1) To note the Council Plan Performance and Budget Outturn figures for 2012/13; 2) To note the revenue carry forwards approved by the Chief Financial Officer of £24,300 included in Appendix 2, being amounts not in excess of £10,000; 3) To note the capital carry forwards approved by the Chief Financial Officer of £735,500 included in Appendix 2, being amounts not in excess of £50,000 and committed schemes above £50,000; 4) To agree the proposed changes to Improvement Actions as set out in Section 4; 5) To refer to Council for approval: i) The revenue carry forward of £90,000 for the Superfast Broadband Scheme being a non-committed scheme in excess of £10,000; ii) The capital carry forward of £103,300 for the Disabled Facilities Grants Scheme being a non-committed scheme in excess of £50,000; iii) The overall method of financing of the 2012/13 capital expenditure as set out in Appendix 7 of the report; iv) The capital determinations in Section 3.4.
Word for word from the decision Gedling published for this meeting.Source: democracy.gedling.gov.uk
This report presents the Council Plan and Budget Outturn and Budget Carry Forwards for 2012/13.
Cabinet is asked to note the final outturn position for 2012/13 and recommend that Council:
a) Approve the method of financing the 2012/13 capital expenditure which includes making the Capital Determinations required by the Local Government and Housing Act 1989; b) Approve the carry forward of budgets from 2012/13 as additions to the 2013/14 budgets, in accordance with financial regulations.
Key Decision
This is a not a key decision
Background
1.1The Council’s financial regulations allow for the carry forward of capital and revenue budgets to the new financial year where there is an underspend against the approved budget.
1.2The Chief Financial Officer has delegated authority to approve the carry forward of contractually committed schemes above £50,000 for Capital and £10,000 for Revenue, and all schemes where the underspend does not exceed £50,000 for Capital and £10,000 for Revenue, subject to reporting the source of the under-spend and the subsequent use of the carry forward to the Portfolio Holder.
1.3Approval of full Council is required for schemes, which are not contractually committed, with a value over £50,000 for Capital and £10,000 for Revenue.
Further information on the subject of this report is available from Alison Ball, Financial Services Manager on (0115) 9013980 Proposal
2.1Summary Budget Outturn Position
This report highlights continued good management of the Revenue and Capital budgets and overall Council performance. The Council has a revenue underspend of £426,151 against the Original Estimate, or £293,851 against the Current Estimate i.e. the latest quarter 3 monitoring projection. Capital expenditure is broadly in line with the Current Estimate after accounting for carry forwards proposals.
2012/13 was a year of significant uncertainty for the future funding of Local Government with preparations for the implementation of the new funding mechanisms introduced in the Local Government Resource Review i.e. Business Rate Retention and Council Tax Discount Scheme. The Local Government Finance Settlement also announced higher than anticipated grant reductions for 2013/14 with an indication of further significant cuts to come. This together with the continuing downturn in the economy putting pressure on both the Council’s expenditure and income streams means that 2012/13 has been a challenging financial year.
Against this backdrop Services have responded well to delivering efficiency savings for the 2013/14 budget and where possible have implemented these early contributing to the 2012/13 under-spend. The outturn position will be analysed to identify any further under-spends which can be removed from the future budget.
Given the extent of changes this represents a robust outturn position for the Council which is in line with the revised medium term financial plan projections for 2012/13 and which increases reserve balances and provisions in a worsening economic and funding climate.
2.2General Fund Revenue Outturn 2012/13
2.2.1 The actual net revenue expenditure for each Portfolio area 2012/13 is detailed in Appendix 1, together with explanations of major variances in expenditure and income.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.