(i) Cabinet noted AECOM Gateshead Viaduct Principal Inspection – Issued 29 January 2025 Report (Appendix2). (ii) Cabinet note the timeline of key decisions and events to date (Appendix 3). (iii) Cabinet agreed that the only viable option for the flyover is demolition. (iv) Cabinet agreed that Officers should continue to undertake all tasks associated with pursuing the demolition of the flyover as soon as practicable with delegated authority to the Interim Strategic Director Housing, Environment and Healthy Communities, following consultation with the Strategic Director Resources and Digital and following consultation with the Portfolio holder for Environment and Transport to proceed once the final demolition plans and costs are available. (v) Cabinet noted the ongoing work on a suitable transport and regeneration scheme in conjunction with our partners. (vi) Cabinet considered and approved Corporate Procurement to award contracts for works and services required for the efficient and effective delivery of the flyover demolition in accordance with the Contract Procedure Rules. For the following reasons: (a) Demolishing the flyover is safer, more cost-effective, and supports future development better than repairing it. (b) Demolishing the flyover will support the Council's strategic priorities for a safer, more connected, and thriving Gateshead.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. The report outlines the key decisions, events and expenditure incurred to date on the Gateshead Highway known locally as the flyover. It also recommends demolishing the flyover as soon as possible and highlights the ongoing work with our partners on a new transport and regeneration plan and funding options.
Background
2. As with all our highway structures the flyover is subject to regular inspections. We carry out general inspections of its condition around every two years with special inspections as required and over and above this we carry out periodically Principal Inspections which are more detailed.
3. During the recent Principal Inspection, a significant amount of spalling (loose concrete) was found, and it was clear this would require a delamination survey to remove the loose sections and ensure as far as practicable that the flyover remained safe for the public.
4. There are ongoing issues due to the design and construction of the structure with water ingress and it's this water which can lead to the spalling. This spalling is due to the steel reinforcement rusting and expanding causing the concrete cover to fail or the water can simply freeze in the structure and again this can cause the concrete to fail.
5. During the recent delamination survey carried out between 10th and 16th of December 2024, it was identified that one of the piers had significant issues with loss of concrete integrity and the steel reinforcement was in a condition which could not guarantee the overall structural integrity of the structure.
6. Due to safety concerns the Council closed the structure on 13th December 2024 using temporary traffic management and diversionary routes for traffic as well as fencing to prevent pedestrian access.
7. Closures were not introduced at the Park Lane and Bellview (Five Bridges) roundabouts as based on specialist structural advice these areas could remain in use.
8. Expert advice advised that the integrity of the Metro tunnels may be compromised, therefore Nexus made the decision to withdraw the Metro service on 19th December 2024 between Central Station and Heworth causing major
1 of 12 disruption.
9. We worked with consulting engineers and contractors to implement a temporary propping solution which was introduced between 27th and 29th December 2024 which allowed Nexus to carry out their necessary checks and subsequently enabled the Metro service to be restored on 31st December 2024.
10. We completed the interim solution to reinforce two of the pillars which has allowed the temporary supports to be removed and the Sunderland Road bus link and cycling and pedestrian access to be restored on the 10 March 2025.
11. Our long-term plan has been to demolish the flyover and regenerate the area; however, funding has not been secured despite several attempts to obtain such funding.
12. A Project Leader and Officers from the Council are working with consultants to ensure safety by continuing to monitor the flyover including removing loose concrete.
13. The Council has received a Report (AECOM – Gateshead Viaduct Principal Inspection – Issued 29 January 2025) in Appendix 2 that helps to understand the risks and make informed decisions going forward.
Proposal
14. The situation with the flyover is evolving rapidly and is subject to change as surveys are completed and plans are developed. Several key decisions have been made to ensure safety remains the highest priority. A timeline of these key decisions and events is included in Appendix 3.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.