AI summaryCabinet has agreed to recommend that full Council approve Gateshead's 30 year Housing Revenue Account Business Plan for 2025 to 2055, projecting borrowing of £461.044 million by year 30 to fund stock investment and 500 new homes while keeping reserves above £3 million.
Written from the decision and the officer reportPDF Pro
OutcomeAgreed30 year HRA Business Plan 2025 to 2055
Money£461.044 millionprojected borrowing by year 30 of the plan
What happens nextFull Council to considerCabinet recommendation to be decided by full Council
Who it affectsCouncil tenants, all wardsAll wards in Gateshead affected by HRA proposals
What was decided
Cabinet agreed to recommend that full Council approve the 30 year Housing Revenue Account Business Plan for 2025 to 2055. Report P21
The plan assumes borrowing of £461.044 million by year 30, an increase of £115.539 million on the current underlying loan debt, while keeping the minimum HRA reserve balance at £3 million throughout the 30 years. Report P10, P15, P47, P48
The plan includes a programme to deliver over 500 new social and affordable homes by 2033, and assumes that £1.5 million of additional investment in repairs and maintenance in 2025/26 is removed over the following three years. Report P14, P19, P54
Why
To ensure the medium to long term sustainability of the Housing Revenue Account. Report P23
To deliver the Council's Housing Strategy and maintain and enhance Council housing provision in Gateshead. Report P24
To support the Council's vision set out in Making Gateshead a Place where Everyone Thrives. Report P25, P28
What happens next
Full Council will consider the recommendation to approve the 30 year Business Plan at a future meeting. Report P20, P21
The plan will be reviewed and refreshed at least annually, with a robust savings delivery plan to be developed during the budget setting process. Report P33, P65
Additional borrowing will be required from 2026/27 onwards, with the timing of any new borrowing to depend on cash flow needs and interest rates. Report P15, P48, P49
The money
£461.044 million projected total HRA borrowing by year 30 of the plan Report P15, P48
£115.539 million increase in borrowing above the current underlying loan debt Report P15, P48
£3 million minimum HRA reserve balance maintained throughout the 30 years Report P10, P47
£0.804 million HRA overspend reported in 2024/25 Provisional Revenue Outturn Report P6
£1.770 million increase in the revised 2025/26 HRA budget related to depreciation Report P7
£0.711 million forecast overspend on the revised 2025/26 HRA budget Report P7
£1.5 million additional investment in repairs and maintenance in 2025/26, removed over 2026/27 to 2028/29 Report P14
£39 billion Government Social and Affordable Homes Programme for 2026 to 2036 Report P44
Options considered
Chosen: Approve the 30 year HRA Business Plan 2025 to 2055. Ensures long term sustainability of the HRA and supports the Council's housing and corporate priorities; no alternative options were proposed. Report P21, P22, P57
Implications
Financial: The HRA reserve balance is projected to remain above £3 million over the 30 year plan, but the plan is sensitive to changes in assumptions about rent, voids, and costs. Report P11, P47, P61, P65
Risk: Borrowing and debt affordability will be kept under review, with interest rates monitored to inform the timing of any new borrowing. Report P16, P49, P62
Equalities: An equality impact framework has been developed to assess efficiency proposals arising from the plan. Report P66
Climate: The capital programme includes progress towards net zero carbon and other sustainability measures for the housing stock. Report P51, P69
Staffing: Any direct human resources implications will form part of the budget planning framework and identification of budget proposals. Report P63
Other: Capital investment in HRA assets supports the delivery of corporate priorities under the Thrive agenda. Report P64
Other: There are no direct crime and disorder, health, or human rights implications identified, with health outcomes expected to be positive. Report P67, P68, P70
Other: All wards in the Borough are affected by the proposals. Report P71
Who and where
Council tenants across all wards in Gateshead Report P30, P71
Households waiting for new social and affordable housing Report P19, P54
Residents in older persons accommodation and high rise blocks subject to stock options reviews and demolitions Report P53
Prospective fostering households using the social housing portfolio Report P51
The Council as landlord and its wider housing service, last graded C2 by the Regulator of Social Housing Report P2, P41
Timeline
20 February 2025: Council agreed the HRA budget for 2025/26 and the prior business plan Report P3, P34
11 June 2025: Government confirmed a 10 year social housing rent settlement of CPI plus 1% from April 2026 Report P4, P43
2 July 2025: Government issued consultation on implementing social rent convergence, with outcome expected in the Autumn Budget Report P5, P45
15 July 2025: Cabinet received the Provisional Revenue Outturn 2024/25 and the HRA First Quarter Review 2025/26 Report P6, P7
2026/27: Additional borrowing is expected to be required to support the HRA capital programme Report P15, P48
April 2026: New 10 year social housing rent settlement begins, with rent convergence mechanism confirmed in the Autumn Budget Report P4, P43, P45
2026 to 2036: Government Social and Affordable Homes Programme period, with £39 billion available Report P44
by 2033: Target for delivery of over 500 new social and affordable homes from the HRA Report P19, P54
Plain English for the jargon
HRA: Housing Revenue Account: the ringfenced fund councils use to manage and maintain their own housing stock
CPI: Consumer Price Index, the main measure of inflation used by the Government
Right to Buy: Government policy allowing eligible council tenants to buy their home at a discount
RSH: Regulator of Social Housing, which grades providers on consumer standards
Rent convergence: Government proposal to bring social rents closer together, with a maximum additional weekly amount under consultation
Net zero carbon: Reducing carbon emissions to as close to zero as possible, with any remaining emissions balanced by removals
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemC74
Resolved
i ) That Cabinet agreed to recommend Council approval of the 30 Year Business Plan 2025–2055 as set out in Appendix 2. The above decision was made for the following reasons: a) To ensure the medium to long term sustainability of the Housing Revenue Account. b) To realise the Council’s policies and objectives in relation to the Housing Strategy, maintaining and enhancing Council Housing provision in Gateshead. c) To assist in the delivery of the Council’s vision for Gateshead as set out in Making Gateshead a Place where Everyone Thrives.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. Cabinet is asked to recommend to Council the proposed Housing Revenue Account (HRA) 30-year Business Plan 2025-2055.
Background
2. The HRA Business Plan is a key strategic document which sets out the Council’s income and expenditure plans for delivering Council Housing Services in Gateshead.
3. On 20 February 2025 Council agreed the Housing Revenue Account (HRA) budget for 2025/26 which outlined draft budget estimates for the next 4 years and business plan which continued to be viable over 30 years.
4. On 11 June 2025 the Government confirmed a 10-year social housing rent settlement from April 2026 of CPI+1% plus the intention to consult on how to implement social rent convergence.
5. On 2 July 2025 the Government issued the consultation on how to implement social rent convergence which proposed either £1 or £2 maximum additional weekly amount and requested views on the timing i.e. should it fall in line with the new rent policy. The details of precisely how, and at what level, this mechanism will be implemented will be confirmed in the Autumn Budget.
6. On 15 July 2025 Cabinet received the Provisional Revenue Outturn 2024/25 report which included the HRA position, an overspend of £0.804 million which is in line with reported projections.
7. On 15 July 2025 Cabinet also received the Housing Revenue Account Budget – First Quarter Review 2025/26 which asked it to recommend to Council a revised budget, an increase of £1.770 million related to depreciation and a forecast overspend of £0.711 million on this revised budget.
8. Given the HRA business plan is a 30-year plan the longer-term assumptions become more subjective and are likely to change and therefore it is of utmost importance that the medium term planning horizon is robust. It continues to be challenging given the current uncertain financial environment.
1 of 8 Proposal
9. Overall, the revised HRA Business Plan (appendix 2) is a fully costed, sustainable plan and does not breach the minimum £3 million reserve balance during the life of the plan (30 years).
10. The plan is setting out the financial trajectory for the HRA based on specific assumptions which are clearly outlined. Any variation to these assumptions will have an impact on the plan and therefore an impact on stock investment plans, council new build and the provision of housing services.
11. To incorporate all the cost pressures and anticipated capital investment, including new social housing stock, over the longer term borrowing will need rise significantly above the current levels and medium-term efficiency savings will be required.
12. In refreshing the business plan, it is assumed that management interventions during 2025/26 will enable the HRA to be delivered on budget.
13. The plan assumes the £1.5 million additional investment in repairs and maintenance in 2025/26 is removed over the period 2026/27 – 2028/29. This is in addition to savings which should accrue from the reduction in stock numbers.
14. To accommodate the stock investments and associated cost implications based on current assumptions borrowing would increase by £115.539 million to £461.044 million by year 30. Additional borrowing will start to accrue in year 2 of the plan.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.