the Council’s Climate Emergency Action Plan to achieve net zero emissions by 2030
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1. To request approval to award construction contracts up to a value of £3.736m to Equans Regenerations Ltd to complete installations of heat pumps and solar PV systems at Dunston and Blaydon leisure centres.

Background

2. The Council has committed to reducing its carbon emissions to net zero by 2030.

3. The Council had been successful in grant funding applications made to Sport England (£0.356m) and the Public Sector Decarbonisation Scheme Round3c (£4.164m) to support the installation of low carbon technology at various swimming pool sites in Gateshead.

4. Cabinet has previously agreed to the following, to progress decarbonisation projects at Dunston Leisure Centre, and Blaydon Leisure and Primary Care Centre. a. Enter design stage contracts, up to £0.475m b. Instruct further works / materials orders up to £1.300m

5. Progress has reduced risks further and confirmed costs of construction, to the point where it's proposed to enter construction contracts, to complete the works. Proposal

6. It is proposed that the projects proceed to construction stage, noting the risks reduced to date, and outstanding risks still, as referenced in Appendix 1.

7. Construction contracts will be awarded to Equans Regeneration Ltd for the remaining works required, under the NEPO Retrofit and Decarbonisation Framework, at a value up to £3.736m (which includes £0.914m of.equipment already ordered to date). Recommendations

8. It is recommended that:

(i) Cabinet note the progress to date, and the remaining risks and reasons, in taking this project forward to construction at this time (ii) Cabinet approve the award of construction contracts up to a value of £3.736m to Equans Regeneration Limited for heat pump and solar PV installations at Dunston Leisure Centre and Blaydon Leisure and Primary Care Centre For the following reason(s): (i) To improve energy efficiency and reduce carbon emissions of the swimming pools in question (ii) To support the future viability of swimming pools in Gateshead (iii) To support the Council’s Climate Emergency Action Plan to achieve net zero emissions by 2030

CONTACT: Jim Gillon, Service Director, Energy and Design extension: 392 APPENDIX 1

Policy Context

1. The proposals here continue to contribute to the delivery of many targets within the Corporate Plan, Thrive and the Council’s Climate Emergency Action Plan. specifically: • Supporting the ongoing viability of leisure centres, under their new management arrangements, to ensure communities continue to receive health and activity benefits • The heat pumps will ensure these leisure centres – some of the Councils largest gas consumers – are on a path to have zero carbon emissions

Background / Progress update 2. In early 2024, the Council was successful in bidding for

a. £4.164m Public Sector Decarbonisation Scheme grant for a £4.75m scheme to install heat pumps at Dunston, Blaydon and Birtley Swimming Pools. b. £0.356m Sport England grant (100% funding) towards Solar PV and LED Lighting for Dunston Leisure Centre

3. The new Birtley Aquatics group were not able to accept their element of the PSDS grant funding.

4. On 16 April 2024, Cabinet agreed to accept the grant funding and commence scheme design stage for Dunston and Blaydon sites, committing up to £0.475m and approving the appointment of Equans Ltd to progress design stages.

5. In September 2024, cabinet agreed to progress a further £1.300m of works and advance orders, to continue developing the project, in line with grant spending deadlines.

6. Progress since Sept 2024 has been as follows, for each site.

7. Dunston Leisure Centre – PSDS grants (heat pumps) and Solar PV / LED (Sport England)

a. LED lighting replacements (ca. £102k) were instructed to Construction Services, and will be complete by end December 2024

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Construction contracts for swimming pool energy projectsReport 196 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 16 attended
MG
Councillor Martin GannonChair, present
CD
Councillor Catherine DonovanVice-Chair, present
JA
Councillor John AdamsCommittee Member, present
CB
Councillor Chris BuckleyCommittee Member, present
AD
Councillor Angela DouglasCommittee Member, present
MH
Councillor Maria HallCommittee Member, present
GH
Councillor Gary HaleyCommittee Member, present
LK
Councillor Leigh KirtonCommittee Member, present
JM
Councillor John McElroyCommittee Member, present
BO
Councillor Bernadette OliphantCommittee Member, apologies
RB
Councillor Ron BeadleCommittee Member, in attendance
DO
Dale OwensOfficer, present

All 16 on the meeting page

More from Gateshead Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Approval of Refreshed Resident Influence Strategyi) To approve the Resident Influence Strategy (Appendix 2). ii) To authorise implementation of the strategy supported... Approved Open
22 Sep 2026 Business North East Business Support Frameworki) To agree that the Council be included as a named delivery partner in NEMSA’s Business North East business case and... Agreed Open
22 Sep 2026 NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ... Approved Open
22 Sep 2026 Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report... Approved Open
22 Sep 2026 Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies