Resolved
To note the report.
Cabinet noted this item on Thursday 24 April 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
To note the report.
Arnold St Mary’s
Purpose
To inform Cabinet that the additional expenditure of £74,709 in respect of the above project has been committed in breach of the Council’s financial regulations.
Key Decision
This is not a key decision.
The site of the former Druids Tavern Public House was purchased by the council with the intention of constructing a car park on the site.
The cost of the construction was estimated at £250,000 prior to any site surveys or design having been carried out and a capital budget was approved for this amount.
It was proposed that the cost of the scheme was to be fully funded through Growth Point funding. Pre Contract Expenditure
Expenditure acquired prior to the tender process is detailed below.
Surveys and additional plans £2,345.00
Planning fees £487.00
Highway fees £1,000.00
Fees for purchase of land £906.00
Total £4,738.00
Tendered Price
The works were tendered in November 2013 and Whitehouse construction submitted the lowest bid of £249,014.15. Negotiations with the Contractor resulted in the use of alternative suppliers for some of the materials at the same contract specification and a £10,000.00 reduction in price was agreed.
The only additional works that were known about at the time of tendering were surfacing works to the Apollo works adjacent to the site as part of a land swap deal we were still arranging at the time the tender was being advertised. These costs were estimated at £15,000.
This gave a total expected cost of £258,746.15.
At this stage in the project the known variations in total expenditure was predicted to be above the available budget, the variation in the contract price was within the 5% allowance or £5,000 allowed in Financial Regulations (4.67). However, this variation should have been reported to the Executive.
Project Plan
The site was to be developed in six phases;
Phase 1 The boundary wall,
Phase 2 The rear half of the site excavation and civil works,
Phase 3 The front half of the site excavation and civil works,
Phase 4 Electricals, surfacing and off site works,
Phase 5 Entrance and landscaping, Phase 6 Final fit.
Additional Expenditure
The majority of the additional costs are associated with the following areas of work;-
1. In December 2013 additional power supply costs were identified at £1,625.84, however this was to be offset by a saving that had been identified in the main contract in respect of the construction of a brick wall surrounding the car park.
2. Additional costs were then identified for the extra depth of excavation and back fill required.
The surfacing was designed using information from a ground condition survey, unfortunately some areas of the site were overgrown and not accessible at the time the surveys were completed.
When the excavation began in phase 2 it became apparent that rather than the 300mm of unsuitable material expected requiring excavation some parts of the site required up to 1m of unsuitable material to be removed giving an average extra depth of excavation and backfill of 280mm.
The clearance of the site also revealed that in some areas the topsoil was contaminated and needed to be riddled to remove the contamination and keep disposal costs as low as possible.
It was hoped that the additional costs incurred could be recouped through changes to the specification and through better ground conditions in Phase 3 which was completed more recently.
The excavation in Phase 3 while not adding to the additional cost did not give the opportunity to reduce costs either.
Additional cost of £27,349.35.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Druids Tavern Car Park Breach of Financial RegulationsReport | 45 KB | DownloadRead as text |
Follow Cabinet at Gedling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | To approve, as a correct record, the minutes of the meeting held on 25.06.26.That the minutes of the above meeting, having been circulated, be approved as a correct record. | Approved | Open |
| 16 Jul 2026 | Forward Plan1) To note the report. | Noted | Open |
| 16 Jul 2026 | Housing Strategy 2026-2030That Cabinet: 1) Noted the representations and comments received during the public consultation, together with the of... | Noted | Open |
| 16 Jul 2026 | Gedling BC Asset Management Plan 2026-2028THAT Cabinet: 1) Agreed to adopt the Asset Management Strategy 2026-2028 at appendix 1. 2) Approved the proposals for... | Agreed | Open |
| 16 Jul 2026 | Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.