i) Cabinet agreed to accept the NECA grant for 2025/26 from NECA to continue to deliver the investment plan priorities identified in paragraphs 6-17 of Appendix 1. The above decision was made for the following reason: a) To ensure that the Council has funding to deliver its priorities as identified in the Corporate Plan and Council’s Capital Programme.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. The purpose of this report is to seek Cabinet approval to accept North East Combined Authority (NECA) grant funding for 2025/26.
Background
2. Gateshead Council is a constituent local authority of the Mayoral North East Combined Authority (NECA). NECA has been developing its strategies for delivering on its missions as set out in its Corporate Plan and Medium Term Financial Strategy (2025/29).
Proposal – NECA Capital Funding 2025/26
3. NECA has 7 Cabinet Portfolio Plans and associated funding allocations approved through NECA Cabinet in July 2024 and November 2024. Gateshead Council is developing a number of business cases for grant funding from NECA to deliver Gateshead Council priorities.
4. There are 3 business cases that have been approved recently by NECA or are in the process of seeking NECA approval. These are:
(i) Early Priority Events Programme – approval of £356,000 (ii) Early Capital Programme – application for £3,000,000 (iii) UKSPF Capital for Local Growth Plan – application for £2,500,000.
5. It is proposed that this funding will be allocated to deliver Gateshead Council priorities as identified in paragraphs 6-17 of Appendix 1.
6. Given the timescales involved to deploy resources effectively, it is proposed that the 2025/26 NECA Capital Funding is allocated to:
• Council priorities • Ability to leverage further funding • Deliverability by 31 March 2026.
Recommendations 7. It is recommended that Cabinet:
(i) Accept the NECA grant for 2025/26 from NECA to continue to deliver the investment plan priorities identified in paragraphs 6-17 of Appendix 1.
1 of 6 for the following reason(s):
(i) to ensure that the Council has funding to deliver its priorities as identified in the Corporate Plan and Council’s Capital Programme.
CONTACT: Lindsay Murray, Service Director Economic Development and Regeneration, Extension: 2794
2 of 6 APPENDIX 1
Policy Context
1. NECA early Capital funding will support the Council’s Thrive pledge to invest in our economy to provide opportunities for employment, innovation, and growth and specifically the Gateshead Economic Development Strategy objectives of building the economy of the future and supporting local businesses.
2. Delivering externally funded schemes is critical to achieving Economic Development Strategy objectives and the vision for Gateshead of a fairer, greener, and more resilient economy.
3. NECA Early Capital funding will deliver the objectives of the Council Corporate Plan and the Medium-Term Financial Strategy.
4. NECA early capital funding will also support the delivery of the North East Combined Authority (NECA) Corporate Plan, the emerging Local Growth Plan, and the NECA Portfolio plans.
5. NECA has 7 Cabinet Portfolio Plans and associated funding allocations approved through NECA Cabinet in July 2024 and November 2024. Gateshead Council is developing a number of business cases for early Capital Funding from NECA to deliver Gateshead Council priorities.
Proposal
6. There are 3 business cases that have been approved recently by NECA or are in the process of seeking NECA approval. These are:
(i) Early Priority Events Programme – approval of £356,000 (ii) Early Capital Programme – application for £3,000,000 (iii) UKSPF Capital for Local Growth Plan – application for £2,500,000.
7. The funding is available for spend in 2025/26, with a requirement for all spend to be defrayed by 31st March 2026. This has limited the opportunities available. The following projects have been identified as a) meeting strategic objectives and policy considerations, b) contributing to or unlocking wider regeneration initiatives and c) deliverable within the timescales.
(i) Early Priority Events Programme - £356,000
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.