CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Gateshead Metropolitan Borough Council
Cabinet, Tuesday 20 January 2026 at 10.00am

Capital Programme and Prudential Indicators – Third Quarter Review 2025/26

Agreed Executive 2 papers

AI summaryGateshead Cabinet recommends cutting the 2025/26 capital programme by £18.048m to £118.576m, with no prudential limits breached.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedVariations to 2025/26 capital programme
Money£118.576m revised programmeDown £18.048m from original budget
What happens nextFull Council approvalCabinet recommends to Council
Who it affectsGateshead residentsWards across the borough

What was decided

Cabinet agreed to recommend to Council approval of variations to the 2025/26 Capital Programme set out in Appendix 2. Report P18

Cabinet agreed to recommend to Council the financing of the revised programme as outlined in the report. Report P18

Cabinet confirmed to Council that no approved Prudential Indicators for 2025/26 have been breached. Report P18, P55

Why

To ensure optimal use of the Council's capital resources in 2025/26. Report P20, P31

To accommodate changes to in-year capital expenditure plans, including the £18.048m reduction and slippage of £38.656m. Report P20, P27, P51

To ensure performance has been assessed against the approved Prudential Limits. Report P20, P15

What happens next

Cabinet recommends the variations to a future meeting of full Council for approval. Report P18

Cabinet will continue to receive quarterly capital monitoring reports and recommend any issues to Council. Report P34

The money

  • £118.576m Revised planned capital expenditure for 2025/26 at Q3 Report P13, P2
  • £157.232m Original 2025/26 capital budget agreed by Council 20 February 2025 Report P2, P14, P25
  • £18.048m Net reduction from the original budget at Q3 Report P27, P48
  • £38.656m Slippage forecast in 2025/26 against the five-year programme Report P9, P51
  • £54.160m Forecast increase over the original five-year programme Report P9, P51
  • £679.455m Revised five-year capital programme total 2025/26 to 2029/30 Report P49, P51
  • £625.295m Original five-year capital programme approved by Council February 2025 Report P9, P50

Options considered

  • Chosen: Approve the proposed variations and financing. Best available arrangement to ensure optimum use of capital resources in 2025/26 Report P31

Implications

  • Financial: The Strategic Director, Resources and Digital confirms the financial implications are as set out in the report and appendices. Report P33
  • Risk: Risks are assessed through programme monitoring and treasury management, with quarterly reports continuing to Cabinet. Report P34
  • Legal: No legal implications arising from the report. Report P35
  • Equalities: No equality and diversity implications arising from the report. Report P37
  • Staffing: No human resources implications arising from the report. Report P36
  • Other: No direct crime and disorder implications arising from the report. Report P38
  • Other: No direct human rights implications arising from the report. Report P41
  • Climate: Sustainability implications are considered for individual projects; planned investment is expected to result in improvements across the borough. Report P40

Who and where

  • Residents across Gateshead borough, with capital schemes delivering improvements in wards throughout the area Report P42
  • Service users of specific schemes covering transport, housing, schools, adult social care, and leisure facilities Report P48

Timeline

  • 20 February 2025: Original 2025/26 to 2029/30 capital programme of £625.295m agreed by Council Report P2, P15, P25, P50
  • 17 July 2025: First quarter capital review reported to Council Report P45
  • 20 November 2025: Second quarter capital review reported to Council Report P46
  • 31 December 2025: End of third quarter monitoring period for the report Report P1, P54
  • 20 January 2026: Cabinet considers third quarter review (this report) Report P1

Plain English for the jargon

  • Prudential Indicators: Statutory measures set under CIPFA's Prudential Code that regulate a council's borrowing, capital expenditure and investment.
  • CIPFA: Chartered Institute of Public Finance and Accountancy, the professional body for public finance.
  • HRA: Housing Revenue Account, the ring-fenced account for council housing income and spending.
  • General Fund: The main council fund for services other than council housing.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemC124

Resolved

i) That Cabinet agreed to recommend to Council approval of the variations to the 2025/26 Capital Programme as set out in Appendix 2. ii) That Cabinet agreed to recommend to Council the financing of the revised programme as outlined in the report. iii) That Cabinet confirmed to Council that the capital expenditure and financing requirement indicators have been updated in line with the amended budget and that no approved Prudential Indicators for 2025/26 have been breached. The above decision was made for the following reasons: a) To ensure optimal use of the Council’s capital resources in 2025/26. b) To accommodate changes to the Council’s in-year capital expenditure plans. c) To ensure performance has been assessed against the approved Prudential Limits.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1. This report sets out the latest position on the 2025/26 Capital Programme and Prudential Indicators at the end of the third quarter to 31 December 2025. The report assesses reasons for the variances from the approved programme and details the proposed financing of the Capital Programme. In addition, the report considers the impact of CIPFA’s Prudential Code on the Capital Programme and the monitoring of performance against the statutory Prudential Indicators.

Background

2. The original budget for the Capital Programme for 2025/26, as agreed by Council on 20 February 2025, totalled £157.2m. At the first quarter review, this reduced to £145.5m, at the second quarter review reduced to £136.6m and at the third quarter review expenditure is now projected to be £118.6m; £82.9m General Fund and £35.7m HRA by year end.

3. The proposed changes to the 2025/26 Capital Programme are shown in Appendix 2 and are summarised below.

Slippage • (£7.872m) Local Transport Plan – Integrated Transport Bus Service Improvement Plan (BSIP) – Re-profiling of schemes. • (£5.000m) School Basic Need Funding – Funding now allocated to projects for 2026/27. • (£3.200m) Clasper Housing Development – Works delayed and now expected to commence in June 2026. • (£1.550m) Loan to GECo. Green Heat Network – Re-Profiling of scheme. • (£0.775m) Extra Care Scheme - Slippage to future years • (£0.700m) Flood Alleviation Investment – Re-profiling of schemes.

Accelerated spend • £0.793m Local Transport Plan – Planned Maintenance

1 of 5 New projects added to the current year

• £1.000m Maiden Walk Coal Drops • £0.750m Pride in Place • £0.220m Metro Riverside

4. The other changes relate to minor amendments to realign the schemes within the programme based on updated forecasts from project leads.

5. It is also important to consider how a change in year impacts the five-year programme. Appendix 3 demonstrates how slippage in one year impacts future years as resources are realigned to the revised phasing of schemes. Whilst there is slippage of £38.7m forecast in the current year, over the five-year programme it is estimated that spend will be £54.1m more than the original £625.3m approved by Council in February 2025. The main reasons for this are:

• Additional grant funding on Transport schemes within Economy, Innovation and Growth. • Additional grant funding for Schools SEN and additional spend on waste collection vehicles within Housing, Environment and Health Communities. • Slippage from previous years and new grant funded projects.

6. Appendix 4 shows how the revised five-year programme is expected to be funded based on the information available. This position may change as we move towards outturn, particularly if further grant funding becomes available.

Proposal

7. The report identifies revised planned capital expenditure of £118.576m for the 2025/26 financial year. The expected resources required to fund the Capital Programme for each revision are shown below:

Original Qtr. 1 Qtr. 2 Qtr. 3 Budget Revised Revised Revised £m Budget Budget Budget £m £m £m Borrowing 70.483 50.066 48.220 46.337 Capital Grants & Contributions 41.654 45.267 51.060 35.196 General Fund Capital Receipts 0.750 1.326 1.326 1.333 Major Repairs Reserve (HRA) 18.868 20.886 20.886 20.886 HRA Capital Receipts 25.219 27.568 13.980 13.672 Capital Grants & Contributions (HRA) 0.258 0.420 1.152 1.152 Total 157.232 145.533 136.624 118.576

8. CIPFA’s Prudential Code advises the regular monitoring of performance against the prudential indicators which regulate borrowing and investment. Targets and limits for the prudential indicators for 2025/26 were agreed at Council on 20 February 2025 and borrowing and investment levels have remained within these limits. Performance against the indicators for 2025/26 is set out in Appendix 5.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme and Prudential Indicators: Third Quarter Review 2025/26Report 608 KB DownloadRead as text
PDF
RTC Capital Programme and Prudential Indicators: Third Quarter Review 202526 BReport 193 KB Download

At this meeting

Whole meeting

Who was there

9 of 14 attended
MG
Councillor Martin GannonChair, present
GH
Councillor Gary HaleyVice-Chair, present
CD
Councillor Catherine DonovanCommittee Member, apologies
JA
Councillor John AdamsCommittee Member, present
CB
Councillor Chris BuckleyCommittee Member, present
AD
Councillor Angela DouglasCommittee Member, present
MH
Councillor Maria HallCommittee Member, present
LK
Councillor Leigh KirtonCommittee Member, present
JM
Councillor John McElroyCommittee Member, present
BO
Councillor Bernadette OliphantCommittee Member, present
MM
Melvyn Mallam-ChurchillSecretary, in attendance
DC
Darren CollinsOfficer, in attendance

All 14 on the meeting page

On this subject at Gateshead

Search all
  1. Capital Programme and Prudential Indicators – Third Quarter Review 2025/26This decision
  2. Capital Programme and Prudential Indicators - Year End Outturn 2025-26Noted
  3. Capital Programme and Prudential Indicators - First Quarter Review 2026-27Approved
  4. Capital Programme and Prudential Indicators – Year End Outturn 2025-26Approved
  5. Capital Programme and Prudential Indicators – First Quarter Review 2026-27Approved
  6. Transport Capital Programme Year End ReportApproved

More from Gateshead Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Approval of Refreshed Resident Influence Strategyi) To approve the Resident Influence Strategy (Appendix 2). ii) To authorise implementation of the strategy supported... Approved Open
22 Sep 2026 Business North East Business Support Frameworki) To agree that the Council be included as a named delivery partner in NEMSA’s Business North East business case and... Agreed Open
22 Sep 2026 NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ... Approved Open
22 Sep 2026 Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report... Approved Open
22 Sep 2026 Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other... Approved Open