CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Gateshead Metropolitan Borough Council
Corporate Resources Overview and Scrutiny Committee, Monday 20 October 2025 at 10.00am

Resilience and Emergency Planning Annual Update

Decided Scrutiny 1 paper

AI summaryGateshead scrutiny committee receives annual resilience and emergency planning update and asks for a further progress report in six months.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCommittee asks for another update in six months
MoneyUp to about £439k per yearGovernment grant for Northumbria LRF Trailblazer pilot
What happens nextFurther progress report in six monthsCommittee request following annual update
Who it affectsCouncil emergency response and residentsCovers incidents, training and counter terrorism work

What was decided

The committee received the annual update on the Council's resilience and emergency planning work covering September 2024 to the present. Report P4

Members asked that a further progress report be brought back in six months, rather than the twelve months originally proposed in the recommendations. Report P37

Why

The Council is a Category 1 Responder under the Civil Contingencies Act 2004 and must report annually on its resilience and emergency planning activities. Report P5, P6

The update covers training, exercises, incidents responded to since September 2024, multi-agency preparedness and counter terrorism work. Report P4, P14, P16, P17

What happens next

A further progress report will be presented to the committee in approximately six months. Report P37

Work continues on a new Council Cyber Response Plan, recruitment to the Emergency Response Team, and counter terrorism site plans for Council buildings and schools. Report P13, P20, P36

The money

  • approximately £439k per year over a 3-year period Government grant for the Northumbria LRF Trailblazer pilot, covering staffing of a new Chief Resilience Officer and team Report P31

Options considered

  • Rejected: Receive a further progress report in twelve months (as recommended in the report). Committee asked for a report in six months instead Report P37
  • Chosen: Receive a further progress report in six months. Set out in the formal decision of the committee

Implications

  • Risk: Learning from the Gateshead Flyover closure points to the need for more proactive planning for infrastructure risks and better recording on the Council Risk Register. Report P19
  • Risk: The Council's Cyber Response Plan is under development following a cyber incident in January 2025 that affected around 900 people. Report P20
  • Legal: The Protection of Premises Act (Martyn's Law) gained Royal Assent in April 2025 and will create new duties for publicly accessible premises with a capacity of 200+. Report P34
  • Staffing: The Emergency Response Team has 29 volunteers, with 2 new members joining in the last 12 months, and a recruitment campaign is planned for the year. Report P12, P13

Who and where

  • Residents affected by incidents including the flyover closure, a tower block water loss, a high-rise decant, and a gas leak evacuation Report P19, P22, P25, P26
  • Around 900 people whose data was breached in a cyber incident in January 2025 Report P20
  • Pupils, parents and schools in Gateshead following hoax threat emails Report P23
  • Northumbria Local Resilience Forum partners, including emergency services, NHS, Environment Agency and other local authorities Report P6, P27

Timeline

  • 24th September 2024, present: Court demonstrations linked to the 'Freeman of the Land' movement, with protests over Council Tax non-payment Report P18
  • 13th December 2024: Gateshead Flyover closed due to safety reasons, with knock-on effects for Metro tunnels below Report P19
  • 8th January 2025: Cyber security breach identified on Council network drives, affecting around 900 people Report P20
  • 12th January 2025: Regent Court tower block lost access to water Report P22
  • 24th January 2025: Storm Eowyn affected the UK, with multi-agency coordination in place Report P21
  • 6th March 2025: Several Gateshead schools received hoax threat emails Report P23
  • April 2025: Protection of Premises Act (Martyn's Law) received Royal Assent Report P34
  • 2nd May 2025: Fire at a building on an industrial park in which a 14-year-old died, with arrests of teenagers reported Report P24
  • 12th May 2025: Exercise Solaris multi-agency pandemic exercise held Report P16
  • 6th June 2025: Priory Court high-rise block decanted after accidental water ingress and electrical power loss Report P25
  • 1st August 2025: Gas leak at Westbourne Avenue led to evacuation of around 40 homes Report P26
  • 22nd September 2025, 4th November 2025: Exercise Pegasus national multi-agency pandemic exercise in phases Report P16

Plain English for the jargon

  • Category 1 Responder: Organisations with the full set of civil protection duties under the Civil Contingencies Act 2004, including local authorities, emergency services, NHS bodies and the Environment Agency.
  • Northumbria LRF: Northumbria Local Resilience Forum, the multi-agency body that coordinates emergency planning and preparedness across the area.
  • LRF Trailblazer: A government pilot, originally the Stronger Local Resilience Forums Pilot, testing new resilience leadership and partnership arrangements.
  • Martyn's Law / Protection of Premises Act: New legislation requiring publicly accessible premises with a capacity of 200 or more to put counter terrorism security measures in place.
  • CONTEST: The UK's national counter terrorism strategy, structured around the 4 Ps: Prevent, Pursue, Protect and Prepare.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCR14

Resolved

RESOLVED that a progress report be received in a further six months.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Corporate Resources Overview and Scrutiny Committee

Corporate Resources Overview and Scrutiny Committee 20th of October 2025

TITLE OF REPORT: Resilience and Emergency Planning Annual Update

REPORT OF: Alice Wiseman, Director of Public Health and Wellbeing

Summary Corporate Resources Overview and Scrutiny Committee receive annual updates on the Council’s Resilience and Emergency Planning activities. This report provides a summary from the date of the last report in September 2024 through to the current date.

Background 1. The Council’s Resilience and Emergency Planning functions continue to operate in adherence with the Civil Contingencies Act 2004, ensuring that we perform our statutory duties in collaboration with our partners and communities.

2. Within the Civil Contingencies Act 2004, Gateshead Council, along with all other local authorities, emergency services, NHS England, Integrated Care Board and the Environment Agency are defined as Category 1 Responders. A Category 1 responder is subject to the full set of civil protection duties which requires them to: • Assess the risk of emergencies occurring and use this to inform contingency planning. • Put in place emergency plans. • Put in place business continuity management arrangements. • Put in place arrangements to make information available to the public about civil protection matters and maintain arrangements to warn, inform and advise the public in the event of an emergency. • Share information with other local responders to enhance co- ordination. • Co-operate with other local responders to enhance co-ordination and efficiency. • Provide advice and assistance to businesses and voluntary organisations about business continuity management (local authorities only).

Resilience and Emergency Planning Team 3. The Resilience and Emergency Planning Manager continues to be responsible for ensuring that the Council adheres to the statutory duties outlined in paragraph 2 of this report, in adherence with the Civil Contingencies Act 2004.

4. The Resilience and Emergency Planning Team are generally the first point of contact during working hours when a response to an incident is required from the Council. The team will manage any escalation requirements to ensure a proportionate response is provided on behalf of the Council.

Emergency Response Team

Out of hours arrangements 5. During out of hours periods, a rota is in place to ensure that the Council can provide 24/7 incident response arrangements: • Initial point of contact: Care Call will receive the initial call, record the information using a specific template and relay the information on to the Emergency Response Team Duty Officer. • Emergency Response Team Duty Officer: this voluntary role is staffed by trained Council officers from a wide range of service areas. Upon receipt of the information from Care Call, an initial assessment will be made as to whether the incident can be managed using operational arrangements or if an escalation to emergency response arrangements is necessary. If an escalation is required, the duty officer will contact and liaise with a duty Incident Director. • Incident Directors: this role is undertaken by Strategic Directors/Service Directors (who are contractually obliged to undertake this role) to provide strategic leadership, make decisions and to commit resources as part of a proportionate incident response. • Communications Team Duty Officer: A Communications Team Officer will be on standby to support the incident response and will assist the Incident Director in providing accurate and consistent communications to the public, councillors and MPs, senior management and partner organisations. • The Council’s Go Gateshead service previously provided 24/7 arrangements to open and access Gateshead International Stadium as part of emergency reception centre arrangements. This arrangement now sits with GLL who manage the facility and were happy to continue with this arrangement to assist local residents during an emergency.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Resilience and Emergency Planning Annual UpdateReport 140 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 18 attended
JE
Councillor John EagleChair, apologies
KW
Councillor Kathryn WalkerVice-Chair, present
RB
Councillor Ron BeadleVice-Chair, present
MB
Councillor Malcolm BrainCommittee Member, present
BC
Councillor Brenda ClellandCommittee Member, present
BD
Councillor Bill DickCommittee Member, apologies
TG
Councillor Tom GrahamCommittee Member, apologies
JG
Councillor Jill GreenCommittee Member, present
SG
Councillor Stuart GreenCommittee Member, present
MM
Councillor Michael McNestryCommittee Member, present
SR
Councillor Steve RonchettiCommittee Member, present
JS
Councillor Julie SimpsonCommittee Member, present

All 18 on the meeting page

On this subject at Gateshead

Search all
  1. Resilience and Emergency Planning Annual UpdateThis decision
  2. Resilience and Emergency Planning UpdateNoted
  3. Strategic Resilience and Emergency Planning FrameworkApproved
  4. Strategic Resilience and Emergency Planning FrameworkAgreed
  5. Resilience and Emergency Planning Framework - Progress UpdateNoted

More from Gateshead Corporate Resources Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
22 Jun 2026 Performance Management and Improvement FrameworkRESOLVED that: i) The contents of the Annual Report at Appendix 1 be noted; ii) The additional information available ... Noted Open
22 Jun 2026 Work Programme 2026/27RESOLVED that: i) The proposed work programme items to date be noted; ii) Committee Members should share their views ... Noted Open
2 Apr 2026 Information Governance Annual ReportRESOLVED that the report be noted. Noted Open
12 Jan 2026 Budget Outturn Performance ReportRESOLVED that the report be noted. Noted Open
10 Nov 2025 Annual Workforce Strategy ReportRESOLVED that Corporate Resources OSC: i. Noted the report ii. Supported the delivery of the Corporate Workforce Stra... Noted Open