Resolved
To endorse and refer onto Council for approval an addition to the capital programme for the works to Gedling Country Park as described in the report, for the Stage 1 work, for the amount of £270,100 financed by S106 Contributions.
Cabinet approved this item on Thursday 19 December 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
To endorse and refer onto Council for approval an addition to the capital programme for the works to Gedling Country Park as described in the report, for the Stage 1 work, for the amount of £270,100 financed by S106 Contributions.
Borough-wide
Purpose
1 To endorse and refer onto council for approval, an addition to the capital programme for the Stage 1 works to Gedling Country Park.
Key Decision
2 This is a key decision.
3 The Creation of a Country Park on the former Gedling Colliery site has long been an ambition of the Council, and on 12 September 2013, following the signing of a lease, its creation, via a program of staged works, was approved by Cabinet.
The 2013/14 Capital Programme for the Country Park currently provides for the initial site acquisition costs and due diligence works estimated at £250,000 of which .£216,300 is committed.
The next Stages in the creation of the Country Park are outlined below:
Stage 1 consists of remediation work on the site’s drainage system, and works to ensure the site is safe for access by members of the public. It will additionally include path construction and fence erection. These works are expected to be completed by March – June 2014.
Stage 2 will involve the construction of new access road off Spring Lane onto the site and a car parking facility. This work is programmed to be undertaken between April and June 2014.
Stage 3 will involve the provision of a large children’s play area next to the Spring Lane Car Park to be installed in autumn/winter 2014.
Addition to the Capital Programme of Works to the Country Park
4 Following Portfolio Holder approval tenders were invited from companies on the
Further information on the subject of this report is available from Melvyn Cryer Parks and Street Care Manager on (0115) 901 3788 approved select tender list for the Stage 1 works and the selected bid (which is yet to be approved) is in the amount of £933,799.27. It is intended that Stage 1 works will be completed under a joint contract with Gedling Homes who are making £630,000 of Public Realms monies available for the scheme which they will spend directly.
As the current Gedling Capital Programme does not fully provide for the remainder of Stage 1 works , this report seeks approval for an addition to the Capital Programme..
5 The Council could choose not to progress implementation of the Country Park. However, given that it is a local priority and that the Council has invested a significant amount of time and money in securing the land, that option is not recommended.
6 The financial implications of the proposal are summarised in the tables below:
Current Budget Position £
Current Approved Capital Programme Gedling Country Park 250,000 2013/14 (financed by Growth Point Grant)
Less Expenditure Committed to Initial Project Phase (Site/Surveys) (216,300)
Approved Budget Remaining for Phase 1 Works 33,700
Proposed Addition to Gedling Country Park Capital Budget £
Estimated Phase 1 Works Per Tender 933,800
Less Gedling Homes Public Realms Works (630,000)
Gedling Borough Council Budget Requirement Phase 1 303,800
Less Current Approved Budget Remaining (see table above) (33,700)
Additional Capital Budget Approval Required for Phase 1 270,100
To be financed by:
S106 Contribution Mapperley Plains 39,400
S106 Contribution Spring Lane (note total contribution of £249,700: £230,700 Phase 1 Works; £19,000 available for Phase 2 which will be subject of future report when other funding is secured) 230,700
Total Financing 270,100 Future Funding/Expenditure
The delivery of Stages 2 and 3 will be subject to additional resources being identified and to a future report identifying what is to be developed and requesting approval of budget. It is expected that there will be further Section106 money available from Spring Lane developments over the next few years to fund future maintenance costs on the site.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 2.1 MB | Download |
PDF |
Gedling Country Park: Variation to Capital ProgrammeReport | 133 KB | DownloadRead as text |
Follow Cabinet at Gedling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | To approve, as a correct record, the minutes of the meeting held on 25.06.26.That the minutes of the above meeting, having been circulated, be approved as a correct record. | Approved | Open |
| 16 Jul 2026 | Forward Plan1) To note the report. | Noted | Open |
| 16 Jul 2026 | Housing Strategy 2026-2030That Cabinet: 1) Noted the representations and comments received during the public consultation, together with the of... | Noted | Open |
| 16 Jul 2026 | Gedling BC Asset Management Plan 2026-2028THAT Cabinet: 1) Agreed to adopt the Asset Management Strategy 2026-2028 at appendix 1. 2) Approved the proposals for... | Agreed | Open |
| 16 Jul 2026 | Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.