Budget 2026/27 update and provisional Local Government Finance Settlement
NotedExecutive1 paper
AI summaryGateshead Cabinet noted the provisional 2026/27 funding settlement and approved the start of internal staff and union consultation on workforce budget proposals, ahead of a final budget in February 2026.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted funding update, budget planning update, government consultation response
Money£20.528m MTFS gapTo be closed by reserves, social care interventions, cuts
What happens nextFinal Cabinet 24 February 2026Full Council approval on 26 February 2026
Who it affectsCouncil workforce and residentsStaff consultation on redundancy proposals open 14 Jan to 12 Feb 2026
What was decided
Cabinet noted the update to the funding position, including the outcome of the provisional Local Government Finance Settlement set out in Appendix 1. Report P23
Cabinet noted the update on the 2026/27 budget planning process. Report P23
Cabinet approved the commencement of internal consultation with employees and trade unions on workforce related budget proposals for 2026/27 as detailed in Appendix 3. Report P23
Why
To contribute to the good financial management practice of the Council. Report P25
To assist the financial sustainability of the Council over the medium to long term. Report P25
To support delivery of the Council's Corporate Plan priorities and the Thrive objectives. Report P25
What happens next
Internal employee consultation on workforce budget proposals will run from 14 January 2026 to 12 February 2026, with comments sent to [email protected]. Report P20
Full Council Tax and Budget proposals will be reported to Cabinet on 24 February 2026 and considered for approval by Council on 26 February 2026. Report P18
Any workforce proposals resulting in compulsory redundancies would be implemented from 1 April 2026. Report P21
£4.000m Planned use of reserves to close the gap Report P4
£5.912m Social care interventions to close the gap Report P4
£10.616m Budget cuts and efficiencies to close the gap Report P4
£17.2m Budget sustainability reserve balance as at 31 March 2025 Report P2
4.99% Assumed combined Council Tax increase (2.99% core and 2% Adult Social Care precept) Report P12, P37
Options considered
Rejected: No alternative options proposed. Local authorities are legally obliged to set a balanced budget each year and to ensure they have sufficient reserves to cover any unexpected events Report P49
Implications
Financial: The Council will deliver a balanced budget consistent with legislation through planned use of reserves, budget cuts and service interventions. Report P52
Legal: There is a requirement to enter into the statutory period of consultation with employees affected by the proposals; failure to do so exposes the Council to the risk of claims from affected employees. Report P55
Staffing: A collective consultation period of no less than 30 days will be applied, with statutory redundancy consultation under section 188 of the Trade Union and Labour Relations (Consolidation) Act 1992. Report P55
Equalities: Integrated Impact Assessments are being developed and will be available to stakeholders as part of the consultation process on request. Report P57
Risk: The use of reserves over the period of the MTFS carries a risk to the Council's financial sustainability if savings are not identified and delivered. Report P54
Other: Increased financial pressure and stress experienced by some groups affected by proposals can have multiple impacts on health and wellbeing. Report P59
Who and where
Council employees and trade unions Report P21, P55
All wards in Gateshead Report P62
Council tax payers Report P36
Local businesses affected by business rates changes Report P45
Timeline
17 December 2025: Provisional Local Government Finance Settlement announced Report P8
14 January 2026: Government consultation period on the provisional settlement ends Report P8
14 January 2026: Internal employee consultation on workforce budget proposals begins Report P20
31 January 2026: NNDR 1 return must be submitted to the Government Report P45
Early February 2026: Final Local Government Finance Settlement expected to be confirmed Report P50, P53
12 February 2026: Internal employee consultation ends Report P20
24 February 2026: Full Council Tax and Budget proposals reported to Cabinet Report P18
26 February 2026: Budget considered for approval by full Council Report P18
1 April 2026: Any compulsory redundancies implemented from this date Report P21
Plain English for the jargon
MTFS: Medium Term Financial Strategy, the Council's forward-looking financial plan
CSP: Core Spending Power, a government measure indicating the impact of changes in local authority funding
FFA: Fair Funding Assessment, the main formula-based funding allocation for local authorities
RSG: Revenue Support Grant, general government funding for local authority services
NNDR 1: National Non-Domestic Rates return forecasting business rates income to be retained by the Council
FTE: Full-Time Equivalent, a measure of staffing posts
IIA: Integrated Impact Assessment, an assessment of equalities and other impacts
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemC118
Resolved
i) That the update to the funding position, including the outcome of the Provisional Local Government Finance Settlement set out in Appendix 1, be noted. ii) That the update on the 2026/27 budget planning process be noted. iii) That the response to the Government consultation on the Provisional Local Government Finance Settlement included at Appendix 2 be noted. iv) That approval be given to the commencement of internal consultation with employees and trade unions on workforce related budget proposals for 2026/27 as detailed in Appendix 3. The above decision was made for the following reasons: a) To contribute to the good financial management practice of the Council. b) To assist the financial sustainability of the Council over the medium to long term. c) To support delivery of the Council’s Corporate Plan priorities and the Thrive objectives.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
2. In December 2021 Cabinet approved the planned use of £20m of the budget sustainability reserve over three financial years to 2024/25.
3. In October 2023, Cabinet agreed to extend the planned use of reserves for a further two years to 2026/27. The budget sustainability reserve balance as at the 31 March 2025 stood at £17.2m.
4. The current Medium Term Financial Strategy (MTFS), approved by Cabinet in September 2025, confirmed that the reliance on reserves to balance the budget is forecast to end in 2026/27. Further to this, the MTFS assumes that the Council will start to replenish reserves from 2027/28 onwards.
5. For 2026/27 there was an estimated MTFS gap of £20.528m which was projected would be closed in the following ways: • using £4.000m of reserves, • implementing £5.912m of social care interventions; and • identifying £10.616m of budget cuts and efficiencies.
6. The funding assumptions within the MTFS presented to Cabinet in September 2025 have not materially changed following the announcement of the provisional local government finance settlement on the 17 December 2025.
Provisional Local Government Finance Settlement 2026/27
7. The provisional settlement is an important stage in the budget setting process as it provides a firmer base for the resource assumptions.
8. The provisional settlement was announced on 17 December 2025, the Government opened a four-week consultation period ending on the 14 January 2026 . The provisional settlement is the first multi-year settlement in over a decade but will still be revised every year due to changes in population estimates and refinements to the Business rates base. The settlement is largely in keeping with the Chancellor’s Budget Statement and Local Government Finance Policy Statement.
9. In addition to being a multi-year settlement, this provisional settlement was created using formula within the Fair Funding Review 2.0. The Government’s aim was to direct funding to those areas with the greatest need and the Government is equalising need based on Core Spending power per head.
Core Spending Power
10. The Government uses a measure known as Core Spending Power (CSP) to indicate the impact of changes in funding. The CSP is not in itself a statement of the actual resources available to the Council. It is simply a mechanism used by Government to illustrate the potential funds available to Local Authorities. For 2026/27, the measure includes:
• Fair Funding Assessment (SFA) comprising: Revenue Support Grant (RSG) Top up Grant Assumed Retained business rates and Local Authority Better Care Grant • Council Tax income, which as detailed previously is assumed by Government to increase by 4.99% (2.99% Council Tax and 2% Adult Social Care precept) in addition to any growth in the Council Tax base;
11. Further details on the provision settlement are provided in Appendix 1.
Summary Budget Position Update 2026/27 12. The approach to the budget remains in line with the assumptions within the MTFS. Whilst there is still uncertainty around funding and budget pressures, the Council will deliver a balanced budget through the planned use of reserves, budget cuts and planned service interventions. 13. There are areas of significant impact which are still currently unknown, namely:
• the Council’s retained business rates position,
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.