Local Transport Plan Capital Programme Mid-Year Update (December 2025)

Approved Executive 2 papers

AI summaryGateshead Cabinet approved revised 2025/26 transport capital programmes and indicative 2026/27 plans, with flexibility to award contracts and adjust schemes during the year.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedRevised 2025/26 programmes and indicative 2026/27 plans
Money£7.19m maintenance, £1.23m integrated transport 2025/26Plus £20.04m external and prudential borrowing
What happens nextNot stated
Who it affectsAll wards in Gateshead boroughHighways, cycleways, buses, active travel

What was decided

Cabinet approved the revised 2025/26 integrated transport and maintenance programmes in Appendices A and B, noting ongoing review may be needed. Report P7

Cabinet authorised the Service Director, Highways and Waste to award works under the Highways, Drainage and Street Lighting Maintenance Contract. Report P7

Cabinet authorised the Interim Service Director, Climate Change, Compliance, Planning and Transport to amend the approved programme after consulting the Cabinet Member for Environment and Transport. Report P7

Cabinet approved the indicative 2026/27 integrated transport and maintenance programmes in Appendices C and D as a basis for future planning. Report P7

Why

To enable design and implementation of transport schemes supporting the North East Transport Plan and the Council's policy objectives. Report P9

Programmes support the Thrive agenda, the Core Strategy, the North East Local Transport Plan, the Highways Asset Management Plan, the Health and Wellbeing Strategy and the Council's climate emergency initiatives. Report P12

The capital programme is managed flexibly with overprogramming to ensure the Local Transport Plan grant and other funding are fully used, and minor changes have been made during the year. Report P6

What happens next

The Highways, Drainage and Street Lighting Maintenance Contract works can be awarded by the Service Director, Highways and Waste. Report P7

Indicative 2026/27 schemes will be subject to further consultation with members before being finalised. Report P21

Several schemes on hold because of the flyover closure, including Albany Road pedestrian crossing, Bensham Road roundabout and final two Regional ITS locations, will be kept under review. Report P17

The money

  • £1.197 million LTP integrated transport allocation for 2025/26 Report P16
  • £0.35 million Additional public transport grant expected via NECA Report P16
  • £1.23 million Total integrated transport LTP funding expected 2025/26 Report P16
  • £20.04 million External funding and prudential borrowing for integrated transport 2025/26 Report P16
  • £1.55 million Integrated transport funding carried over from 2024/25 Report P16
  • £7.19 million Total maintenance funding 2025/26 including CRSTS supplement and underspend Report P19
  • £3.86 million Prudential borrowing for maintenance, traffic signals, lighting, surfacing, footways Report P19
  • £9,556,626 Regional BSIP funding approved by Cabinet for bus corridor improvements Report P28
  • £163.5 million Regional BSIP package submitted to Government in 2021 Report P27

Options considered

  • Chosen: Approve revised 2025/26 programmes and indicative 2026/27 programmes as recommended. Only deliverable option to meet regional policy objectives and local priorities. Report P36, P7
  • Rejected: Consider alternative options to the transport capital programme. No alternative considered; the programme is the only deliverable option to meet regional policy objectives while supporting more local priorities. Report P36

Implications

  • Financial: The Strategic Director, Resources and Digital confirms there is sufficient allocation within the capital programme to fund Appendices A and B. Report P38
  • Risk: Significant underspend or failure to deliver externally funded schemes could lead to loss of that funding and jeopardise future funding. Report P39
  • Legal: Individual schemes may require legal advice or procedures such as traffic regulation orders or land ownership changes, handled case by case. Report P40
  • Staffing: The programme has significant resource implications for Transport Strategy, Highway Operations, Maintenance and Streetscene teams, with sector-wide challenges retaining staff. Report P41
  • Equalities: An Integrated Impact Assessment was completed alongside the June 2025 Capital Programme Year End Report; the assessment is unchanged at this Q2 update. Report P42
  • Climate: The programme is aligned with the Council's climate emergency initiatives, seeking to reduce car dependence, increase active travel and cut carbon emissions. Report P12, P45
  • Other: Proposals in the integrated transport programme will help improve safety and security for the travelling public. Report P43

Who and where

  • All wards in Gateshead borough Report P47
  • Bus passengers using BSIP corridors into and through the borough Report P28
  • Cyclists and pedestrians using new and improved cycleways and crossings Report P13, P17
  • Residents of specific scheme areas including Felling, Deckham, Birtley, Ryton, Gateshead town centre, and the A1 Coalhouse to Birtley corridor Report P22, P23, P31
  • Council teams in Transport Strategy, Highway Operations, Maintenance and Streetscene Report P41
  • Electric vehicle users benefitting from additional charging points Report P21, P30

Timeline

  • 2025/26: Revised integrated transport and maintenance programmes in operation for the current financial year. Report P6, P7
  • End of 2025/26: Firm costs for West Tyneside Cycleway and Durham Road Cycleway expected by year end. Report P17
  • 2026/27: Indicative integrated transport and maintenance programmes to be delivered, subject to confirmation of LTP allocation. Report P4, P18, P21
  • March 2027: End of CRSTS1 period; construction of CRSTS-funded schemes must be completed by this date. Report P33
  • 2027 to 2032: Transport for City Regions five-year devolved funding programme period for the North East, with early development underway. Report P33

Plain English for the jargon

  • LTP: Local Transport Plan, government funding allocated to integrated transport schemes and highways maintenance.
  • NECA: North East Combined Authority, through which integrated transport funding is routed.
  • CRSTS: City Regional Sustainable Transport Settlement, a multi-year devolved transport funding stream.
  • BSIP: Bus Service Improvement Plan, a regional programme of bus corridor improvements funded by the Department for Transport.
  • ATF: Active Travel Fund, government funding for walking and cycling infrastructure.
  • LCWIP: Local Cycling and Walking Infrastructure Plan, being developed for Gateshead.
  • TCR: Transport for City Regions, a proposed significant devolved funding programme for the North East covering 2027 to 2032.
  • VMS: Variable Message Sign, electronic roadside signs used for traffic information.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemC109

Resolved

i) Cabinet approved the revised programmes for 2025/26 as set out in Appendices A and B, noting the need for ongoing review. ii) Cabinet authorised the Service Director, Highways and Waste to award relevant works under the Highways, Drainage and Street Lighting Maintenance Contract. iii) Cabinet authorised the Interim Service Director, Climate Change, Compliance, Planning & Transport to make changes to the approved programme following consultation with the Cabinet Member for Environment and Transport. iv) Cabinet approved the indicative integrated transport and maintenance programmes for 2026/27 as a basis for future planning. The above decision was made for the following reason: a) To enable the design and implementation of transport schemes in support of the North East Transport Plan and the Council’s policy objectives.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1. This report is an update on the Local Transport Plan (LTP) Capital Programme. It provides a summary of the progress that has been made and any changes to the programme that have occurred as of the end of Quarter 2. Indicative programmes for integrated transport and maintenance schemes scheduled for 2026/27 are included as appendices to allow for forward planning of these works.

Background

2. LTP funding is allocated by government and provides a source of funding for integrated transport schemes and maintenance of highways and structures. It is supplemented wherever possible by external sources such as developer contributions and bids for government funding, or prudential borrowing. Investment in highways infrastructure is identified and prioritised in accordance with the Council’s Highways Asset Management Plan

3. The integrated transport and maintenance programmes were approved by Cabinet in June 2025.

4. The indicative programmes for 2026/27 are provisionally based on receiving the same LTP allocation as in 2025/26 and can be adjusted as necessary dependent on the final funding allocation.

Proposal

5. The transport capital programme is managed flexibly and includes an element of overprogramming to ensure that the LTP grant and other funding sources are fully utilised. Some minor changes to the programme have occurred during the first part of the year. These changes have been set out in the report and in the appended programmes.

Recommendations

6. It is recommended that Cabinet: i. Approves the revised programmes for 2025/26 as set out in Appendices A and B, noting that there may be a need to review these as the year progresses in line with available resources. ii. Authorises the Service Director, Highways and Waste to award the relevant works under the terms of the Highways, Drainage and Street Lighting Maintenance Contract. iii. Authorises the Interim Service Director, Climate Change, Compliance, Planning & Transport to make changes to the approved programme following consultation with the Cabinet Member for Environment and Transport, as and when the need arises. iv. Approves the indicative integrated transport and maintenance programmes for 2026/27 as set out in Appendices C and D as a basis for future planning.

For the following reason(s):

i. To enable the design and implementation of transport schemes in support of the North East Transport Plan and the Council’s policy objectives.

Contact: David Majarich

Extension: 3851 Email: [email protected] APPENDIX 1

Policy Context 1. The programmes support the pledges within Gateshead Council’s Thrive agenda. They also support the Core Strategy and Urban Core Plan, the aims and objectives of the North East Local Transport Plan, the Gateshead Highway Asset Management Plan, Gateshead’s Economic Development Strategy and Housing Strategy and the Gateshead Health and Wellbeing Strategy. The programmes are aligned with the Council’s initiatives to tackle the climate emergency. Furthermore, the proposed programme utilises funding received through specific government grants as well as the proposed use of Council resources.

Background 2. LTP funding is allocated by government and provides a source of funding for integrated transport schemes and maintenance of highways and structures. The integrated transport funding comes via NECA and covers a range of works including bus priority, new and improved cycleways, better pedestrian facilities, and road safety improvements. Investment in highways infrastructure is guided by the principles set out in the Highways Asset Management Plan.

3. LTP funding is supplemented wherever possible by prudential borrowing or external funding sources including developer contributions and other capital grants and where necessary by prudential borrowing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Local Transport Plan Capital Programme Mid-Year Update (December 2025)Report 283 KB DownloadRead as text
PDF
Local Transport Plan Capital Programme Mid-Year Update BReport 137 KB Download

At this meeting

Whole meeting

Who was there

10 of 15 attended
MG
Councillor Martin GannonChair, present
GH
Councillor Gary HaleyVice-Chair, present
CD
Councillor Catherine DonovanCommittee Member, present
JA
Councillor John AdamsCommittee Member, present
CB
Councillor Chris BuckleyCommittee Member, present
AD
Councillor Angela DouglasCommittee Member, present
MH
Councillor Maria HallCommittee Member, present
LK
Councillor Leigh KirtonCommittee Member, present
JM
Councillor John McElroyCommittee Member, present
BO
Councillor Bernadette OliphantCommittee Member, present
MM
Melvyn Mallam-ChurchillSecretary, expected
BF
Brian FaganOfficer, expected

All 15 on the meeting page

On this subject at Gateshead

Search all
  1. Local Transport Plan Capital Programme Mid-Year Update (December 2025)This decision
  2. Local Transport Plan Capital Programme Year End ReportApproved
  3. Local Transport Plan: Capital Programme Mid-Year UpdateApproved
  4. Local Transport Plan: Capital Programme Year End ReportApproved
  5. Local Transport Plan: Capital Programme Mid-Year Update (November 2023)Approved
  6. Local Transport Plan: Capital Programme Year End Report (May 2023)Approved

More from Gateshead Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Approval of Refreshed Resident Influence Strategyi) To approve the Resident Influence Strategy (Appendix 2). ii) To authorise implementation of the strategy supported... Approved Open
22 Sep 2026 Business North East Business Support Frameworki) To agree that the Council be included as a named delivery partner in NEMSA’s Business North East business case and... Agreed Open
22 Sep 2026 NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ... Approved Open
22 Sep 2026 Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report... Approved Open
22 Sep 2026 Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other... Approved Open