Resolved

i. That all the variations to the 2024/25 Capital Programme as detailed in Appendix 2 to the report be agreed. ii. That the financing of the revised programme be agreed. iii. To note that the capital expenditure and financing requirements are revised have been amended in line with the budgeted and none of the approved Prudential Indicators set for 2024/25 have not been breached.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Council

Purpose of the report

1. This report sets out the latest position on the 2024/25 Capital Programme and Prudential Indicators at the end of the third quarter to 31 December 2024. The report assesses reasons for the variances from the approved programme and details the proposed financing of the Capital Programme. In addition, the report considers the impact of CIPFA’s Prudential Code on the Capital Programme and the monitoring of performance against the statutory Prudential Indicators.

Background

2. The original budget for the Capital Programme for 2024/25, as agreed by Council on 22 February 2024, totalled £113.9m. This was decreased to £108.0m at the first quarter review and decreased to £92.4m at the second quarter review to accommodate re-profiling to future years. The third quarter review of progress has resulted in a revised estimate for capital expenditure of £77.8m by the year end, £52.7m General Fund and £25.1m HRA.

3. The proposed reduction in the Capital Programme at the third quarter comprises of the following movements: £m Increase in Budget Requirement 1.617 Other Movements (0.777) Re-profiling of capital expenditure to future years (15.467) Total Variance (14.627)

4. The proposed increase of £1.617m relates to variations of less than £0.500m for a number of projects within the General Fund and a £1.364m increase in HRA Decent Homes budget requirement due to accelerated spend. Further details by project and service are shown in appendix 2 and 3.

5. The re-profiling of expenditure to future years of £15.467m generally relates to the following schemes where the variance is +/- £0.500m:

• (£2.000m) West Askew Road – Reprofiled to future years due to change in design scope and delivery timescale. • (£5.000m) Gateshead Quays – Reprofiling. • (£1.000m) Baltic Quarter Remediation and Extension – slippage to future years. • (£3.457m) Energy Efficiency Works at Gateshead Leisure Centres – slippage to 2025/26. • (£0.766m) Building Safety Improvements – slippage to 2025/26 due to time constraints in installing fire doors. • (£1.711m) Estate Regeneration and Demolition – slippage to 2025/56.

6. Whilst not included in the third quarter review year end estimate it should be noted that the cost of addressing the Gateshead Flyover safety concerns is currently being assessed. Emergency works have begun and are likely to impact the outturn position. This will be factored into the position as committed costs become clear.

Proposal

7. The report identifies planned capital expenditure of £77.8m for the 2024/25 financial year with further detail in appendix 4. The expected resources required to fund the Capital Programme are as follows: £m Prudential Borrowing 26.194 Projected Capital Receipts 0.750 Capital Grants and Contributions 25.743 Major Repairs Reserve (HRA) 19.114 Capital Grants and Contributions (HRA) 0.786 Right to Buy Receipts (HRA) 5.199 Total Capital Programme 77.786

8. CIPFA’s Prudential Code advises the regular monitoring of performance against the Prudential Indicators which regulate borrowing and investment. Targets and limits for the Prudential Indicators for 2024/25 were agreed at Council on 22 February 2024 and borrowing and investment levels have remained within these limits. Performance against the indicators for 2024/25 is set out in Appendix 5.

Recommendations

9. It is recommended that

(i) Cabinet recommends to Council the revision to the Capital Programme. (ii) Cabinet recommends to Council the financing of the revised programme. (iii) Cabinet confirms to Council that the capital expenditure and capital financing requirement indicators have been revised in line with the revised budget and that none of the approved Prudential Indicators set for 2024/25 have been breached.

for the following reason(s)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Monitoring 2024-25 Q3 Cabinet 21-01-25Report 284 KB DownloadRead as text
PDF
Capital Programme and Prudential Indicators 2024/25: Third Quarter ReviewReport 82 KB Download

At this meeting

Whole meeting

Who was there

57 of 68 attended
KM
Councillor Kathleen McCartneyChair, present
FG
Councillor Freda GeddesVice-Chair, present
JA
Councillor John AdamsCommittee Member, present
VA
Councillor Vicky AndersonCommittee Member, present
RB
Councillor Ron BeadleCommittee Member, present
MB
Councillor Malcolm BrainCommittee Member, present
LB
Councillor Leanne BrandCommittee Member, present
CB
Councillor Chris BuckleyCommittee Member, present
DB
Councillor Dot BurnettCommittee Member, present
PB
Councillor Pamela BurnsCommittee Member, present
LC
Councillor Lynne CaffreyCommittee Member, present
BC
Councillor Brenda ClellandCommittee Member, present

All 68 on the meeting page

On this subject at Gateshead

Search all
  1. Capital Programme and Prudential Indicators 2024/25 - Third Quarter ReviewThis decision
  2. Capital Programme and Prudential Indicators - Year End Outturn 2025-26Noted
  3. Capital Programme and Prudential Indicators - First Quarter Review 2026-27Approved
  4. Capital Programme and Prudential Indicators – Year End Outturn 2025-26Approved
  5. Capital Programme and Prudential Indicators – First Quarter Review 2026-27Approved
  6. Transport Capital Programme Year End ReportApproved

More from Gateshead Council

All decisions
MeetingDecisionOutcome
16 Jul 2026 To confirm the Minutes of the meeting held 4 June 2026i. That the minutes of the meeting held on 4 June 2026 be approved. Approved Open
16 Jul 2026 Capital Programme and Prudential Indicators - Year End Outturn 2025-26i. That the Capital Programme Outturn for 2025/26 be noted; ii. That the financing of the Capital Programme be approv... Noted Open
16 Jul 2026 Capital Programme and Prudential Indicators - First Quarter Review 2026-27i. That all variations to the 2026/27 Capital Programme as detailed in appendix 2 be approved; ii. That the financing... Approved Open
4 Jun 2026 To confirm the Minutes of the meeting held on 19 March 2026 and on 29 May 2026i. That the minutes of the meeting held on 19 March 2026 and on 29 May 2026 be approved. Approved Open
4 Jun 2026 Post-16 Strategyi. that the Post-16 Education Strategy for Gateshead be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies