Application No. 2012/1472- Severn Trent Water PLC, Stoke Bardolph

Approved Planning 2 papers

Planning Committee approved this item on Wednesday 18 September 2013. Below is the council's own wording, with the papers it was decided on.

Item49

Resolved

RESOLVED to GRANT PLANNING PERMISSION, subject to the following amended conditions: Conditions 1. The development hereby permitted shall begin not later than three years from the date of this decision. Written confirmation of the date when electricity is first exported to the grid from the wind turbine hereby permitted (First Export Date) shall be submitted to the Local Planning Authority within one month of the date of this taking place. 2. This permission shall endure for a period of 25 years from the first export date (of electricity to the grid), after which the use shall cease, and the turbine, ancillary structures, crane erection and lay down areas shall be removed from the site, and the land restored in accordance with details to be approved in writing under condition 45 below. The site shall be decommissioned in accordance with the details to be approved under condition 45. 3. The development hereby permitted shall be carried out in accordance with the following approved plans except insofar as may be otherwise required by other conditions of this planning permission: Figure 1.3 Rev P5 Detailed Proposed Site Layout Plan (During Construction); Figure 1.4 Rev P1 Detailed Proposed Site Layout Plan (Post Construction); Figure 2.1 R0 Constraints Map (100m to tip); Figure 4.1 Rev P0 Site Entrance Access; Figure 4.2 Rev P3 Road Works Within Compound; Figure 4.3 Rev P1 Road Works Within Compound Near AMP5; Figure 4.4 Rev 0 Typical Widening of Existing Tarmac Site Road; Figure 4.5 Rev 0 Typical Access Track Details New Stone Road; Figure 4.6 Rev P0 Typical Turbine Pile Foundation; Figure 4.8 Rev P0 Indicative 33kV Substation Plan & Elevations; Figure 4.9 Rev 0 Typical Cable Trench Details. 4. The wind turbine shall be of a 3-bladed configuration and not exceed an overall height of 100m measured from ground level to the tips of the turbine blades. The blades of the turbine shall not have a rotor diameter of more than 80m. The hub height of the turbine shall be no more than 60m measured from ground level to the top of the hub. The turbine shall not display any prominent name, logo, symbol, sign or advertisement on any external surface unless otherwise agreed in writing by the Local Planning Authority. The turbine shall not be illuminated and there shall be no permanent illumination on the site, unless otherwise agreed in writing by the Local Planning Authority or required to satisfy any other condition of this planning permission. 5. The 33KV substation to be provided in accordance with figure 4.3 revision P shall have the following maximum dimensions; it shall be no wider than 9m, no longer than 15m and it shall have a ridge height of no more than 6m. 6. The wind turbine and its associated hard standing areas shall be provided in the position indicated in Figure 1.3 Rev P5 subject to a micro siting allowance of 30m as shown on ... view the full minutes text for item 49.
Word for word from the decision Gedling published for this meeting. Source: democracy.gedling.gov.uk

Follow this further

Built from Gedling's papers

What the report saysPro

Report to Planning Committee

Application Number: 2012/1472

Location: Severn Trent Water PLC, Stoke Lane, Stoke Bardolph

NOTE: This map is provided only for purposes of site location and should not be read as an up to date representation of the area around the site. Reproduced with the permission of the Controller of H.M.S.O. Crown Copyright License No. LA 100021248 Unauthorised reproduction infringes Crown copyright and may lead to prosecution of civil proceedings Report to Planning Committee Application Number: 2012/1472

Location: Severn Trent Water Plc, Stoke Lane, Stoke Bardolph, Nottinghamshire

Proposal: Erection of a single wind turbine (rated capacity up to 2.5MW) and other ancillary development.

Applicant: Severn Trent Water Limited

Agent: [name removed]

1.0The Proposed Development

1.1Full planning permission is sought for the erection of one wind turbine on agricultural land to the east of the existing Severn Trent sewage treatment works. The applicant has advised that the turbine would be operational for 25 years.

1.2Access to the site would be gained off Stoke Lane and through the existing Severn Trent sewage treatment works. The junction access from Stoke Lane into the Severn Trent site would need to be upgraded as part of the proposed development. Alterations would be required to provide the access road from the Severn Trent site to the site of the wind turbine (approximately 500m to the north east of the treatment works). Vegetation including a number of trees would have to be removed in order to create the new access track.

1.3A 33kv electricity substation is proposed to the north of the existing track that forms the northern boundary of the built up element of the sewage treatment works. The substation would measure at its maximum 15m x 9m, with an eaves height of 3m and a ridge height of 6m.

1.4The proposed turbine would have a maximum hub height of 60m and a rotor diameter of 80m giving a maximum tip height of 100m. The turbine would have three blades, each 40m in length. The turbine would have a concrete foundation measuring approximately 18m x 18m and would extend to a depth of 3m below ground level. A temporary site compound and a crane erection area and component lay down area would be constructed adjacent to the site of the proposed wind turbine.

1.5The site compound would provide temporary cabin structures to be used as a site office and parking would also be provided within the area. The site compound, the component lay down area and the crane erection area would be surfaced with a geo-textile mat with crushed stone laid on top. The construction compound is proposed to be removed upon the completion of the development. The lay down area and the crane hard standing area would be retained and utilised during decommissioning. These areas would be covered in soil and reseeded during the operational phase of the turbine.

1.6Cabling would need to be laid down to connect the turbine to the proposed electricity substation, although the exact route has not been confirmed it is anticipated that the cabling would be buried within or to the side of the access track.

1.7The proposed development would comprise three distinct phases; phase 1 would be the construction phase; phase 2 would be the operational phase and phase 3 would be the decommissioning phase. It is anticipated that the construction phase would last for approximately 4 months. Construction would involve enabling works such as site preparation, upgrading of junctions to create the access, construction of accesses and the site compound, crane erection and component lay down areas. The main construction works would involve constructing the turbine foundations, electricity substation, laying cables, erecting the turbine and undertaking restoration works to remove the site compound, crane erection and component lay down areas.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 198 KB Download
PDF
Application No. 2012/1472- Severn Trent Water PLC, Stoke BardolphReport 479 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 24 attended
JT
Councillor John TruscottChair, present
BM
Councillor Barbara MillerVice-Chair, present
PA
Councillor Pauline AllanCommittee Member, present
RA
Councillor Roy AllanCommittee Member, present
PB
Councillor Peter BarnesCommittee Member, present
CB
Councillor Chris BarnfatherCommittee Member, present
DB
Councillor Denis Beeston MBECommittee Member, present
AB
Councillor Alan BexonCommittee Member, present
JB
Councillor John BootCommittee Member, apologies
BC
Councillor Bob CollisCommittee Member, present
AE
Councillor Andrew EllwoodCommittee Member, present
CH
Councillor Cheryl HewlettCommittee Member, present

All 24 on the meeting page

More from Gedling Planning Committee

All decisions
MeetingDecisionOutcome
14 Oct 2026 To approve, as a correct record, the minutes of the meeting held on 9 September 2026That the minutes of the above meeting, having been circulated, be approved as a correct record. Approved Open
14 Oct 2026 Application no. 2026/0501 - Richard Herrod Centre, Foxhill Road Central, Carlton, NottinghamshireTo Grant Planning Permission: Subject to the conditions listed for the reasons set out in the report. Conditions The ... Approved Open
14 Oct 2026 Appeal Summary Ref: 6014560 - 31 Mansfield Road, Daybrook, NottinghamshireTo note the information. Noted Open
14 Oct 2026 Appeal Summary Ref: 6013777 - 6 Pateley Road, Woodthorpe, NottinghamshireTo note the information. Noted Open
14 Oct 2026 Future planning applicationsTo note the information. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies